| 2018-04-19 19:07:41 | 04/19/2018 1ST PLUMBING REVIEW**DENIED** |
| | |
| | 1) VALUE OF JOB CLAIM SEEMS TOO LOW. PROVIDE SIGNED |
| | BONA FIDE CONTRACT OF TOTAL JOB COST .FOR PERMITTING |
| | PURPOSES, VALUATION OF BUILDINGS AND SYSTEMS SHALL |
| | BE TOTAL REPLACEMENT VALUE TO INCLUDE STRUCTURAL, |
| | ELECTRIC, PLUMBING, MECHANICAL, INTERIOR FINISH, |
| | RELATIVE SITE WORK, ARCHITECTURAL AND DESIGN FEES, |
| | MARKETING COSTS, OVERHEAD AND PROFIT; EXCLUDING |
| | ONLY LAND VALUE. VALUATION REFERENCES MAY INCLUDE THE |
| | LATEST PUBLISHED DATA OF NATIONAL |
| | CONSTRUCTION COST ANALYSIS SERVICES (MARSHALL-SWIFT, |
| | MEANS, ETC.), AS PUBLISHED BY INTERNATIONAL |
| | CODE CONGRESS. FINAL BUILDING PERMIT VALUATION SHALL BE |
| | SET BY THE BUILDING OFFICIAL.WPB AMEND TO THE 2017 6TH |
| | ED OF THE FBC 109.3 |
| | |
| | 2) AS OF 12/31/2017 THE CODE IN AFFECT IS THE 2017 6TH |
| | ED OF THE FBC. PLEASE REVISE YOUR PLANS TO REFLECT THIS |
| | |
| | 3) SHOW PIPE SIZING BASE ON (TDH) TOTAL DYNAMIC HEAD AS |
| | YOU CAN NO LONGER BASE FLOW OFF THE PUMP CURVE. ANSI/ |
| | APSP/ ICC 3 AND 7 |
| | |
| | 4) PLAN SHOWS POOL TO HAVE AN AUTO. PLEASE ADD NOTE |
| | THAT 2 BACKFLOWS WILL BE REQUIRED. 1 RPZ AT THE CITY |
| | METER PER THE WPB CROSS CONNECTION MANUAL ORD #2853-95 |
| | AND 1 PVC AT THE POINT OF CONNECTION TO THE HOUSE |
| | SUPPLY SYSTEM. FBC-P 608.16 |
| | |
| | TIM HUNT |
| | PLUMBING INSPECTOR / PLUMBING PLAN REVIEWER |
| | CITY OF WEST PALM BEACH DEVELOPMENT SERVICES DEPARTMENT |
| | BUILDING DIVISION |
| | 561-805-6695 |
| | [email protected] |
| | |