Text |
| 2018-03-29 11:37:39 | THIS PLAN WAS REVIEWED AND FAILED BY PETER LEDUC, FIRE |
| | MARSHAL, WITH THE FOLLOWING COMMENTS: |
| | |
| | |
| | 1) SHEET 11 OF 16 & 12 OF 16 - THERE APPEARS TO BE ONE |
| | (1) FIRE LINE WATER SUPPLY LEADING TO EACH HIGH RISE'S |
| | FIRE PUMPS. |
| | |
| | PER NFPA 101 AND THE FLORIDA BUILDING CODE 2 SEPARATE |
| | WATER SUPPLIES ARE REQUIRED FOR EACH RIE PUMP. |
| | |
| | 2014 NFPA 101 CHAPTER 11. |
| | |
| | 11.1.6 MINIMUM CONSTRUCTION REQUIREMENTS. MINIMUM |
| | CONSTRUCTION REQUIREMENTS SHALL BE IN ACCORDANCE WITH |
| | THE APPLICABLE |
| | OCCUPANCY CHAPTER AND WITH THE FLORIDA BUILDING CODE. |
| | |
| | 2014 FLORIDA BUIL;DING CODE: |
| | |
| | [F] 403.3.2 WATER SUPPLY TO REQUIRED FIRE PUMPS. |
| | REQUIRED FIRE PUMPS SHALL BE SUPPLIED BY CONNECTIONS TO |
| | NO FEWER THAN TWO WATER MAINS LOCATED IN DIFFERENT |
| | STREETS. SEPARATE SUPPLY PIPING SHALL BE PROVIDED |
| | BETWEEN EACH CONNECTION TO THE WATER MAIN AND THE |
| | PUMPS. EACH CONNECTION AND THE SUPPLY PIPING BETWEEN |
| | THE CONNECTION AND THE PUMPS SHALL BE SIZED TO SUPPLY |
| | THE FLOW AND PRESSURE REQUIRED FOR THE PUMPS TO |
| | OPERATE. |
| | |
| | EXCEPTION: TWO CONNECTIONS TO THE SAME MAIN SHALL BE |
| | PERMITTED PROVIDED THE MAIN IS VALVED SUCH THAT AN |
| | INTERRUPTION CAN BE ISOLATED SO THAT THE WATER SUPPLY |
| | WILL CONTINUE WITHOUT INTERRUPTION THROUGH NO FEWER |
| | THAN ONE OF THE CONNECTIONS. |
| | |
| | |
| | PLEASE REVIEW AND CORRECT OR JUSTIFY. |
| | |
| | |
| | 2) WHEN RESUBMITTING, PLEASE PROVIDE PLAN SHEET |
| | REVISION CLOUDS OR NUMBERED NARRATIVE RESPONSES TO THE |
| | ABOVE. |
| | |
| | |
| | 3) ADDITIONAL COMMENTS MAY BE PROVIDED ON THE |
| | RE-SUBMITTAL OF THE ABOVE. |
| | |
| | |
| | PETER LEDUC |
| | FIRE MARSHAL |
| | 561-804-4709 |
| | [email protected] |
| | |