| 2018-03-19 12:04:32 | 1ST REVIEW FBC-2017 MECHANICAL , ENERGY CONSERVATION |
| | CODES, WEST PALM BEACH AMENDMENTS TO THE FBC-17 |
| | PERMIT #18030386 |
| | 3/19/18 |
| | |
| | PLAN REVIEW RESULTS: DENIED. |
| | |
| | 1) M-2.0: THE AIR BALANCE SCHEDULE DOES NOT PROVIDE |
| | CALCULATIONS FOR THE REQUIRED REPLACEMENT AIR FOR THE |
| | KITCHEN EXHAUST SYSTEMS- SEE SECTION 508.1.2. |
| | |
| | 2) PLEASE SHOW COMPLIANCE WITH SECTION 508.1.1 MAKEUP |
| | AIR TEMPERATURE- FBC-17 MECHANICAL, AND SECTION |
| | C403.2.8 FBC-17 ENERGY CONSERVATION. |
| | |
| | 508.1.1 MAKEUP AIR TEMPERATURE. |
| | THE TEMPERATURE DIFFERENTIAL BETWEEN MAKEUP AIR AND THE |
| | AIR IN THE CONDITIONED SPACE SHALL NOT EXCEED 10 |
| | DEGREES F (6 DEGREES C) EXCEPT WHERE THE ADDED HEATING |
| | AND COOLING LOADS OF THE MAKEUP AIR DO NOT EXCEED THE |
| | CAPACITY OF THE HVAC SYSTEM. |
| | |
| | C403.2.8 KITCHEN EXHAUST SYSTEMS. |
| | REPLACEMENT AIR INTRODUCED DIRECTLY INTO THE EXHAUST |
| | HOOD CAVITY SHALL NOT BE GREATER THAN 10 PERCENT OF THE |
| | HOOD EXHAUST AIRFLOW RATE. CONDITIONED SUPPLY AIR |
| | DELIVERED TO ANY SPACE SHALL NOT EXCEED THE GREATER OF |
| | THE FOLLOWING: |
| | 1.THE VENTILATION RATE REQUIRED TO MEET THE SPACE |
| | HEATING OR COOLING LOAD. |
| | 2.THE HOOD EXHAUST FLOW MINUS THE AVAILABLE TRANSFER |
| | AIR FROM ADJACENT SPACE WHERE AVAILABLE TRANSFER AIR IS |
| | CONSIDERED THAT PORTION OF OUTDOOR VENTILATION AIR NOT |
| | REQUIRED TO SATISFY OTHER EXHAUST NEEDS, SUCH AS |
| | RESTROOMS, AND NOT REQUIRED TO MAINTAIN PRESSURIZATION |
| | OF ADJACENT SPACES. |
| | |
| | 3) M-3.0: PLEASE IDENTIFY ALL THE COOKING APPLIANCES |
| | SHOWN IN THE HOOD 2 ELEVATION VIEW. CLARIFY IF THE |
| | HOODS ARE TO BE PERMITTED ASTYPE1 GREASE HOODS, OR TYPE |
| | II HEAT HOODS- SEE SECTION 507.1. |
| | |
| | 4) M-3.0: PLEASE SHOW THE ENTIRE EXHAUST DUCT RUNS FOR |
| | HOODS 1 & 2 FROM HOOD OUTLET TO ROOF TERMINATION. |
| | INDICATE THE TYPE AND SIZES OF EXHAUST DUCTWORK. |
| | |
| | 5) PROVIDE A ROOF PLAN SHOWING THE LOCATIONS OF THE |
| | EXHAUST FANS AND THE REQUIRED MINIMUM CLEARANCES FROM |
| | EXHAUST OUTLETS TO MECHANICAL OR GRAVITY AIR INTAKES. |
| | PLEASE INCLUDE AN ELEVATION VIEW WHICH SHOWS THE HEIGHT |
| | OF THE EXHAUST OUTLETS ABOVE THE FINISH ROOF, |
| | |
| | 6) PROVIDE COMPLETE WINDLOAD ENGINEERING FOR |
| | INSTALLATION OF THE ROOF EXHAUST FANS INCLUDING THE |
| | STRUCTURAL ROOF OPENING, THE CURB ATTACHMENT TO THE |
| | STRUCTURE, AND THE RTU ATTACHMENT TO THE CURB- SECTION |
| | 301.15 |
| | |
| | WHEN RESUBMITTING, IT IS HELPFUL TO PROVIDE A RESPONSE |
| | LETTER ADDRESSING EACH ITEM ALONG WITH THE CITY |
| | RE-SUBMITTAL FORM. ADDITIONALLY, PLEASE INSERT |
| | CORRECTED PLAN SHEETS INTO THE SETS, REMOVE THE |
| | PREVIOUSLY REVIEWED SHEETS AND MARK VOID ON THEM, AND |
| | KEEP THEM WITH THE SUBMITTALS. |
| | |
| | CHRISTOPHER L. COLE |
| | MECHANICAL PLANS EXAMINER |