| Date |
Text |
| 2018-03-12 14:11:38 | 03/12/2018 GAS 1ST REVIEW**DENIED** |
| | |
| | NOTE - A COMPREHENSIVE REVIEW COULD NOT BE DONE AT THIS |
| | TIME AND ADDITIONAL PLAN REVIEW COMMENTS MAY BE |
| | GENERATED UPON THE RE-REVIEW OF SUBMITTED CORRECTIONS. |
| | |
| | |
| | 1) VALUE**THE VALVE OF JOB MUST INCLUDE TOTAL COST OF |
| | ALL MATERIAL INCLUDING TANKLESS.109.3 BUILDING PERMIT |
| | VALUATIONS. |
| | IF, IN THE OPINION OF THE BUILDING OFFICIAL, THE |
| | CLAIMED VALUATION OF |
| | BUILDING, ALTERATION, STRUCTURE, ELECTRICAL, GAS, |
| | MECHANICAL OR PLUMBING SYSTEMS APPEARS TO BE |
| | UNDERESTIMATED ON THE APPLICATION, THE PERMIT SHALL BE |
| | DENIED, UNLESS THE APPLICANT CAN SHOW |
| | DETAILED, QUANTITY ESTIMATES, AND/OR BONA FIDE SIGNED |
| | CONTRACTS (EXCLUDING LAND VALUE) TO MEET THE |
| | APPROVAL OF THE BUILDING OFFICIAL. FOR PERMITTING |
| | PURPOSES, VALUATION OF BUILDINGS AND SYSTEMS SHALL |
| | BE TOTAL REPLACEMENT VALUE TO INCLUDE STRUCTURAL, |
| | ELECTRIC, PLUMBING, MECHANICAL, INTERIOR FINISH, |
| | RELATIVE SITE WORK, ARCHITECTURAL AND DESIGN FEES, |
| | MARKETING COSTS, OVERHEAD AND PROFIT; EXCLUDING |
| | ONLY LAND VALUE. VALUATION REFERENCES MAY INCLUDE THE |
| | LATEST PUBLISHED DATA OF NATIONAL CONSTRUCTION |
| | COST ANALYSIS SERVICES (MARSHALL-SWIFT, MEANS, ETC.), |
| | AS PUBLISHED BY INTERNATIONAL CODE CONGRESS. |
| | FINAL BUILDING PERMIT VALUATION SHALL BE SET BY THE |
| | BUILDING OFFICIAL. |
| | |
| | 2) FLOOR PLAN PROVIDED MUST INCLUDE MEASURMENT FROM |
| | INSIDE CORNER AND OUTSIDE CORNER. FBC 107.2.1 |
| | |
| | 3) SHOW THE TYPE OF PIPE MATERIAL BEING INSTALLED, ALL |
| | PIPE SIZES, AND THE CORRESPONDING EHD NUMBER OF THE |
| | CORRUGATED STAINLESS STEEL TUBING |
| | |
| | (IF APPLICABLE) FOR EACH PIPE SIZE. WPB AMENDMENTS TO |
| | FBC SEC.107.2.1 |
| | |
| | 4) TYPE OF GAS (LP OR NATURAL). FBC 107.2.1 |
| | |
| | 5) SUBMIT MANUFACTURER?S SPECIFICATION SHEETS / |
| | INSTALLATION MANUAL FOR ALL GAS EQUIPMENT TO VERIFY |
| | COMPLIANCE WITH STANDARDS NFPA 54, NFPA 58, AND |
| | FBC-2014 FUEL GAS CODE SEC. 402.2, AND 301.3 OR 2014 |
| | FBC-RES. SEC. G2404.3. GAS APPLIANCES SHALL BE LISTED |
| | AND LABELED. THE INSTALLATION MANUALS FOR ALL GAS |
| | APPLIANCES / EQUIPMENT SHALL BE ONSITE AT THE TIME OF |
| | INSPECTION. FGC SEC.305.1, FBC-RES. SEC.G2408.1. |
| | |
| | 6) ) SUBMIT TWO COPIES OF THE APPLICABLE SIZING TABLES |
| | USED TO SIZE THE GAS SYSTEM OR PLACE A NOTE ON THE |
| | PLANS/DRAWINGS SPECIFYING WHICH SIZING TABLE(S) FROM |
| | THE GAS CODE OR OTHER STANDARD THAT WERE USED IN THE |
| | DESIGN OF THIS GAS SYSTEM. REFER TO THE 2014 FBC-FUEL |
| | GAS SECS. 401.4, 401.8 THRU 402.6.1 AND TABLES 402.4 |
| | (1) THRU 402.4 (37) OR 2014 FBC-RES. SEC. G2412.4, |
| | G2412.8, G2413.1, G2413.2, & G2413.3. |
| | |
| | 7) ) THE PLANS INDICATE AN EXISTING GAS METER. THE LINE |
| | 1" AT THE POOL HEATER IS UNDERSIZED ONWITH THE ADDING |
| | OF THE TANKLESS HEATER.THE BTU LOAD OF THE EXISTING GAS |
| | SYSTEM MUST BE ADDED INTO THE TOTAL BTU LOAD ON THE |
| | SYSTEM TO ENSURE THE EXISTING SYSTEM IS PROPERLY SIZED. |
| | IF UNDERSIZED, THE EXISTING SYSTEM MUST BE REDONE TO |
| | ENSURE A SAFE OPERATING SYSTEM. SUBMIT A GAS PIPING |
| | RISER DIAGRAM THAT SHOWS THE TYPE OF EXISTING |
| | APPLIANCE, THE BTU LOAD OF EACH APPLIANCE, THE PIPE |
| | SIZE AND TYPE OF PIPE TO EACH APPLIANCE, AND THE |
| | DISTANCE OF THE LONGEST LENGTH OF PIPING FROM THE POINT |
| | OF DELIVERY TO THE MOST REMOTE OUTLET AND THE LOAD OF |
| | THE SECTION. NOTE: IF THE EXISTING SYSTEM IS LESS THAN |
| | A 2 PSI SYSTEM AND THE SYSTEM PRESSURE IS INCREASED TO |
| | 2 PSI, A LINE PRESSURE REGULATOR IS REQUIRED AT ALL THE |
| | EXISTING APPLIANCES. FGC SECS. 401.4, 401.8, 402.1, |
| | 402.2, 402.3 OR FBCR SECS.G2412.4, G2412.8, G2413.1, |
| | G2413.2, G2413.3. |
| | |
| | |
| | |
| | |
| | TIM HUNT |
| | PLUMBING INSPECTOR / PLUMBING PLAN REVIEWER |
| | CITY OF WEST PALM BEACH DEVELOPMENT SERVICES DEPARTMENT |
| | BUILDING DIVISION |
| | 561-805-6695 |
| | [email protected] |
| | |