| Plan Review Notes For Permit 18030092 |
| Permit Number |
18030092 |
|
| Review Stop |
B |
| Sequence Number |
1 |
|
| Notes |
| Date |
Text |
| 2018-03-07 07:49:56 | THE FOLLOWING NEEDED FOR ISSUANCE; | | | | | | 1) A TURN-A-ROUND PERMIT TO CAP THE SEWER LATERAL WILL | | | NEED TO BE PULLED. WHEN THE SEWER LATERAL CAP IS | | | COMPLETED, REQUEST A FINAL PLUMBING #703 ON THAT PERMIT | | | NUMBER. THAT INSPECTION WILL NEED TO BE PASSED PRIOR TO | | | ISSUANCE OF THE DEMO PERMIT. | | | | | | 2) HISTORIC AND ENGINEERING'S PLAN REVIEWS PASSED. I AM | | | MOVING THE APPLICATION ON TO ENGINEERING'S MAILBOX. | | | | | | 3) DEMO WILL NEED TO BE KEPT WET AND DUST MINIMIZED. | | | EITHER A HYDRANT METER ACQUIRED FROM THE WATER | | | DEPARTMENT, A BACKFLOW PREVENTER INSTALLED ON SITE, OR | | | PROVIDE A LETTER DESCRIBING AND TAKING RESPONSIBILITY | | | FOR KEEPING THE DEMO WET. | | | | | | ANY QUESTIONS FEEL FREE TO CALL. TOM @ 561-805-6669 | | | | | | | | | |
|