| 2018-02-28 17:47:04 | 02/28/2018 1ST PLUMBING REVIEW**DENIED** |
| | |
| | |
| | A STOP WORK ORDER WAS ISSUED ON 01/17/2018 DURING THE |
| | DEMO OF THE BATH TUB. BOTH OWNER AND PLUMBERS ON-SITE |
| | HAD BEEN ADVISED TO CEASE ALL WORK UNTIL PERMIT WAS |
| | ISSUED AND APPROVED INSPECTIONS HELD. THIS WAS IGNORED |
| | AND THE JOB WAS FOUND TO BE COMPLETED DURING A STATUS |
| | CHECK OF THE STOP WORK ORDER THAT WAS PERFORMED ON |
| | 02/22/2018 COMFIRMED BY THE OWNER.1 OF THE FOLLOWING 2 |
| | OPTIONS BELOW MUST HAPPEN IN ORDER FOR THIS PERMIT TO |
| | BE ISSUED BY 03/12/2018 OR THE VIOLATION WILL BE |
| | FORWARDED TO THE SPECIAL MAGISTRATE FOR A HEARING. |
| | |
| | 1) THE REMOVAL OF ALL MATERIALS DOWN TO THE BARE WALLS |
| | SAME AS WHICH THE INSPECTOR ISSUED THE STOP WORK ORDER. |
| | |
| | 2) A SIGN LETTER FROM YOU ( GEORGE BEYS) ACKNOWLEDGING |
| | THE WORK HAS BEEN PERFORMED WITH OUT PERMITS AND |
| | BENEFIT OF CITY OF WEST PALM BEACH INSPECTION AS |
| | REQUIRED BY THE FLORIDA BUILDING CODE AND TAKING FULL |
| | RESPONSIBILITY OF THE ENTIRE INSTALL OF ALL COMPONENTS |
| | OF THIS REMODEL. A SIGED LETTER FROM THE OWNER (MR. |
| | ROSE) ACKNOWLEDGE HE IS AWARE OF THE CURRENT EVENTS AND |
| | ACCEPTS THIS COURSE OF ACTION. A MIN OF 2 HOLES CUT |
| | INTO THE DRYWALL IN LOCATIONS OF THE INSPECTORS CHOICE |
| | TO ALLOW SOME INSPECTION TO BE PERFORMED. 2- COPIES WET |
| | SIGNED FROM EACH |
| | |
| | MUST COMPLY WITH 1 OF THE 2 BY 03/12/2018 OR THE |
| | VIOLATION WILL BE FORWARDED TO THE SPECIAL MAGISTRATE |
| | FOR A HEARING |
| | |
| | |
| | TIM HUNT |
| | PLUMBING INSPECTOR / PLUMBING PLAN REVIEWER |
| | CITY OF WEST PALM BEACH DEVELOPMENT SERVICES DEPARTMENT |
| | BUILDING DIVISION |
| | 561-805-6695 |
| | [email protected] |
| | |