| 2018-05-08 16:31:34 | CODES IN EFFECT: |
| | FBC = FLORIDA BUILDING CODE 2017 6TH EDITION |
| | FBC EC = FLORIDA BUILDING CODE ENERGY CONSERVATION 2017 |
| | 6TH EDITION |
| | FBC RE = FLORIDA RESIDENTIAL CODE 2017 6TH EDITION |
| | NEC = NFPA 70 2014 EDITION, NATIONAL ELECTRICAL CODE |
| | FS = FLORIDA STATUTES |
| | |
| | ELECTRICAL REVIEW STATUS: DENIED, SEE COMMENTS BELOW. |
| | |
| | THESE ITEMS HAVE BEEN DISCUSSED WITH ENGINEER AT |
| | MEETING ON 5-7-18. |
| | |
| | PREVIOUS COMMENTS THAT HAVE BEEN ADDRESSED |
| | SATISFACTORILY ARE MARKED AS CORRECTED. PREVIOUS |
| | COMMENTS THAT HAVE NOT BEEN ADDRESSED SATISFACTORILY |
| | HAVE ADDITIONAL COMMENTS IN PARENTHESES. ANY NEW |
| | COMMENTS WILL BE LISTED AFTER PREVIOUS COMMENTS. |
| | |
| | 1. CORRECTED. |
| | 2. CORRECTED. |
| | 3. RISER DIAGRAM SHOWS 3 MAINS. IT APPEARS MAIN # 1 AND |
| | 2 ARE LOCATED IN MDB AND MAIN # 3 IS IN A SEPARATE |
| | LOCATION. SHOULD MDB BE LABELED MDP? THERE IS A NOTE |
| | THAT THIS EQUIPMENT IS RATED FOR 12000 AMPS, PROVIDE |
| | CLARIFICATION AND/OR CORRECTION. PROVIDE PANEL SCHEDULE |
| | FOR THIS PANEL. ALSO, I DO NOT SEE MAIN # 3 IN THE |
| | ELECTRICAL ROOM (ROOM 127). PROVIDE CLARIFICATION AND |
| | NAMES FOR EACH MAIN. WHAT IS THE RATING OF MAIN #1? |
| | ALSO, FOR PANEL ?MDB?, THERE APPEARS TO ONLY BE 17? |
| | CLEARANCE FOR THIS? PROVIDE CORRECTIONS AND/OR |
| | CLARIFICATIONS AS NEEDED. FBC 107.2.1; NEC 110.26, |
| | 695.3 (SOME ITEMS CORRECTED. BASED ON NEW RISER |
| | DIAGRAM, THERE WOULD BE 4 SERVICES TO THIS BUILDING. |
| | THERE IS A 2000 AMP SERVICE AT MDP, A 600 AMP SERVICE |
| | SHOWN ON RISER BUT NOT ON POWER PLAN, A SERVICE TO FIRE |
| | PUMP, AND A PROPOSED 200 AMP SERVICE FOR KITCHEN. EACH |
| | SERVICE NEEDS TO BE CLEARLY IDENTIFIED WITH LABELS THAT |
| | STATE WHICH SERVICE IT IS AND THE LOCATION OF OTHER |
| | SERVICES ON PROPERTY. EACH MAIN WITHIN EACH SERVICE |
| | SHOULD ALSO BE LABELED ACCORDINGLY. PANEL A ON ROOF IS |
| | SHOWS AS BEING FED FROM THE 600 AMP SERVICE, WHICH ONLY |
| | HAS 198 AMPS DEMAND, SO WHY DOES THE 200 AMP SERVICE |
| | NEED TO BE ADDED? PANEL A IS ALSO BEING SHOWN AS FED |
| | FROM MDP AS AN 800 AMP PANEL INSTEAD OF 600 AMP AND IT |
| | IS INCLUDED IN THE LOAD CALCULATION FOR PANEL MDP, |
| | WHICH IS AN OBVIOUS DISCREPANCY. WHILE ADDITIONAL |
| | SERVICES CAN BE ALLOWED, THERE NEEDS TO BE |
| | JUSTIFICATION. PROVIDE CLARIFICATIONS.)(3RD REVIEW, |
| | PLAN CURRENTLY SHOWS MORE THAN 6 MAINS WHICH VIOLATES |
| | NEC 230.71. ENGINEER IS CONFIRMING THE LAYOUT OF MDP |
| | AND WILL RE-LABEL PLAN WITH ACCURATE COUNT OF MAINS.) |
| | 4. CORRECTED. |
| | 5. CORRECTED. |
| | 6. PROVIDE LOAD CALCULATION FOR SERVICE, INCLUDE |
| | EXISTING AND NEW LOADS TO CONFIRM CAPACITY OF SERVICE |
| | IS ADEQUATE. SOME PANEL SCHEDULE SHOW DEMAND FACTORS |
| | FOR DWELLING UNITS. THE NEC DEFINES A DWELLING UNIT AS: |
| | ?A SINGLE UNIT, PROVIDING COMPLETE AND INDEPENDENT |
| | LIVING FACILITIES FOR ONE OR MORE PERSONS, INCLUDING |
| | PERMANENT PROVISIONS FOR LIVING, SLEEPING, COOKING, AND |
| | SANITATION.? THIS DEFINITION DOES NOT MATCH THIS |
| | FACILITY, SO THESE DEMAND FACTORS SHOULD NOT BE USED. |
| | ALSO, PROVIDE LOAD CALCULATION FOR BUS DUCT. NEC 100, |
| | 215.2, 220, 408.30 (NEED FURTHER EXPLANATION OF LOAD ON |
| | SERVICE. THE FEEDERS AND OVERCURRENT PROTECTION SHOULD |
| | BE SIZED TO HANDLE 100% OF THE NON-CONTINUOUS LOAD PLUS |
| | 125% OF THE CONTINUOUS LOAD. THE ONLY CONTINUOUS LOAD |
| | SHOWN IS FOR LIGHTING, THE LARGEST MOTOR LOAD IS NOT |
| | SHOWN ON ANY SCHEDULES. ADDITIONALLY, THE RISER DIAGRAM |
| | SHOWS A FUTURE POOL, BUT NO LOAD IS INCLUDED FOR THIS. |
| | PROVIDE CORRECTIONS. NEC 215.2, 215.3, 220.14(C), |
| | 430.24)(3RD REVIEW - SOME DATA IS NOT TRANSFERRING |
| | CORRECTLY IN PANEL SCHEDULES. ENGINEER ADVISED THAT THE |
| | PROBLEM WILL BE FIXED AND AN ACCURATE LOAD CALCULATION |
| | PROVIDED.) |
| | 7. CORRECTED. |
| | 8. EXPLANATION PROVIDED FOR CLEARANCE, WILL NEED TO BE |
| | CONFIRMED BY INSPECTOR. |
| | 9. EXPLANATION PROVIDED FOR CLEARANCE, WILL NEED TO BE |
| | CONFIRMED BY INSPECTOR. |
| | 10. EXPLANATION PROVIDED FOR CLEARANCE, WILL NEED TO BE |
| | CONFIRMED BY INSPECTOR. |
| | 11. CORRECTED. |
| | 12. PROVIDE PANEL SCHEDULE FOR EACH PANEL INDICATING |
| | ANY NEW OR ALTERED CIRCUITS, THE WIRE AND BREAKER SIZE |
| | FOR THESE CIRCUITS, AND AFCI OR GFCI PROTECTION WHERE |
| | APPLICABLE TO COMPLY WITH CODE. IT APPEARS THAT SOME |
| | SCHEDULES ARE MISSING AND SOME HAVE INFORMATION THAT IS |
| | TBD. PROVIDE COMPLETED SCHEDULES. PANEL SCHEDULES |
| | SHOULD INCLUDE UNIQUE IDENTIFIERS FOR CIRCUITS, SUCH AS |
| | ROOM NUMBERS OR LOCATIONS. GENERAL TERMS ARE NOT |
| | ACCEPTABLE. NEC 210.8, 210.12, 215.5, 408.4 (SOME |
| | PANELS STILL DO NOT HAVE CLEAR LOCATIONS FOR EQUIPMENT |
| | THAT IS USED IN MORE THAN ONE LOCATION. PROVIDE |
| | CORRECTION.) |
| | 13. THE FOLLOWING PANELS ARE SHOWN WITH A 125 MAIN |
| | CIRCUIT BREAKER, BUT HAVE A LOAD THAT EXCEEDS 125 AMP: |
| | PANEL EML, 4LA, 5LA, 6LA, 7LA, 8LA 9LA, 10LA. PROVIDE |
| | CORRECTION. NEC 215.3 (THERE ARE STILL MANY PANELS THAT |
| | ARE NOT SHOWING THE CORRECT TYPE AND SIZE. PROVIDE |
| | CORRECTIONS.) |
| | 14. CORRECTED. |
| | 15. CORRECTED. |
| | 16. IT APPEARS THE GENERATOR WILL BE OVERLOADED AS |
| | PANEL EMH SHOWS A LOAD OF 330.7 KVA BEFORE CORRECTIONS |
| | NOTED IN COMMENT # 14. PROVIDE CORRECTION. NEC 701.4, |
| | 695.3(D)(1) (3RD REVIEW - THE GENERATOR IS STILL SHOWN |
| | AS OVERLOADED. PROVIDE CORRECTIONS.) |
| | 17. CORRECTED. |
| | 18. CORRECTED. |
| | 19. CORRECTED. |
| | |
| | NEW COMMENTS: |
| | |
| | 20. FIRE PUMP IS BEING SHOWN AS FED FROM MDP IN PANEL |
| | SCHEDULE. PROVIDE CORRECTION. ALSO, DID NOT SEE A LOAD |
| | FOR A JOCKEY PUMP ANYWHERE. WILL THERE BE A PRESSURE |
| | MAINTENANCE PUMP WITH THIS SYSTEM, AND WHERE IS IT FED |
| | FROM? FBC 107.2.1 |
| | 21. DURING MEETING WITH ENGINEER, THE FAULT CURRENT FOR |
| | THE MAINS WAS DISCUSSED. FAULT CALCULATIONS WILL NEED |
| | TO BE PROVIDED FOR ANY MODIFICATIONS OF THE SERVICE |
| | EQUIPMENT SO THAT PROPER SIZING OF EQUIPMENT CAN BE |
| | CONFIRMED, AS WELL AS PROPER LABELING. PROVIDE |
| | AVAILABLE SHORT CIRCUIT CALCULATION FOR EACH PANEL |
| | INCLUDING INFORMATION FROM THE POWER COMPANY STATING |
| | WHAT THE AVAILABLE SHORT CIRCUIT CURRENT IS FOR THE |
| | SERVICE TO CONFIRM THE STATED AIC RATING OF THE SERVICE |
| | EQUIPMENT AND DOWNSTREAM PANELS IS ADEQUATE. IF FPL IS |
| | NOT ABLE TO RESPOND IN A TIMELY FASHION, WE WILL ACCEPT |
| | THIS AS A DEFERRED SUBMITTAL WITH THE UNDERSTANDING |
| | THAT ALL PANELS WILL NEED TO MEET OR EXCEED THE |
| | CALCULATED FAULT CURRENT. NEC 110.9, 110.10 |
| | 22. PROVIDE NOTES TO INDICATE THE REQUIRED MARKING OF |
| | SERVICE EQUIPMENT FOR ARC FLASH HAZARD WARNING AND |
| | AVAILABLE FAULT CURRENT PER CODE. NEC 110.16, 110.24 |
| | |
| | END OF COMMENTS. |
| | |
| | PLEASE NOTE: SUBMITTAL OF ADDITIONAL AND/OR REVISED |
| | MATERIALS MAY RESULT IN NEW PLAN REVIEW COMMENTS. WHEN |
| | RESUBMITTING, IT IS HELPFUL TO PROVIDE A RESPONSE |
| | LETTER ADDRESSING EACH ITEM ALONG WITH THE CITY |
| | RESUBMITTAL FORM. ADDITIONALLY, INSERT CORRECTED PAGES |
| | INTO THE ORIGINAL SUBMITTAL AND REMOVE OR VOID THE |
| | PREVIOUSLY REVIEWED SHEETS. |
| | |
| | SINCERELY, |
| | |
| | JOHN PEARSON |
| | ELECTRICAL PLANS EXAMINER |
| | 561-805-6746 |
| | [email protected] |
| | |
| | |