| 2018-03-19 07:13:11 | 03/19/18 |
| | GAS PLAN REVIEW |
| | |
| | DENIED WITH COMMENTS NOTE - A COMPREHENSIVE REVIEW |
| | COULD NOT BE DONE AT THIS TIME AND ADDITIONAL PLAN |
| | REVIEW COMMENTS MAY BE GENERATED UPON THE RE-REVIEW OF |
| | SUBMITTED CORRECTIONS. |
| | |
| | 1. SUBMIT AN ISOMETRIC DRAWING THAT CLEARLY SHOWS THE |
| | LENGTH OF ALL CUT SECTIONS OF PIPE PER 2017 FBC FUEL |
| | GAS, SECS. 402.4.1, 402.4.2. 14. THE PLANS INDICATE AN |
| | EXISTING GAS METER. THE BTU LOAD OF THE EXISTING GAS |
| | SYSTEM MUST BE ADDED INTO THE TOTAL BTU LOAD ON THE |
| | SYSTEM TO ENSURE THE EXISTING SYSTEM IS PROPERLY SIZED. |
| | IF UNDERSIZED, THE EXISTING SYSTEM MUST BE REDONE TO |
| | ENSURE A SAFE OPERATING SYSTEM. SUBMIT A GAS PIPING |
| | RISER DIAGRAM THAT SHOWS THE TYPE OF EXISTING |
| | APPLIANCE, THE BTU LOAD OF EACH APPLIANCE, THE PIPE |
| | SIZE AND TYPE OF PIPE TO EACH APPLIANCE, AND THE |
| | DISTANCE OF THE LONGEST LENGTH OF PIPING FROM THE POINT |
| | OF DELIVERY TO THE MOST REMOTE OUTLET AND THE LOAD OF |
| | THE SECTION. NOTE: IF THE EXISTING SYSTEM IS LESS THAN |
| | A 2 PSI SYSTEM AND THE SYSTEM PRESSURE IS INCREASED TO |
| | 2 PSI, A LINE PRESSURE REGULATOR IS REQUIRED AT ALL THE |
| | EXISTING APPLIANCES 2017 FBC FUEL GAS SECS. 401.4, |
| | 401.8, 402.1, 402.2, 402.3 |
| | 2. SUBMIT MANUFACTURER'S SPECIFICATIONS FOR THE |
| | PRESSURE REGULATORS. REGULATORS INSTALLED ON THE |
| | EXTERIOR OF THE BUILDING SHALL BE APPROVED FOR OUTDOOR |
| | INSTALLATION. 2017 FBC FUEL GAS SEC.410.1 |
| | 3. 21. GAS RISER DIAGRAM REQUIRED WPB AMENDMENTS TO THE |
| | FBC SEC. 107.5.1.5 (9) COMMERCIAL GAS |
| | 4. LIST THE BTU LOAD OF EACH APPLIANCE AND THE TOTAL |
| | BTU LOAD ON THE SYSTEM. REFER TO THE 2017 FBC FUEL GAS |
| | SECS. 401.8 THROUGH 402.6.1 AND TABLES 402.4 (1) |
| | THROUGH 402.4 (37) |
| | 5. SHOW THE DISTANCE FROM THE POINT OF DELIVERY, (GAS |
| | METER / MP REGULATOR / LP TANK) TO THE MOST REMOTE |
| | OUTLET IN THE BUILDING AND/OR SYSTEM PER THE 2017 FBC |
| | FUEL GAS SEC. 402.4.1 |
| | 6. THE WATER HEATER HAS BEEN MOVED, PLEASE SUBMIT |
| | CALCULATIONS FOR COMBUSTION AIR PER THE 2017 FBC FUEL |
| | GAS SEC. 304.1, 614.5 |
| | 7. INDICATE THE DELIVERY PRESSURE (PSI) OF THE SYSTEM |
| | ON THE PLAN PER 2017 FBC FUEL GAS SEC. 402.2 |
| | 8. SUBMIT A DETAIL SHOWING THE TYPE, LOCATION, SIZE, |
| | TERMINATION POINT, HEIGHT ABOVE THE ROOF AND ANCHORING |
| | DETAILS OF THE GAS VENT(S) PER 2017 FBC FUEL GAS SECS. |
| | 502 THRU 505. |
| | 9. SUBMIT MANUFACTURER'S SPECIFICATION |
| | SHEETS/INSTALLATION MANUAL FOR ALL GAS EQUIPMENT TO |
| | VERIFY COMPLIANCE WITH 2017 FBC FUEL GAS SEC.305.1. |
| | 11. GAS APPLIANCES SHALL BE LISTED AND LABELED. |
| | 10. SUBMIT TWO COPIES OF THE APPLICABLE SIZING TABLES |
| | USED TO SIZE THE GAS SYSTEM OR PLACE A NOTE ON THE |
| | PLANS/DRAWINGS SPECIFYING WHICH SIZING TABLE(S) FROM |
| | THE GAS CODE OR ANOTHER STANDARD THAT WAS USED IN THE |
| | DESIGN OF THIS GAS SYSTEM. REFER TO THE 2017 FBC FUEL |
| | GAS SECS. 401.4, 401.8 THRU 402.6.1 AND TABLES 402.4 |
| | (1) THRU 402.4 (37) |
| | |
| | LUIS A. CRESPO |
| | PLUMBING INSPECTOR / |
| | PLUMBING PLAN REVIEW |
| | [email protected] |
| | 561-805-6720 |
| | |
| | |
| | |