Plan Review Notes For Permit 18010961
Permit Number 18010961
Review Stop G
Sequence Number 1
Notes
Date Text
2018-02-08 05:52:241) SHOW THE DISTANCE OF THE GENERATOR FROM THE
 STRUCTURE ON BOTH COPIES OF THE SURVEY. THE GENERATOR
 DISTANCE SHALL COMPLY WITH MANUFACTURER'S INSTALLATION
 REQUIREMENTS AND NFPA 37.
 2) SUBMIT AN ISOMETRIC DRAWING THAT CLEARLY SHOWS THE
 LENGTH OF ALL CUT SECTIONS OF PIPE PER 2017 FBC-FUEL
 GAS, SECS. 402.4.1, 402.4.2. OR 2014 FBC-RES SEC.
 G2413.
 3) SHOW THE TYPE OF PIPE MATERIAL BEING INSTALLED, ALL
 PIPE SIZES, FOR EACH PIPE SIZE. WPB AMENDMENTS TO FBC
 SEC.107.2.1.
 4) LIST THE BTU LOAD OF THE GENERATOR AND THE TOTAL BTU
 LOAD ON THE SYSTEM. REFER TO THE 2017 FBC-FUEL GAS
 SECS.401.8 THRU 402.6.1 AND TABLES 402.4 (1) THRU 402.4
 (37) OR 2017 FBC-RES. SEC. G2413.
 5).SHOW THE DISTANCE FROM THE POINT OF DELIVERY, (GAS
 METER / MP REGULATOR / LP TANK) TO THE MOST REMOTE
 OUTLET IN THE BUILDING AND / OR SYSTEM PER THE 2017
 FBC-FUEL GAS SEC.402.4.1 OR 2014 FBC-RES. SEC. G
 2413.3.
 6) INDICATE THE DELIVERY PRESSURE (PSI) OF THE SYSTEM
 ON THE PLAN PER 2017 FBC-FUEL GAS SEC.402.2 OR FBC RES.
 SEC. G2413.2. .
 7) SUBMIT TWO COPIES OF THE APPLICABLE SIZING TABLES
 USED TO SIZE THE GAS SYSTEM OR PLACE A NOTE ON THE
 PLANS/DRAWINGS SPECIFYING WHICH SIZING TABLE(S) FROM
 THE GAS CODE OR OTHER STANDARD THAT WERE USED IN THE
 DESIGN OF THIS GAS SYSTEM. REFER TO THE 2017 FBC-FUEL
 GAS SECS. 401.4, 401.8 THRU 402.6.1 AND TABLES 402.4
 (1) THRU 402.4 (37) OR 2017 FBC-RES. SEC. G2412.4,
 G2412.8, G2413.1, G2413.2, & G2413.3.
 8) SHOW THE LOCATION OF ALL MP (STEP-DOWN) REGULATORS.
 A LISTED SHUTOFF VALVE SHALL BE INSTALLED IMMEDIATELY
 AHEAD OF EACH MP REGULATOR. FBC-FUEL GAS SEC.409.4,
 FBC-RESIDENTIAL SEC. G 2420.4.
 9) SUBMIT MANUFACTURER?S SPECIFICATIONS FOR THE
 PRESSURE REGULATORS. REGULATORS INSTALLED ON THE
 EXTERIOR OF THE BUILDING SHALL BE APPROVED FOR OUTDOOR
 INSTALLATION. 2017 FGC SEC.410.1.
 10) THE GENERATOR SHALL MEET THE REQUIREMENTS OF UL
 2200. THE SPECIFICATIONS FOR THE GENERATOR THAT THE
 LISTING IS FOR THE 60 HZ ONLY. INDICATE THE HZ OF THIS
 UNIT. 2017 FBC-FUEL GAS SEC. 616.1.
  
 TIM LARGE
 CHIEF PLUMBING INSPECTOR
 PLUMBING PLAN REVIEW
 561-805-6692
 [email protected]
  
  
  
  
  
  
  
  
  
  