| 2018-02-22 14:38:26 | 1ST REVIEW: FBC 2010 |
| | |
| | PLUMBING COMMENTS: |
| | |
| | 1. PLEASE SHOW THE DIMENSIONS ON THE CLEAR FLOOR SPACE |
| | FOR THE TOILET IN THE SPEC B MASTER BATHROOM. PER FHA |
| | DESIGN MANUAL REQUIREMENT #7 PG 7.43 |
| | |
| | 2. PLEASE INDICATE ON THE PLAN THE SAFE HARBOR DESIGN |
| | DOCUMENT THAT WAS USED TO DESIGN THIS UNIT TO THE FHA |
| | REQUIREMENTS. WPB AMEND TO FBC 107.2.1 |
| | |
| | 3. REINFORCEMENT FOR GRAB BARS IS REQUIRED IN ALL THE |
| | BATHROOM LOCATED IN DWELLING UNIT PLEASE PROVIDE |
| | DETAILS SHOWING MOUNTING HEIGHTS AND LOCATION OF GRAB |
| | BAR BACKING. PER FHA DESIGN MANUAL REQUIREMENT #6 |
| | |
| | 4. SHT. A-4 DETAIL #4 THE WATER PROOF MEMBRANE FOR THE |
| | SHOWER PAN SHALL BE SLOPED TO THE DRAIN MIN OF 2% SLOPE |
| | .PER FBC PL 417.5.2 |
| | |
| | 5. PLEASE PROVIDE MANUFACTURE SPECIFICATION AND |
| | INSTALLATION GUIDE FOR THE WATER PROOF MEMBRANE FOR |
| | SHOWER LINER SHALL COMPLY WITH FBC PL 417.5.2.5 |
| | |
| | 6. PROVIDE DETAIL FOR HIEGHT OF LAVATORY VANITARY TO |
| | COMPLY WITH FHA |
| | |
| | 7. SHT. P001.00 THIS PROJECT IS DESIGNED UNDER FBC 2010 |
| | UNDER THE BUILDING DEPARTMENT NOTES IT LIST 2014. THE |
| | GAS SHALL COMPLY WITH FBC FG 2010 PLEASE CLARIFY PER |
| | WPB AMEND TO FBC 107.2.1 |
| | |
| | PLEASE NOTE THAT SUBMITTAL OF ADDITIONAL AND/OR REVISED |
| | MATERIALS MAY RESULT IN NEW PLAN REVIEW COMMENTS. |
| | WHEN RESUBMITTING, IT IS HELPFUL TO PROVIDE A RESPONSE |
| | LETTER ADDRESSING EACH ITEM ALONG WITH THE CITY |
| | RE-SUBMITTAL FORM. PLEASE, ADDITIONALLY, INSERT |
| | CORRECTED PAGES INTO TO SUBMITTAL AND REMOVE OR VOID |
| | THE PREVIOUSLY REVIEWED SHEETS. |
| | |
| | GEORGE JOHNSON |
| | PLUMBING PLANS EXAMINER |
| | CITY OF WEST PALM BEACH |
| | 561-805-6711 |
| | [email protected] |
| | |