| 2018-01-11 15:05:42 | ** FAILED ** |
| | |
| | PLEASE ADDRESS THE FOLLOWING COMMENTS. RESPOND TO THE |
| | COMMENTS IN WRITING AND/OR ON THE PLANS WHERE |
| | APPLICABLE: |
| | |
| | 1.) PLEASE HAVE THE SURVEYOR VERIFY THAT ALL EXISTING |
| | STRUCTURES ARE REPRESENTED IN THE SURVEY. AN AERIAL |
| | VIEW OF THE PROPERTY SHOWS THAT THERE IS AN EXISTING |
| | STRUCTURE/ADDITION ALONG THE EAST PROPERTY LINE THAT IS |
| | NOT REFLECTED IN THE SURVEY. |
| | |
| | 2.) WHY DOES THE SURVEY SHOW THAT THE PROPERTY IS SPLIT |
| | INTO THREE SEPARATE PARCELS? PLEASE ADDRESS. |
| | |
| | 3.) PER ZLDR S.94-72, THE REQUIRED REAR SEATBACK IS 15 |
| | FT. OR 10% OF THE LOT DEPTH. BASED ON THE CURRENT |
| | SURVEY AND SITE PLAN, THE BUILDING DOES NOT MEET THE |
| | MINIMUM SETBACK REQUIREMENT. |
| | |
| | 4.) PER ZLDR S.94-72, THE REQUIRED SIDE SETBACK IS A |
| | MINIMUM OF 5 FT. AND 15 FT. TOTAL ON BOTH SIDES. PLEASE |
| | SHOW THE SETBACK DIMENSION FROM THE CLOSEST POINT OF |
| | THE BUILDING TO THE EAST SIDE PROPERTY LINE TO |
| | DEMONSTRATE COMPLIANCE. |
| | |
| | 5.) PLEASE CLARIFY THE SIZE OF THE PROPOSED ADDITION ON |
| | SHEET A-1 OF THE PERMIT PACKET. THE SITE PLAN INDICATES |
| | THE ADDITION IS 780 SQ. FT. AND THE SITE DATA TABLE |
| | INDICATES THAT THE PROPOSED ADDITION IS 587 SQ. FT. |
| | PLEASE CHECK THE CALCULATIONS AND MAKE THE |
| | CORRECTION(S) WHERE NECESSARY. |
| | |
| | 6.) WHAT WILL THE PROPOSED ADDITION BE USED FOR? PLEASE |
| | PROVIDE ADDITIONAL INFORMATION. |
| | |
| | 7.) THE VALUE OF THE CONSTRUCTION ($88,000) EXCEEDS 50% |
| | OF THE STRUCTURE'S VALUE ($159,074) ACCORDING TO THE |
| | P.B.C. PROPERTY APPRAISER'S OFFICE; THEREFORE, PURSUANT |
| | TO SECTION 94-441(C)(2) OF THE ZONING AND LAND |
| | DEVELOPMENT REGULATIONS (ZLDR), THE LANDSCAPE ON THE |
| | SITE SHALL BE IN COMPLIANCE WITH ALL APPLICABLE |
| | REGULATIONS FOUND IN ARTICLE XIV OF THE ZLDR. IF THE |
| | SITE CONFORMS TO ARTICLE XIV, THEN TWO (2) COPIES OF A |
| | LANDSCAPE PLAN DEMONSTRATING COMPLIANCE SHALL BE |
| | INCLUDED WITH THE PERMIT RE-SUBMITTAL. IF THE SITE DOES |
| | NOT CONFORM TO ARTICLE XIV, THEN PRIOR TO THE ZONING |
| | APPROVAL OF THIS PERMIT A SEPARATE LANDSCAPE PERMIT AND |
| | IRRIGATION PERMIT SHALL BE SUBMITTED SHOWING MATERIAL |
| | TO BRING THE SITE INTO CONFORMITY. |
| | |
| | NOTES: |
| | |
| | * REVISIONS MAY RESULT IN ADDITIONAL COMMENTS. |
| | |
| | * CONTACT LINDA LOUIE @ (561) 822-1458 IF THERE ARE |
| | QUESTIONS. |
| | |
| | * ZONE: SF7 |
| | |
| | |