| 2017-12-21 12:25:30 | 1ST REVIEW FBC-2014 MECHANICAL, ENERGY CONSERVATION |
| | CODES. |
| | PERMIT #17120042 |
| | 12/20/17 |
| | |
| | PLAN REVIEW RESULTS: DENIED. |
| | |
| | 1) SHEETS M6.3 & M7.3 WERE NOT SUBMITTED WITH THE PLAN |
| | SETS, AND THERE ARE TWO DIFFERENT M6.1 SHEETS. DUE TO |
| | THESE PLAN OMISSIONS, THE AC EQUIPMENT SCHEDULES FOR |
| | SYSTEMS IN THE OCCUPIED AREAS ARE NOT AVAILABLE TO |
| | REVIEW AND COMPARE WITH THE CALCULATIONS. |
| | |
| | 2) THE ENERGYGAUGE COMPLIANCE REPORT IS LISTING DATA |
| | FOR ZONES AND AHU IDENTIFICATIONS THAT DO NOT MATCH |
| | WITH THE PLANS- THERE ARE NO ZONES SHOWN ON THE PLANS, |
| | AND THE AHU'S SHOWN ON THE PLANS ARE LABELED 1-1, 1-2, |
| | 2-1, 2-2, 3-1, 3-2, AND 4-1. |
| | |
| | 3) THE AC CALCULATIONS ARE INDICATING THAT THE SYSTEMS |
| | SELECTED (AS SHOWN ON THE ENERGY CALCULATIONS ) ARE |
| | OVERSIZED- SEE SECTION C403.2.2 FBC-14 ENERGY |
| | CONSERVATION. |
| | |
| | 4) THE ENERGY REPORT IS MISSING COMPLIANCE DATA FOR THE |
| | CHILLER, THE 3-TON MINI SPLIT SYSTEM, AND THE PIPING |
| | SYSTEM. |
| | |
| | 5) M7.2: THE SYSTEM RISER DIAGRAM SHOWS TWO CHILLERS, |
| | TWO ERV'S, AND WFC SYSTEMS THAT ARE NOT SHOWN ON THE |
| | PLANS - PLEASE CLARIFY. |
| | |
| | 6) M2.1, M2.2, M2.3: THE JUMP DUCTS TRANSFERRING AIR |
| | INTO THE CORRIDORS ARE NOT PERMITTED PER SECTION 601.2. |
| | |
| | 7) M2.1, M2.2, M2.3: SHOW COMPLIANCE WITH SECTION |
| | 606.2.2 FOR THE AHU'S AND VAV BOXES SHARING THE COMMON |
| | RETURN PLENUMS ON EACH FLOOR. INDICATE IF AREA SMOKE |
| | DETECTORS WILL BE INSTALLED IN THE COMMON PLENUM AND |
| | THE SEQUENCE OF OPERATION FOR SHUTDOWN OF THE AHU'S AND |
| | VAV BOXES. |
| | |
| | 8) M2.1 & M2.2: SHOW COMPLIANCE WITH SECTION 401.4 AND |
| | 401.5 RELATING TO THE O/A INTAKES. SUBMIT A FL. PRODUCT |
| | APPROVAL OR MIAMI-DADE NOA FOR THE LOUVERS. |
| | |
| | 9) PROVIDE A SUBMITTAL FOR THE FIRE DAMPER, AND AN |
| | INSTALLATION DETAIL ON THE PLAN. |
| | |
| | 10) PROVIDE A UL LISTED AND LABELED FIRESTOPPING SYSTEM |
| | FOR THE REFRIGERANT PIPING PENETRATIONS. |
| | |
| | 11) PROVIDE WIND LOAD ENGINEERING FOR INSTALLATION OF |
| | THE CHILLER AND ROOF FAN INCLUDING ATTACHMENT DETAILS |
| | AND WIND DESIGN CRITERIA- SECTION 1609 FBC-14 BUILDING. |
| | |