Plan Review Notes For Permit 17110684
Permit Number 17110684
Review Stop B
Sequence Number 1
Notes
Date Text
2017-11-21 07:31:43NO UTILITY RELEASES WERE SUBMITTED WITH THIS
 APPLICATION. TO ISSUE THE DEMO PERMIT, THE FOLLOWING
 WILL NEED TO BE COMPLETED.
  
 1) A CONFIRMATION LETTER FROM F.P.L. THAT THE POWER HAS
 BEEN DISCONNECTED.
  
 2) A CONFIRMATION LETTER FROM F.P.U. THAT THE GAS HAS
 BEEN DISCONNECTED.
  
 3) A CONFIRMATION LETTER FROM THE WATER DEPARTMENT THAT
 THEY HAVE RECEIVED REQUEST TO PULL THE WATER METER.
 WHILE ON SITE, THEY WILL ALSO MARK THE LOCATION OF THE
 SEWER LATERAL. THE DEMO MUST BE KEPT WET. IT MAY BE
 PREFERRED TO INSTALL A HOSE BIB AND BACKFLOW TO
 ACCOMPLISH THIS. THE BACKFLOW INSTALLATION WILL ALSO
 REQUIRE A PERMIT OR BE COMBINED WITH THE CAPPING
 PERMIT.
  
 4) A SEWER LATERAL CAPPING PERMIT PULLED. THE SEWER
 CAPPED AND A FINAL PLUMBING CALLED ON THAT PERMIT. AT
 THE SAME TIME A REQUEST SUBMITTED TO THE WATER
 DEPARTMENT REQUESTING THE WATER METER BE PULLED. THE
 WATER DEPARTMENT WILL MARK THE LOCATION OF THE SEWER
 LATERAL.
  
 5) A RODENT LETTER FROM A PEST CONTROL COMPANY THAT
 THEY HAVE INSPECTED FOR RODENTS AND FOUND NONE, OR
 FOUND RODENTS AND TREATED FOR THEM.
  
 6) A DEBRIS DISPOSAL FORM FILLED OUT. THIS CAN BE DONE
 AT PERMIT PICKUP.
  
 7) HISTORIC AND ENGINEERING'S APPROVALL.
  
 8) ASBESTOS ABATEMENT SURVEY.
  
 I WILL MOVE THE APPLICATION TO THE ENGINEERING MAILBOX
 AT THIS TIME. FEEL FREE TO CALL WITH ANY QUESTIONS.
  
 TOM 561-805-6669