| 2018-06-04 10:33:30 | ****PROVISOS**** |
| | ****ISSUED AT APPLICANT'S RISK**** |
| | |
| | SAMANTHA HILL |
| | BUILDING PLANS EXAMINER |
| | [email protected] |
| | 561-805-6724 |
| | |
| | FBC = FLORIDA BUILDING CODE, 5TH EDITION (2014) |
| | FBC B = FBC BUILDING |
| | FBC EB = FBC EXISTING BUILDING |
| | FBC A = FBC ACCESSIBILITY |
| | FBC EC = FBC ENERGY CONSERVATION |
| | |
| | 1. GENERAL COMMENT, FBC 107, SOME FMEP COMMENTS ARE |
| | ALSO FBC B REQUIREMENTS. A BUILDING REVIEW ON THESE |
| | ITEMS WILL BE DONE UPON RESUBMITTAL. |
| | |
| | 2. REVISION REQUIRED PRIOR TO INSTALLATION - FBC 107, |
| | 6-A6.4.1, A 2 HOUR HORIZONTAL SHAFT WALL SYSTEM IS |
| | SHOWN AND REFERS TO DETAILS 13 AND 14 ON A10.0.1. |
| | DETAIL 14 SPECS "1 HOUR RATED SHAFTWALL ASSEMBLIES". |
| | SHAFT IS TO BE 2 HOUR, A HORIZONTAL ASSEMBLY IS TO BE |
| | SPECIFIED RATHER THAN A WALL ASSEMBLY. PROVIDE LISTING |
| | WHICH ADDRESSES USE OF U415 UTILIZED IN A HORIZONTAL |
| | ORIENTATION OR REVISE DETAIL. |
| | |
| | DETAIL TO COMPLY WITH FBC B 717.3.1, 713.4, 703.2.1 |
| | (ALSO 713.14, 909.21.3 IF APPLICABLE). |
| | |
| | 3. FBC B 403.4, 907.2.13.1, 907.3.3, 907.3.4, AUTOMATIC |
| | SMOKE DETECTION TO BE IN ACCORDANCE WITH THIS SECTION. |
| | FIRE ALARM IS UNDER A SEPARATE PERMIT; PLANS ARE TO |
| | COMPLY WITH OR CLARIFY THE FOLLOWING: |
| | |
| | SHEET FA1.0.0, THE FIRE ALARM LEGEND AND OTHER TEXT ON |
| | THE PAGE ARE TOO LIGHT TO BE LEGIBLE. |
| | SHEET FA1.1.1A, FBC B 970.2.13.1.1(1), A SMOKE DETECTOR |
| | IS REQUIRED IN THE TRANSFORMER VAULT. |
| | THE GRAPHIC IN THE EMERGENCY SWITCH GEAR ROOM WITH TEXT |
| | R/F IS NOT ON THE LEGEND BUT IS SIMILAR TO THE GRAPHIC |
| | FOR "HEAT DETECTOR SENSOR BASE"; CLARIFY. WHAT IS R/F? |
| | DOES THIS DEVICE MEET THE REQUIREMENT IN FBC B |
| | 907.2.13.1.1? |
| | GRAPHICS ARE NOT CLEAR. SEE FA1.3.1A, SEE STAIR #2 ON |
| | FIRST FLOOR (AND OTHER LOCATIONS), CLARIFY WHAT S IN A |
| | PLAIN SQUARE DEPICTS. ALSO CLARIFY WHY THE EXIT |
| | PASSAGEWAYS/EXIT CORRIDORS DO NOT HAVE ANY DEVICES; ARE |
| | THE EXEMPTED? |
| | HOW WILL THE REQUIREMENTS OF FBC B 908.7.1 BE MET? |
| | |
| | 4. FBC B 403.5.3, REVISE PLAN TO SHOW COMPLIANCE. |
| | |
| | RESPONSE STATES THAT E3.0.0 FIRE COMMAND ROOM HAS A |
| | DOOR UNLOCKING DEVICE; PLEASE HAVE ENGINEER ADVISE AS |
| | TO WHERE THIS CAN BE FOUND. IT DOES NOT APPEAR TO BE |
| | ONE OF THE "FIRE COMMAND ROOM KEYNOTES" OR REVISE PLAN |
| | TO INCLUDE. |
| | |
| | 5. FBC B TABLE 705.8, CLARIFY HOW <15% WAS DETERMINED |
| | FOR THE WALL WHICH OPENS TO ALLOW HOTEL ACCESS. |
| | |
| | RESPONSE WILL BE DISCUSSED WITH BUILDING OFFICIAL AND |
| | ABO. WALL PERCENTAGE CALCULATIONS ARE DONE BASED ON THE |
| | WALL PORTION WHICH IS AFFECTED (PORTION WHICH IS >3' |
| | FROM PROPERTY LINE). ON LS1.1 THE CALCULATION UTILIZES |
| | THE ENTIRE WALL LENGTH. IT IS POSSIBLE THAT THIS WILL |
| | BE PERMITTED DEPENDING ON OPENINGS ON THE ADJACENT |
| | PROPERTY IN THIS LOCATION. PROVIDE INFORMATION |
| | REGARDING OPENINGS ON THE OTHER SIDE OF THE LOT LINE. |
| | |
| | 6. THIS PARCEL IS LOCATED IN A SPECIAL FLOOD HAZARD |
| | AREA; FLOOD MAP IN EFFECT AT TIME OF FOUNDATION PERMIT |
| | APPLICATION 1979 FIRMS + 1' FREEBOARD; MINIMUM |
| | ELEVATION = 8.0' NGVD29, PROPOSED LOWEST FINISHED FLOOR |
| | ELEVATION = 9.0' NGVD29 |
| | A "CONSTRUCTION DRAWING" ELEVATION CERTIFICATE IS |
| | RECOMMENDED AT THIS TIME TO AVOID FUTURE DELAYS |
| | (CORRECTIONS, IF APPLICABLE, WILL NOT DELAY PERMIT |
| | ISSUANCE) |
| | A "BUILDING UNDER CONSTRUCTION" ELEVATION CERTIFICATE |
| | OR FORM BOARD SURVEY IS REQUIRED PRIOR TO CONCRETE |
| | POUR. THIS MAY BE SENT VIA EMAIL FOR PRELIMINARY REVIEW |
| | A "FINISHED CONSTRUCTION" ELEVATION CERTIFICATE IS |
| | REQUIRED PRIOR TO FINAL INSPECTION AND/OR CO AND/OR |
| | TCO. |
| | |
| | 7. BARN DOORS TO MAINTAIN THE 25SF LOUVERS, A1.3.1 AND |
| | OTHER SHEETS UP TO 3RD FLOOR, FOR COMPLIANCE WITH FBC B |
| | 1029.1, OK PER RB. |
| | |
| | 8. DEFERRED SUBMITTALS REQUESTED BY ARCHITECT, SEE |
| | FOLLOWING LIST (MAY NOT BE A COMPLETE LIST); DOCUMENTS |
| | SHOWING COMPLIANCE ARE TO BE REVIEWED BY DESIGNER OF |
| | RECORD PRIOR TO SUBMITTAL (ARCHITECT OR ENGINEER FOR |
| | PRODUCT APPROVALS AND OTHER SPECIFICATION DOCUMENTS, |
| | STRUCTURAL ENGINEER OF RECORD APPROVAL AND REVIEW IS |
| | REQUIRED FOR DELEGATED ENGINEERING). SUBMITTAL, REVIEW |
| | AND APPROVAL ARE REQUIRED PRIOR TO INSTALLATION. |
| | |
| | COMPONENT & CLADDING PRODUCT APPROVALS (COMPLY WITH |
| | PRESSURES SHOWN ON SHEET S0.0.5) |
| | FBC B 2403.2, SEMI FRAMELESS SHOWER ENCLOSURE |
| | ENGINEERING |
| | GLASS GUARDS DELEGATED ENGINEERING |
| | BALCONY ALUMINUM GUARDRAILS DELEGATED ENGINEERING |
| | POOL DECK GUARDRAILS DELEGATED ENGINEERING |
| | ALUCOBOND, PROVIDE PRODUCT APPROVALS AND SPEC SHEETS TO |
| | SHOW COMPLIANCE WITH FBC B 602.2, 1 |
| | TERRACORP, SPEC SHEETS SHOWING COMPLIANCE WITH |
| | REQUIREMENTS FOR NON COMBUSTIBLE BUILDINGS, |
| | INSTALLATION DETAILS FBC B 1609 |
| | DECORATIVE MESH COLUMN ENCLOSURE SHOWN ON A3.1.14 AND |
| | OTHER SHEETS, FBC B 602.2 (NON COMBUSTIBLE), 1609 |
| | (RESISTANCE TO WIND LOADS), PROVIDE SPEC SHEETS AND |
| | PRODUCT APPROVAL OR ENGINEERING TO SHOW COMPLIANCE |
| | |
| | 9. FBC 1207.2, 1207.3, FIELD TESTING FOR STC/IIC WILL |
| | BE DONE, LVT ENVIROQUIET II (NOTE: 8" CONCRETE SLABS) |
| | WHISPER MAT CS IS PROPOSED BUT DOES NOT HAVE A FLAME |
| | SPREAD TEST FOR LVT. PLEASE CONTACT ME IN A FEW WEEKS; |
| | AT THIS TIME THE WHISPER MAT CS SPEC SHEET HAS BEEN |
| | VOIDED, BUT WE ARE CURRENTLY EVALUATING THIS AND OTHER |
| | UNDERLAYMENTS IN THIS APPLICATION. |
| | |
| | 10. THE FOLLOWING ITEMS MAY REQUIRE A DETAIL OR SPEC |
| | SHEETS TO BE SUBMITTED SUBJECT TO INSPECTOR'S |
| | DISCRETION: |
| | FBC B 603, "WOOD SLATS AT ROOF FASCIA" IS SHOWN; |
| | PROVIDE SPEC SHEETS AT INSPECTION TO SHOW COMPLIANCE. |
| | FBC B 603.1 2-A8.3.3 AND OTHER LOCATIONS, IPE WOOD IS |
| | PROPOSED; PROVIDE SPEC SHEETS AT INSPECTION TO SHOW |
| | COMPLIANCE. |
| | FBC A FAIR HOUSING REQUIREMENT 2 ANSI 4.1-4.3.1, |
| | RECEPTION DESK IN RESIDENTS LOBBY TO COMPLY. |
| | FBC B 603.1(15), A3.1.11 AND OTHER SHEETS, KRINKLGLAS, |
| | SHOWN ON VARIOUS PAGES, TO COMPLY WITH CHAPTER 26 |
| | |
| | 11. SEPARATE PERMITS (APPLICATIONS, PLANS, AND FEES) |
| | ARE REQUIRED FOR: |
| | LIGHT POLES/SITE LIGHTING |
| | SWIMMING POOL |
| | FIRE ALARM |
| | FIRE SPRINKLER |
| | LOW VOLTAGE |
| | ACCESS |
| | LANDSCAPING |
| | IRRIGATION |
| | ALL OTHER ITEMS OTHER THAN BMEP |
| | |
| | 12. PROVIDE THE RECORDED PLAT WHEN FINALIZED; EITHER A |
| | PDF VIA EMAIL OR ADVISE BOOK AND PAGE NUMBER VIA EMAIL. |
| | |
| | 13. AIPP COMPLIANCE REQUIRED; VERIFICATION REQUIRED |
| | PRIOR TO C.O. |
| | |
| | 14. SHORING/RESHORE ENGINEERING IS REQUIRED TO BE |
| | SUBMITTED TO THE BUILDING DIVISION FOR REVIEW. THE |
| | ENGINEERING IS TO BE SUBMITTED, REVIEWED AND ISSUED |
| | PRIOR TO CONCRETE POUR. |
| | |
| | 15. A CONSTRUCTION GUARD RAIL ENGINEERED DETAIL IS |
| | REQUIRED TO BE PROVIDED PRIOR TO INSTALLATION. |
| | |
| | |
| | |