| 2018-02-15 13:31:22 | 2ND REVIEW FBC-2014 MECHANICAL |
| | PERMIT #17110075 |
| | 2/13/2018 |
| | |
| | PLAN REVIEW RESULTS: DENIED. |
| | |
| | THE SECOND REVIEW OF THE PLANS IS BASED ON THE |
| | RESUBMITTED PLANS AND DOCUMENTS, AND THE RESPONSES BY |
| | THE ENGINEER OF RECORD. COMMENTS FROM THE 1ST REVIEW |
| | THAT HAVE NOT BEEN ADDRESSED, OR PARTIALLY STILL EXIST |
| | WILL BE REITERATED BELOW. |
| | |
| | 1) COMMENT #1: 2ND REQUEST FOR ELECTRONICALLY SIGNED |
| | AND SEALED AC CALCULATIONS. |
| | |
| | 2) COMMENT #2: IT IS AGREED THAT THE APARTMENT SYSTEMS |
| | DO NOT HAVE TO BE COMMISSIONED HOWEVER THE COMMON AREA |
| | AND CORRIDOR SYSTEMS DO NOT FALL UNDER SECTION C408.2 |
| | EXCEPTION #2. PLEASE NOTE THAT COMMISSIONING OF THE |
| | ELECTRICAL POWER AND LIGHTING SYSTEMS IS ALSO REQUIRED |
| | AND SHALL BE INCLUDED IN THE REPORT. |
| | |
| | 3) COMMENTS #3 & 4: PLEASE PROVIDE DOCUMENTATION THAT |
| | THE TRACE 700 PROGRAM IS COMPLIANT WITH ASHRAE/ACCA |
| | STANDARD 183 OR ACCA MANUAL N. |
| | |
| | 4) COMMENT #5: 2ND REQUEST FOR AN ACCURATE ENERGYGAUGE |
| | COMPLIANCE REPORT THAT PROVIDES DATA CONSISTENT WITH |
| | THE SYSTEMS SHOWN ON THE PLANS. |
| | |
| | 5) COMMENT #6: AS STATED IN THE RESPONSE NARRATIVE, |
| | ESTIMATED LOADS HAVE BEEN USED TO PROVIDE INPUT DATA |
| | FOR THE FUTURE OLIVE AND BANYAN RETAIL SPACES IN THE |
| | ENERGYGAUGE REPORT. PLEASE INDICATE SPECIFICALLY WHERE |
| | THIS INPUT DATA CAN BE FOUND IN THE REPORT. I WAS |
| | UNABLE TO LOCATE IT. |
| | |
| | 6) COMMENT #7: 2ND REQUEST FOR THE SMOKE ANALYSIS |
| | REPORT TO BE ELECTRONICALLY SIGNED AND SEALED. |
| | |
| | 7) COMMENT #8: ACKNOWLEDGED. COMMISSIONING OF THE SMOKE |
| | CONTROL SYSTEMS WILL BE PROVIDED BY THE OWNERSHIP IN |
| | CONJUNCTION WITH SLS AS A DEFERRED SUBMITTAL. |
| | |
| | 8) COMMENT #9: 2ND REQUEST FOR MINIMUM VENTILATION |
| | CALCULATIONS FOR THE ELEVATOR LOBBIES. THE REQUIREMENT |
| | FOR VENTILATING THE LOBBIES IS FOUND IN SECTION 403.3 |
| | AND TABLE 403.3, AND ALSO SECTION 404.3. |
| | |
| | 404.3 OCCUPIED SPACES ACCESSORY TO PUBLIC GARAGES. |
| | CONNECTING OFFICES, WAITING ROOMS, TICKET BOOTHS AND |
| | SIMILAR USES THAT ARE ACCESSORY TO A PUBLIC GARAGE |
| | SHALL BE MAINTAINED AT A POSITIVE PRESSURE AND SHALL BE |
| | PROVIDED WITH VENTILATION IN ACCORDANCE WITH SECTION |
| | 403.3 |
| | |
| | 9) COMMENT #11, SHEETS M1.1.1B, M.1.1.1C: IT IS AGREED |
| | THAT THE TRANSFER GRILLS FROM THE STAIRWELL ENCLOSURES |
| | INTO THE EXIT PASSAGEWAYS ARE PERMITTED UNDER SECTION |
| | 1022.5 AND 1022.10.1 FOR PRESSURIZATION OF THE EXIT |
| | PASSAGEWAYS, HOWEVER PRESSURIZATION OF THE PASSAGEWAYS |
| | AND THE SEQUENCE OF OPERATION FOR THE FIRE DAMPERS IN |
| | THE TRANSFER GRILLS ABOVE THE STAIRWELL ENCLOSURE |
| | |
| | DOORS ARE NOT INCLUDED IN THE SMOKE ANALYSIS REPORT, OR |
| | MENTIONED IN THE SEQUENCE OF OPERATION ON SHEET M5.03. |
| | PLEASE REVISE THE REPORT AND PLANS ACCORDINGLY, AND |
| | CLARIFY IF THE EXISTING FANS HAVE THE CAPACITIES TO |
| | PRESSURIZE THE PASSAGEWAYS IN A SMOKE EVENT. PLEASE |
| | NOTE THAT THE DOOR OPENINGS THAT ARE SHOWN IN THE |
| | PASSAGEWAYS CONNECTING THE LOADING BAY AND GARAGE ETC. |
| | |
| | ARE PERMITTED ONLY IF THE EXIT PASSAGEWAYS ARE |
| | PRESSURIZED IN THE SAME MANNER AS THE STAIRWELLS- |
| | SECTION 1022.10.1 EXCEPTIONS. THE PRESSURIZATION OF |
| | THESE PASSAGEWAYS HAS NOT BEEN ADDRESSED. |
| | |
| | 10) COMMENTS #14 & 31: ACKNOWLEDGED. PLEASE PROVIDE A |
| | NOTE ON THE PLAN FOR O/A CLEARANCE REQUIREMENTS. |
| | |
| | 11) COMMENTS #15 & 27: ACKNOWLEDGED. MANUFACTURER'S |
| | SPECIFICATIONS FOR THE CONDENSERS TO BE A DEFERRED |
| | SUBMITTAL. THE SPECS SHALL INDICATE THE UNITS MAY BE |
| | INSTALLED INDOORS. |
| | |
| | 12) COMMENT #18: THERE IS NO NOTE IN THE FAN SCHEDULE |
| | TO INDICATE THE FIRE PUMP EXHAUST FAN EF-L1 WILL RUN |
| | CONTINUOUSLY. |
| | |
| | 13) COMMENT #25: THERE IS NO NOTE IN THE FAN SCHEDULE |
| | TO INDICATE THE EXHAUST FANS EF-M1 & EF-M2 WILL RUN |
| | CONTINUOUSLY. |
| | |
| | 14) COMMENT #26: ACKNOWLEDGED. PLEASE PROVIDE A NOTE ON |
| | THE PLAN PERTAINING TO REQUIRED GENERATOR EXHAUST |
| | CLEARANCES. SUBMIT SPECS FOR THE GENERATOR AND EXHAUST |
| | PIPING. |
| | |
| | 15) COMMENTS #28, 29, 37, & 38: : INDICATE HOW THE |
| | CONDENSER AND FAN SUPPORTS BARS WILL BE ATTACHED TO |
| | FLOOR/CEILING SLAB ABOVE. |
| | |
| | 16) COMMENT #30: REQUESTED ARCHITECTURAL DETAILS AND |
| | SECTION CUTS FOR THE GENERATOR INTAKE PLENUM NOT |
| | PROVIDED. |
| | |
| | 17) COMMENT #32: PLEASE SEE COMMENT #8 FROM THIS |
| | CURRENT REVIEW. MINIMUM VENTILATION AND PRESSURIZATION |
| | IS REQUIRED FOR ALL ELEVATOR LOBBIES ON ALL LEVELS THAT |
| | ARE ADJACENT TO PARKING GARAGE AREAS. |
| | |
| | 18) COMMENT #33, SHEET M1.3.1.B: THE O/A OPENING SHALL |
| | BE LOCATED ON THE EXTERIOR WALL. THE PLAN SHOWS THE |
| | LOUVER CONNECTING WITH AN ENCLOSED PARKING GARAGE- |
| | SECTION 401.2 |
| | |
| | 19) COMMENT #39: A) MINIMUM 8' FROM FINISHED FLOOR TO |
| | THE BOTTOM OF THE SMOKE EXHAUST DUCT AND FAN REQUIRED- |
| | SECTION 304.6. B) SUBMIT MANUFACTURER'S SPECIFICATIONS |
| | FOR THE FIRE WRAP WITH SHOP DRAWING APPROVAL BY THE |
| | EOR. |
| | |
| | 20) COMMENT #41: BECAUSE THE SPECS INDICATE THE SYSTEM |
| | WILL PRODUCE OVER 2000 CFMS AT .10, .20, OR .30 STATIC |
| | PRESSURE, THE DUCT SMOKE DETECTOR WILL BE REQUIRED. |
| | |
| | 21) COMMENT #43: PLEASE ADD A NOTE IN THE SCHEDULE THAT |
| | THE POOL EQUIPMENT ROOM EXHAUST FAN EF-5-1 WILL RUN |
| | CONTINUOUSLY. |
| | |
| | 22) COMMENT #44: SUBMIT SPECS FOR THE BBQ AND INDICATE |
| | HOW IT WILL BE ANCHORED TO RESIST WIND LOADS- SECTIONS |
| | 301.10 & 623.1 FBC-14 FUEL GAS. |
| | |
| | 23) COMMENTS #45 & 46: ACKNOWLEDGED. THE POOL AND POOL |
| | EQUIPMENT SHALL BE SUBMITTED UNDER SEPARATE PERMIT. |
| | |
| | 24) COMMENT # 47, SHEET A10.1.1: FIRESTOPPPING FOR THE |
| | REFRIGERANT PIPING PENETRATING THE FIRE-RATED STEEL |
| | FRAMED AND GYPSUM ENCLOSURE NOT PROVIDED. |
| | |
| | 25) COMMENT #51: ACKNOWLEDGED. WIND LOAD ENGINEERING |
| | FOR ALL ROOFTOP MECHANICAL INSTALLATIONS SHALL BE |
| | DEFERRED SUBMITTALS. |
| | |
| | 26) COMMENT #52: PLEASE SEE COMMENT #9 FROM THIS REVIEW |
| | CONCERNING THE EXIT PASSAGEWAYS FOR STAIRS #2 & #3. |
| | REVISIONS TO THE SMOKE CONTROL REPORT AND PLANS MAY BE |
| | REQUIRED. |
| | |
| | 27) COMMENT #54: REFER TO COMMENT #20 FROM THIS CURRENT |
| | REVIEW. |
| | |
| | 28) COMMENT #63: PLEASE SEE SECTION 601.5(3). ALL |
| | SUPPLY AIR INTO A MASTER SUITE SHALL BE RETURNED. 10X6 |
| | X 1.5 = 90. THE 72 SQ. IN. RETURN DUCT IS UNDERSIZED. |
| | |
| | 29) COMMENTS #64 & 65: SEE COMMENT #28 FROM THIS REVIEW |
| | AND CORRECT. |
| | |
| | 30) COMMENT #68: MINIMUM 90 SQ. IN. RETURN DUCT FROM |
| | THE MASTER SUITE REQUIRED- SECTION 601.5(3). |
| | |
| | 31) COMMENT #71: MINIMUM 90 SQ. IN. RETURN DUCT FROM |
| | THE MASTER SUITE REQUIRED- SECTION 601.5(3). |
| | |
| | 32) COMMENT #73: MINIMUM 90 SQ. IN. RETURN DUCT FROM |
| | THE MASTER SUITE REQUIRED- SECTION 601.5(3). |
| | |
| | 33) COMMENT #74: MINIMUM 90 SQ. IN. RETURN DUCT FROM |
| | THE MASTER SUITE REQUIRED- SECTION 601.5(3). |
| | |
| | 34) COMMENT #75: MINIMUM 90 SQ. IN. RETURN DUCT FROM |
| | THE MASTER SUITE REQUIRED- SECTION 601.5(3). |
| | |
| | 35) COMMENT #76: MINIMUM 90 SQ. IN. RETURN DUCT FROM |
| | THE MASTER SUITE REQUIRED- SECTION 601.5(3). |
| | |
| | |
| | WHEN RESUBMITTING, IT IS HELPFUL TO PROVIDE A RESPONSE |
| | LETTER ADDRESSING EACH ITEM ALONG WITH THE CITY |
| | RE-SUBMITTAL FORM. ADDITIONALLY, PLEASE INSERT |
| | CORRECTED PLAN SHEETS INTO THE SETS, REMOVE THE |
| | PREVIOUSLY REVIEWED SHEETS AND MARK VOID ON THEM, AND |
| | KEEP THEM WITH THE SUBMITTALS. |
| | |
| | CHRISTOPHER L. COLE |
| | MECHANICAL PLANS EXAMINER |
| | 401 CLEMATIS STREET |
| | WEST PALM BEACH FL 33401 |
| | 561-805-6719 |
| | [email protected] |
| | |
| | |