| 2018-05-11 18:55:49 | PLAN |
| | REVIEW COMMENTS |
| | |
| | 3RD REVIEW: FBC FIFTH EDITION (2014) |
| | ROBERT MCDOUGAL, CBO |
| | COMMERCIAL COMBINATION PLANS EXAMINER |
| | (561) 805-6714 |
| | [email protected] |
| | |
| | NOTE: THE FIRST REVIEW WAS DONE UNDER THE 2017 FBC DUE |
| | TO CLERICAL ERROR. |
| | DENIED BY MECHANICAL |
| | PLEASE ADDRESS THE ITEMS NOTED BELOW: |
| | |
| | 1) SUBMIT TWO SETS OF EQUIPMENT SIZING CALCULATION. FBC |
| | ENERGY CONSERVATION - SECT. R403.7.1 EQUIPMENT SIZING. |
| | HEATING AND COOLING EQUIPMENT SHALL BE SIZED IN |
| | ACCORDANCE WITH ACCA MANUAL S BASED ON THE EQUIPMENT |
| | LOADS CALCULATED IN ACCORDANCE WITH MANUAL J OR OTHER |
| | APPROVED HEATING AND COOLING CALCULATION METHODOLOGIES, |
| | BASED ON BUILDING LOADS FOR THE DIRECTIONAL ORIENTATION |
| | OF THE BUILDING. THE MANUFACTURER AND MODEL NUMBER OF |
| | THE OUTDOOR AND INDOOR UNITS (IF SPLIT SYSTEM) SHALL BE |
| | SUBMITTED ALONG WITH THE SENSIBLE AND TOTAL COOLING |
| | CAPACITIES AT THE DESIGN CONDITIONS DESCRIBED IN |
| | SECTION 302.1. THIS CODE DOES NOT ALLOW DESIGNER SAFETY |
| | FACTORS, PROVISIONS FOR FUTURE EXPANSION OR OTHER |
| | FACTORS WHICH AFFECT EQUIPMENT SIZING. SYSTEM SIZING |
| | CALCULATIONS SHALL NOT INCLUDE LOADS CREATED BY LOCAL |
| | INTERMITTENT MECHANICAL VENTILATION SUCH AS STANDARD |
| | KITCHEN AND BATHROOM EXHAUST SYSTEMS. NEW OR |
| | REPLACEMENT HEATING AND COOLING EQUIPMENT SHALL HAVE AN |
| | EFFICIENCY RATING EQUAL TO OR GREATER THAN THE MINIMUM |
| | REQUIRED BY FEDERAL LAW FOR THE GEOGRAPHIC LOCATION |
| | WHERE THE EQUIPMENT IS INSTALLED. |
| | NEW COMMENT: THE EQUIPMENT SIZING CALCULATIONS AND |
| | ENERGY CODE COMPLIANCE FORMS THAT WERE SUBMITTED ARE ON |
| | THE 2017 FORMS. THIS PROJECT IS UNDER THE 2014 EDITION |
| | OF THE FBC. |
| | |
| | 2) SUBMIT TWO SETS OF 2014 ENERGY CODE COMPLIANCE FORMS |
| | FOR THE NEW GARAGE, OFFICE AND GAME ROOM STRUCTURE. FBC |
| | ENERGY CONSERVATION - SECT. R103.1.1.2 CODE COMPLIANCE |
| | CERTIFICATION. |
| | NEW COMMENT: THE EQUIPMENT SIZING CALCULATIONS AND |
| | ENERGY CODE COMPLIANCE FORMS THAT WERE SUBMITTED ARE ON |
| | THE 2017 FORMS. THIS PROJECT IS UNDER THE 2014 EDITION |
| | OF THE FBC. |
| | |
| | 3) NEW COMMENT: THE CODE COMPLIANCE FORMS ARE REQUIRED |
| | TO BE SIGNED BY THE OWNER/AGENT. FBC ENERGY |
| | CONSERVATION - SECT. R103.1.1.2 |
| | |
| | 4) NEW COMMENT: THE ENERGY CODE COMPLIANCE FORMS LIST 1 |
| | BEDROOM AND THERE ARE NOT ANY BEDROOMS IN THIS |
| | STRUCTURE SHOWN ON THE PLANS. REVISE. FBC 107.2.1 |
| | |
| | 5) NEW COMMENT: THE EQUIPMENT SIZING CALULATIONS AND |
| | ENERGY FORMS DO NOT MATCH THE EQUIPMENT SCHEDULE ON THE |
| | PLANS. THE SIZING CALCULATIONS SPECIFY 2.2 TONS AND |
| | 23,200 BTUH AND THE PLANS LIST 3 TONS AND 36,000 BTUH. |
| | PLEASE CORRECT FBC 107.2.1. |