| Date |
Text |
| 2017-11-02 08:56:44 | ****PROVISO**** |
| | ****PROVIDE REVISED ELEVATION CERTIFICATE WITHIN SEVEN |
| | WORKING DAYS**** |
| | ****APPROVED AT CONTRACTOR'S / SURVEYOR'S RISK**** |
| | |
| | SAMANTHA HILL |
| | BUILDING PLANS EXAMINER |
| | [email protected] |
| | 561-805-6724 |
| | |
| | FBC = FLORIDA BUILDING CODE, 5TH EDITION (2014) |
| | FBC B = FBC BUILDING |
| | FBC EB = FBC EXISTING BUILDING |
| | FBC A = FBC ACCESSIBILITY |
| | FBC EC = FBC ENERGY CONSERVATION |
| | |
| | ALL ELEVATIONS FOR THIS PROJECT EXCEED THE MINIMUM |
| | REQUIREMENTS. HOWEVER, THE FOLLOWING REVISIONS ARE |
| | REQUIRED: |
| | |
| | 1. PAGE 2 OF 6, COMMENTS SECTION D, THE TEXT (EL 7) |
| | SHOULD INCLUDE VERTICAL DATUM (EL 7 NGVD29). |
| | |
| | 2. COMMENTS SECTION D, SEE ELEVATION CERTIFICATE |
| | INSTRUCTIONS, CONVERSION IS REQUIRED AS PROJECT WAS |
| | PERMITTED UNDER A MAP WHICH UTILIZED NGVD29 DATUM. FOR |
| | ALL ELEVATIONS IN SECTION C2, INCLUDE A CONVERSION TO |
| | NGVD29. |
| | |
| | PLEASE NOTE THAT, AS OF 2017, FOR COMMUNITY RATING |
| | SYSTEM (FEMA) AUDIT, ALL ELEVATION CERTIFICATES FOR NEW |
| | CONSTRUCTION AND SUBSTANTIAL IMPROVEMENTS WILL BE |
| | REVIEWED BY THE AUDITOR IN A DIFFERENT STATE AND |
| | REGION. THE PROJECT'S COMPLIANCE WITH FBC FLOOD |
| | PROVISIONS AND NFIP (FEMA) REQUIREMENTS ARE DOCUMENTED |
| | BY THE ELEVATION CERTIFICATE. |
| | |
| | THIS REVIEW IS PASSED WITH THE UNDERSTANDING AND |
| | AGREEMENT THAT THE ELEVATION CERTIFICATE WILL BE |
| | REVISED AND PROVIDED TO ME OR JULIO GOMEZ WITHIN SEVEN |
| | BUSINESS DAYS. |
| | |
| | |
| | |