| 2017-11-15 17:52:41 | 1ST REVIEW FBC-2014 MECHANICAL, ENERGY CONSERVATION, |
| | WPB AMENDMENTS TO THE FBC. |
| | PERMIT #17100767 |
| | 11/15/17 |
| | |
| | PLAN REVIEW RESULTS: DENIED. |
| | |
| | 1) THE BUILDING PLAN REVIEWER HAS DETERMINED THAT NO |
| | PERMIT EXISTS FOR THE BUILDING AND AS A RESULT IT WILL |
| | BE REVIEWED AS A NEW BUILDING. |
| | |
| | 2) THERE ARE NO MECHANICAL PLANS SUBMITTED HOWEVER |
| | THERE IS AN AIR HANDLER SHOWN IN A CLOSET BY THE |
| | OFFICE. PLEASE PROVIDE COMPLETE AC PLANS INCLUDING: |
| | |
| | A) AC EQUIPMENT SCHEDULE. |
| | |
| | B) DUCT LAYOUT PLAN. |
| | |
| | C) AIR DEVICE SCHEDULE. |
| | |
| | D) LOCATION OF CONDENSER AND FLOOD ELEVATION AND WIND |
| | RESISTANCE COMPLIANCE. |
| | |
| | 3) CALCULATIONS REQUIRED: |
| | |
| | A) MINIMUM VENTILATION CALCULATIONS FOR THE OCCUPIED |
| | AREA EITHER USING NATURAL OR MECHANICAL MEANS- SEE |
| | SECTIONS 402, 403 AND TABLE 403.3 |
| | |
| | B) AC COOLING AND HEATING CALCULATIONS- C403.3.2 FBC-14 |
| | ENERGY COMPLIANCE. |
| | |
| | C) ENERGY CALCULATIONS- SECTION C101 AND C401.2. |
| | |
| | D) EXHAUST VENTILATION CALCULATIONS FOR THE GARAGE - |
| | SEE TABLE 403.3 AND SECTION 404 |
| | |
| | 4) PROVIDE AN EXHAUST VENTILATION SYSTEM FOR THE |
| | GARAGE- SEE SECTION 404. |
| | |
| | WHEN RESUBMITTING, IT IS HELPFUL TO PROVIDE A RESPONSE |
| | LETTER ADDRESSING EACH ITEM ALONG WITH THE CITY |
| | RE-SUBMITTAL FORM. ADDITIONALLY, PLEASE INSERT |
| | CORRECTED PLAN SHEETS INTO THE SETS, REMOVE THE |
| | PREVIOUSLY REVIEWED SHEETS AND MARK VOID ON THEM, AND |
| | KEEP THEM WITH THE SUBMITTALS. |
| | |
| | CHRISTOPHER L. COLE |
| | MECHANICAL PLANS EXAMINER |
| | 401 CLEMATIS STREET |
| | WEST PALM BEACH FL 33401 |
| | 561-805-6719 |
| | [email protected] |
| | |
| | |