| Date |
Text |
| 2017-11-06 17:58:09 | PLAN |
| | REVIEW COMMENTS |
| | |
| | 1ST REVIEW: FBC FIFTH EDITION (2014) |
| | ROBERT MCDOUGAL, CBO |
| | COMMERCIAL COMBINATION PLANS EXAMINER |
| | (561) 805-6714 |
| | [email protected] |
| | |
| | DENIED BY BUILDING |
| | PLEASE ADDRESS THE ITEMS NOTED BELOW: |
| | |
| | 1) THE CODE COMPLIANCE STATEMENT ON THE COVERSHEET IS |
| | NOT SIGNED BY THE DESIGNER OF RECORD. |
| | |
| | 2) SPECIFY THE TYPE OF CONSTRUCTION FOR THE STRUCTURE |
| | ON THE PLANS. IT APPEARS TO BE TYPE V-B. FBC-R301.1.1 & |
| | FBC 602.1 |
| | |
| | 3) THE ELEVATIONS ON THE SITE DRAINAGE PLAN ON AS-1 |
| | INDICATE THAT THE SURFACE WATER ON THE WEST SIDE OF THE |
| | STRUCTURE WILL DRAIN TO THE SOUTHWEST REAR CORNER OF |
| | THE PROPERTY AND POSSIBLY ONTO THE ADJACENT PROPERTY. |
| | PLEASE REVIEW THE ELEVATIONS AND PROVIDE DRAINS OR |
| | SWALES TO ENSURE THAT THE SURFACE DRAINAGE IS DIVERTED |
| | TO A STORM SEWER CONVEYANCE OR OTHER APPROVED POINT OF |
| | COLLECTION. FBC-R401.3 |
| | |
| | 4) THE ENERGY FORM R405-2014 IS REQUIRED TO BE SIGNED |
| | AND DATED BY THE PREPARER AND THE OWNER/AGENT. FBC |
| | ENERGY CONSERVATION SECT. R103.1.1.2 AND R405.4.2 |
| | |
| | 5) THE ENERGY FORM R405-2014 HAS THE WRONG ORIENTATION |
| | FOR THE FRONT AND REAR EXTERIOR DOORS. THE FRONT DOOR |
| | FACES NORTH AND THE REAR DOOR FACES SOUTH. NOT EAST AND |
| | WEST AS LISTED IN THE DOCUMENT. |
| | |
| | 6) ON SHEET S1.1 ONE OF THE MASONRY NOTES REFERENCES |
| | ACI 530-99. CHAPTER 46 OF THE 2014 FBC-R REFERENCES THE |
| | 2011 EDITION OF ACI 530. PLEASE UPDATE TO ACI 530-11. |
| | |
| | 7) FBC 109.3 BUILDING PERMIT VALUATION. FOR PERMITTING |
| | PURPOSES, VALUATION OF BUILDINGS AND SYSTEMS SHALL BE |
| | TOTAL REPLACEMENT VALUE TO INCLUDE STRUCTURAL, |
| | ELECTRIC, PLUMBING, MECHANICAL, INTERIOR FINISH, |
| | RELATIVE SITE WORK, ARCHITECTURAL AND DESIGN FEES, |
| | MARKETING COSTS, OVERHEAD AND PROFIT; EXCLUDING ONLY |
| | LAND VALUE. VALUATION REFERENCES MAY INCLUDE THE LATEST |
| | PUBLISHED DATA OF NATIONAL CONSTRUCTION COST ANALYSIS |
| | SERVICES (MARSHALL-SWIFT, MEANS, ETC.), AS PUBLISHED BY |
| | INTERNATIONAL CODE CONGRESS. FINAL BUILDING PERMIT |
| | VALUATION SHALL BE SET BY THE BUILDING OFFICIAL. THE |
| | VALUATION HAS BEEN INCREASED TO $177,399.00 BASED ON |
| | THE LATEST ICC VALUATION DATA. |
| | |
| | 8) IN ORDER TO REDUCE PLAN REVIEW TIME, PLEASE SUBMIT A |
| | RESPONSE LETTER INDICATING HOW EACH OF THE REVIEW |
| | COMMENTS HAS BEEN ADDRESSED. |
| | |