Plan Review Notes
Plan Review Notes For Permit 17100174
Permit Number 17100174
Review Stop G
Sequence Number 1
Notes
Date Text
2017-10-16 13:29:5610/16/17 GAS REVIEW FOLLOWING SITE INSPECTION
  
 THIS PERMIT WILL BE APPROVED BASED ON THE GAS INSTALL
 UNDER PERMIT #15051024 THAT HAD BEEN PREVIOUSLY CLOSED
 OUT. THIS PERMIT WILL BE FOR THE REINSTALL OF THE GAS
 FIRE PIT AND WILL REQUIRED INSPECTION'S AND GAS
 AFFIDAVIT ON THE FINAL
2017-10-10 16:27:5010/10/17 1ST GAS REVIEW**DENIED**
  
 NOTE - A COMPREHENSIVE REVIEW COULD NOT BE DONE AT THIS
 TIME AND ADDITIONAL PLAN REVIEW COMMENTS MAY BE
 GENERATED UPON THE RE-REVIEW OF SUBMITTED CORRECTIONS.
  
 1) YOU RISER DIAGRAM DOES NOT MATCH THE ONE OF
 FILE.SUBMIT AN ISOMETRIC DRAWING THAT CLEARLY SHOWS THE
 LENGTH OF ALL CUT SECTIONS OF PIPE PER 2014 FBC-FUEL
 GAS, SECS. 402.4.1, 402.4.2. OR 2014 FBC-RES SEC. G2413
  
 2) LIST THE BTU LOAD OF EACH APPLIANCE AND THE TOTAL
 BTU LOAD ON THE SYSTEM. REFER TO THE 2014 FBC-FUEL GAS
 SECS.401.8 THRU 402.6.1 AND TABLES 402.4 (1) THRU 402.4
 (37) OR 2014 FBC-RES. SEC. G2413
  
 3) SHOW THE DISTANCE FROM THE POINT OF DELIVERY, (GAS
 METER / MP REGULATOR / LP TANK) TO THE MOST REMOTE
 OUTLET IN THE BUILDING AND / OR SYSTEM PER THE 2014
 FBC-FUEL GAS SEC.402.4.1 OR 2014 FBC-RES. SEC. G 2413.3
  
 4) SUBMIT MANUFACTURER?S SPECIFICATION SHEETS /
 INSTALLATION MANUAL FOR ALL GAS EQUIPMENT TO VERIFY
 COMPLIANCE WITH STANDARDS NFPA 54, NFPA 58, AND
 FBC-2014 FUEL GAS CODE SEC. 402.2, AND 301.3 OR 2014
 FBC-RES. SEC. G2404.3. GAS APPLIANCES SHALL BE LISTED
 AND LABELED. THE INSTALLATION MANUALS FOR ALL GAS
 APPLIANCES / EQUIPMENT SHALL BE ONSITE AT THE TIME OF
 INSPECTION. FGC SEC.305.1, FBC-RES. SEC.G2408.1.
  
 5) SUBMIT TWO COPIES OF THE APPLICABLE SIZING TABLES
 USED TO SIZE THE GAS SYSTEM OR PLACE A NOTE ON THE
 PLANS/DRAWINGS SPECIFYING WHICH SIZING TABLE(S) FROM
 THE GAS CODE OR OTHER STANDARD THAT WERE USED IN THE
 DESIGN OF THIS GAS SYSTEM. REFER TO THE 2014 FBC-FUEL
 GAS SECS. 401.4, 401.8 THRU 402.6.1 AND TABLES 402.4
 (1) THRU 402.4 (37) OR 2014 FBC-RES. SEC. G2412.4,
 G2412.8, G2413.1, G2413.2, & G2413.3.
  
 6) SHOW THE LOCATION OF ALL MP (STEP-DOWN) REGULATORS
 DIASTANCE IF ONE ALREADY EXIST TO THE FIRE PIT. A
 LISTED SHUTOFF VALVE SHALL BE INSTALLED IMMEDIATELY
 AHEAD OF EACH MP REGULATOR. FBC-FUEL GAS SEC.409.4,
 FBC-RESIDENTIAL SEC. G 2420.4.
  
 7) SHOW THE DISTANCE FROM THE 2 PSI REGULATOR TO THE
 APPLIANCE. COMPLY WITH 2014 FBC-FUEL GAS TABLE 402.4
 (28) FOR THE PROPER PIPE SIZE AND BTU LOAD.
  
 TIM HUNT
 PLUMBING INSPECTOR / PLUMBING PLAN REVIEWER
 CITY OF WEST PALM BEACH DEVELOPMENT SERVICES DEPARTMENT
 BUILDING DIVISION
 561-805-6695
 [email protected]
  