| 2018-01-22 16:13:10 | 2ND REVIEW: FBC 2014 5TH EDITION |
| | |
| | PLUMBING COMMENTS: PREVIOUS COMMENT NOT COMPLIED |
| | |
| | 1. THE VALUATION OF THE THE JOB IS LOW PLEASE PROVIDE A |
| | SIGNED PROPOSAL OF WORK OR CONTRACT. PER WPB AEND TO |
| | FBC 109.3 BUILDING PERMIT VALUATIONS. IF, IN THE |
| | OPINION OF THE BUILDING OFFICIAL, THE CLAIMED VALUATION |
| | OF |
| | BUILDING, ALTERATION, STRUCTURE, ELECTRICAL, GAS, |
| | MECHANICAL OR PLUMBING SYSTEMS APPEARS TO BE |
| | UNDERESTIMATED ON THE APPLICATION, THE PERMIT SHALL BE |
| | DENIED, UNLESS THE APPLICANT CAN SHOW |
| | DETAILED, QUANTITY ESTIMATES, AND/OR BONA FIDE SIGNED |
| | CONTRACTS (EXCLUDING LAND VALUE) TO MEET THE |
| | APPROVAL OF THE BUILDING OFFICIAL. FOR PERMITTING |
| | PURPOSES, VALUATION OF BUILDINGS AND SYSTEMS SHALL |
| | BE TOTAL REPLACEMENT VALUE TO INCLUDE STRUCTURAL, |
| | ELECTRIC, PLUMBING, MECHANICAL, INTERIOR FINISH, |
| | RELATIVE SITE WORK, ARCHITECTURAL AND DESIGN FEES, |
| | MARKETING COSTS, OVERHEAD AND PROFIT; EXCLUDING |
| | ONLY LAND VALUE. VALUATION REFERENCES MAY INCLUDE THE |
| | LATEST PUBLISHED DATA OF NATIONAL CONSTRUCTION |
| | COST ANALYSIS SERVICES (MARSHALL-SWIFT, MEANS, ETC.), |
| | AS PUBLISHED BY INTERNATIONAL CODE CONGRESS. |
| | FINAL BUILDING PERMIT VALUATION SHALL BE SET BY THE |
| | BUILDING OFFICIAL. |
| | |
| | |
| | |
| | PLEASE NOTE THAT SUBMITTAL OF ADDITIONAL AND/OR REVISED |
| | MATERIALS MAY RESULT IN NEW PLAN REVIEW COMMENTS. |
| | WHEN RESUBMITTING, IT IS HELPFUL TO PROVIDE A RESPONSE |
| | LETTER ADDRESSING EACH ITEM ALONG WITH THE CITY |
| | RE-SUBMITTAL FORM. PLEASE, ADDITIONALLY, INSERT |
| | CORRECTED PAGES INTO TO SUBMITTAL AND REMOVE OR VOID |
| | THE PREVIOUSLY REVIEWED SHEETS. |
| | |
| | GEORGE JOHNSON |
| | PLUMBING PLANS EXAMINER |
| | CITY OF WEST PALM BEACH |
| | 561-805-6711 |
| | [email protected] |
| | |