| Date |
Text |
| 2018-01-05 09:42:57 | 2ND REVIEW: FBC 2014 5TH EDITION |
| | |
| | PLUMBING COMMENTS: PREVIOUS COMMENTS NOT COMPLIED. TO |
| | EXPEDITE APPROVAL I SUGGEST A MEETING TO GO OVER |
| | COMMENTS SEE MY CONNECT INFO BELOW. |
| | |
| | PARTIALLY COMPLIED 3) INDICATE HOW THE MED GAS TANKS |
| | WILL BE SECURED AND PROTECTED FORM DAMAGE- SECTION |
| | 5.1.3.3.2(7) NFPA 99. PLEASE PROVIDE MANUFACTURE |
| | SPECIFICATION SHEETS FOR CYLINDER BRACKETS AND A DETAIL |
| | SHOWING HOW THEY WILL BE SECURED TO THE WALL . PER WPB |
| | AMEND TO FBC 107.2.1 |
| | |
| | PARTIALLY COMPLIED 16) SHT. A1.6 - CLARIFY THE ACRONYMS |
| | "LDV" AND "HDV" ON THE VACUUM SYSTEM. IS THE LOW DUTY |
| | AND HIGH DUTY THE SAME AS LOW PERSSURE AND HIGH |
| | PRESSURE PLEASE CLARIFY ON PLAN. PER WPB AMEND TO FBC |
| | 107.2.1 |
| | |
| | PARTIALLY COMPLIED 17) SHT. A1.7 - SUBMIT A MINIMUM OF |
| | TWO COPIES OF THE MANUFACTURER'S PRE-INSTALLATION GUIDE |
| | FOR THE VACUUM PIPING SYSTEM TO BE PROVIDED BY A HENRY |
| | SCHEIN EQUIPMENT SALES SPECIALIST AS REFERENCED IN THE |
| | FIRST NOTE IN THE VACUUM SYSTEM NOTES ON THIS DRAWING |
| | PAGE. WPB AMEND. TO FBC SEC.107.2.1. NO SPECS PROVIDED. |
| | PLEASE SPECIFY ON PLAN EXACTLY WHAT TYPE OF PIPE AND |
| | FITTINGS WILL BE USED FOR VACUUM SYSTEM. RIGHT NOW IT |
| | SAYS USE PVC , EXPERT WHERE PROHIBITED, THE CEILING IS |
| | INDICATED AS AN AIR PLENUM, CLARIFY ONE TYPE OF PIPE. |
| | PER WPB AMEND TO FBC 107.2.1 |
| | |
| | PARTIALLY COMPLIED 25) A BACKFLOW PREVENTER IS REQUIRED |
| | ON THE WATER SUPPLY AT THE BEVERAGE COUNTER AND ICE |
| | MAKER. 2014 FBC-PLUMBING SEC.608.16.10. SHOW ON RISER |
| | DIAGRAM AND PROVIDE SCHEDULE FOR BACFLOW DEVISE AND AIR |
| | HAMMER ARRESTORS. PER WPB AMEND TO FBC 107.2.1 |
| | |
| | PARTIALLY COMPLIED 26) A WATER HAMMER ARRESTOR |
| | CONFORMING TO ASSE 1010 SHALL BE INSTALLED WHERE |
| | QUICK-CLOSING VALVES ARE UTILIZED ON THE WATER |
| | DISTRIBUTION SYSTEM.2014 FBC-PLUMBING SEC. 604.9. SHOW |
| | ON RISER DIAGRAM AND PROVIDE SCHEDULE FOR BACFLOW |
| | DEVISE AND AIR HAMMER ARRESTORS. PER WPB AMEND TO FBC |
| | 107.2.1 |
| | |
| | PARTIALLY COMPLIED 27) SHT. P001 - NOTE #16 REFERS TO |
| | SHT. A1.6 FOR A DETAIL OF A SEDIMENT TRAP. THERE IS NO |
| | DETAIL ON SHT. A1.6. PLAN SHOWS PT MANUFACTURE SPECS |
| | SHOWS BT PLEASE CLARIFY. PER WPB AMEND TO FBC 107.2.1 |
| | |
| | PARTIALLY COMPLIED 29) THE HOT WATER RECIRCULATION |
| | SYSTEM SHALL COMPLY WITH THE 2014 FBC-PLUMBING |
| | SEC.607.5 FOR THE REQUIRED PIPE INSULATION. PLACE NOTE |
| | ON PLUMBING SHEETS REFERRING TO MECHANICAL SPEC-AND |
| | SHEET NUMBER. PER WPB AMEND TO FBC 107.2.1 |
| | |
| | NEW COMMENTS: |
| | |
| | 1. SHT. P003 SHOWS 2 TYPE "N" TANKS, 114 LB AND 200CF. |
| | SHT. P301 NOTE #11 SHOWS 2 TYPE "G" TANKS OX.@ 251CF, |
| | 21LB AND NO.@ 498CF, 57LB PLEASE CLARIFY. PER WPB AMEND |
| | TO FBC 107.2.1 |
| | |
| | 2. SHT. P301 THE EXHAUSTS FROM A VACUUM PUMP SERVING A |
| | VACUUM (FLUID SUCTION) SYSTEM SHALL DISCHARGE |
| | SEPARATELY TO OPEN AIR ABOVE THE ROOF. PER FBC PL 713.6 |
| | |
| | 3. SHT.P301 NOTE #10 IS NOT SHOWN ON THE FLOOR PLAN |
| | PLEASE CLARIFY . PER WPB AMEND TO FBC 107.2.1 |
| | |
| | 4. SHT. P201 # 9+10 ARE SHOWN ON FLOOR PLAN BUT THERE |
| | NOT SHOWN ON THE NOTES PLEASE CLARIFY. PER WPB AMEND TO |
| | FBC 107.2.1 |
| | |
| | 5. SHT. P201 WHAT IS #7 ON THE FLOOR PLAN IT DOES NOT |
| | MATCH THE NOTE PLEASE CLARIFY. PER WPB AMEND TO FBC |
| | 107.2.1 |
| | |
| | 6. THE WASHING MACHINE SHALL HAVE A 3" BRANCH DRAIN. |
| | PER FBC PL 406.2 |
| | |
| | 7. THE WASHING MACHINE SHALL DISCHARGE THROUGH A LINT |
| | TRAP. PER FBC PL 1003.6 |
| | |
| | 8. THE DRAIN FROM THE VACUUM PUMP TANKS SHALL CONNECT |
| | DIRECTLY TO THE SANITARY SYSTEM NO INDIRECT WASTE. |
| | PROVIDE DETAIL FOR DRAINAGE CONNECTION OF VACUUM |
| | SYSTEM. PER FBC PL 713.7 AND WPB AMEND TO FBC 107.2.1 |
| | |
| | 9. THE FLOOR DRAINS AND FLOOR SINK ARE REQUIRED TO HAVE |
| | TRAP PRIMER VALVES. PER FBC PL 1002.4 |
| | |
| | 10. SHT. P001 IN THE SCHEDULE GT-1 IS NOT SHOWN ON PLAN |
| | WHAT IS THIS USED FOR PLEASE CLARIFY. PER WPB AMEND TO |
| | FBC 107.2.1 |
| | |
| | 11. SHT. P101 NOTE #3 THE 2" HUB DRAIN FOR THE VISTA |
| | FILTER SYSTEM IS NOT SHOWN ON THE RISER DIAGRAM NEITHER |
| | IS THE TRAP FOR THE VACUUM SYSTEM DRAIN. PLEASE |
| | CLARIFY. PER WPB AMEND TO FBC 107.2.1 |
| | |
| | 12. SHT. P003 ON THE MED GAS RISER IT SHOWS A HIGH |
| | PRESSURE VACUUM PUMP PLEASE CLARIFY. PER WPB AMEND TO |
| | FBC 107.2.1 |
| | |
| | 13. SHT. A1.7 ON THE SCHEDULE IT SHOWS 13, 13A, 13B, |
| | 13C, AND 15A CONNECTING TO NATURAL GAS WHICH STATES NOT |
| | USED. PLEASE CLARIFY. PER WPB AMEND TO FBC 107.2.1 |
| | |
| | 14. SHT. A1.7 PLEASE PROVIDE DRAWINGS BY HENRY SCHIEN |
| | OR REMOVE NOTE FROM PLAN. PLEASE CLARIFY. PER WPB AMEND |
| | TO FBC 107.2.1 |
| | |
| | |
| | PLEASE NOTE THAT SUBMITTAL OF ADDITIONAL AND/OR REVISED |
| | MATERIALS MAY RESULT IN NEW PLAN REVIEW COMMENTS. |
| | WHEN RESUBMITTING, IT IS HELPFUL TO PROVIDE A RESPONSE |
| | LETTER ADDRESSING EACH ITEM ALONG WITH THE CITY |
| | RE-SUBMITTAL FORM. PLEASE, ADDITIONALLY, INSERT |
| | CORRECTED PAGES INTO TO SUBMITTAL AND REMOVE OR VOID |
| | THE PREVIOUSLY REVIEWED SHEETS. |
| | |
| | GEORGE JOHNSON |
| | PLUMBING PLANS EXAMINER |
| | CITY OF WEST PALM BEACH |
| | 561-805-6711 |
| | [email protected] |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |