| 2018-06-14 18:13:49 | 1ST REVIEW: FBC 2017 6TH EDITION |
| | |
| | PLUMBING COMMENTS: |
| | |
| | 1. AT LEAST ONE OF THE WORK SINKS SHALL COMPLY WITH FBC |
| | ACC 212.3 , 606 |
| | |
| | 2. WHAT SINK IS THE WATER HEATER DRAIN PAN DISCHARGING |
| | INTO PLEASE CLARIFY. PER WPB AMEND TO FBC 107.2.1 |
| | |
| | 3. PROVIDE 2 COPIES OF THE MANUFACTURE SPECIFICATIONS |
| | OF THE WET TABLE IN THE VICHY SHOWER AND THE HAIR |
| | WASHING CHAIR SINK ONLY ONE WAS PROVIDED ALSO THE |
| | SHOWER VALVE. PER WPB AMEND TO FBC 107.2.1 |
| | |
| | 4. THE HAIR WASH SINK SHALL BE EQUIPPED WITH A VACUUM |
| | BREAKER. PER FBC PL 608.2 |
| | |
| | 5. ALL VALVES SHALL COMPLY WITH NSF 372 LEAD FREE . PER |
| | FBC PL 605.2.1 |
| | |
| | 6. SHT. P-3 DETAIL I THE SHOWER LINER SHALL BE PITCHED |
| | TO TH DRAIN. PER FBC PL 417.5.2 |
| | |
| | 7. THE LAVATORY IN THE BATHROOM SHALL COMPLY WITH |
| | TEMPERED WATER SHALL BE DELIVERED FROM LAVATORIES AND |
| | GROUP WASH FIXTURES LOCATED IN PUBLIC TOILET FACILITIES |
| | PROVIDED FOR CUSTOMERS, PATRONS AND VISITORS. TEMPERED |
| | WATER SHALL BE DELIVERED THROUGH AN APPROVED |
| | WATER-TEMPERATURE LIMITING DEVICE THAT CONFORMS TO ASSE |
| | 1070 OR CSA B125.3.PER FBC PL 416.5 |
| | |
| | PLEASE NOTE THAT SUBMITTAL OF ADDITIONAL AND/OR REVISED |
| | MATERIALS MAY RESULT IN NEW PLAN REVIEW COMMENTS. |
| | WHEN RESUBMITTING, IT IS HELPFUL TO PROVIDE A RESPONSE |
| | LETTER ADDRESSING EACH ITEM ALONG WITH THE CITY |
| | RE-SUBMITTAL FORM. PLEASE, ADDITIONALLY, INSERT |
| | CORRECTED PAGES INTO TO SUBMITTAL AND REMOVE OR VOID |
| | THE PREVIOUSLY REVIEWED SHEETS. |
| | |
| | GEORGE JOHNSON |
| | PLUMBING PLANS EXAMINER |
| | CITY OF WEST PALM BEACH |
| | 561-805-6711 |
| | [email protected] |
| | |