| Date |
Text |
| 2017-09-27 12:14:42 | ****CORRECTIONS**** |
| | |
| | SAMANTHA HILL |
| | BUILDING PLANS EXAMINER |
| | [email protected] |
| | 561-805-6724 |
| | |
| | FBC = FLORIDA BUILDING CODE, 5TH EDITION (2014) |
| | FBC B = FBC BUILDING |
| | FBC EB = FBC EXISTING BUILDING |
| | FBC A = FBC ACCESSIBILITY |
| | FBC EC = FBC ENERGY CONSERVATION |
| | |
| | COMMENT FROM FIRST REVEW: |
| | |
| | 1. FOR THE FLOORING UNDERLAYMENT, PROVIDE THE FOLLOWING |
| | TEST REPORTS. IT IS RECOMMENDED THAT THIS BE RESOLVED |
| | VIA EMAIL PRIOR TO RESUBMITTAL. EMAIL THE NAME OF THE |
| | UNDERLAYMENT PROPOSED TO [email protected]. IF THE |
| | MANUFACTURER HAS ALREADY PROVIDED THE REQUIRED TEST |
| | REPORTS DIRECTLY TO US, TEST REPORTS DO NOT NEED TO BE |
| | SUBMITTED WHEN RESUBMITTING. |
| | |
| | PLEASE NOTE THAT TEST REPORTS ARE REQUIRED - |
| | MANUFACTURER SPEC SHEETS ARE NOT ACCEPTABLE DUE TO |
| | DISCREPANCIES BETWEEN SPEC SHEETS/BROCHURES AND TEST |
| | REPORTS FOR SOME MANUFACTURERS (NOT NECESSARILY THE |
| | MANUFACTURER SELECTED; THIS IS A GENERAL COMMENT) |
| | |
| | A. FBC 1207.2, FLOOR/CEILING ASSEMBLIES SEPARATING |
| | DWELLING UNITS FROM EACH OTHER OR FROM PUBLIC OR |
| | SERVICE AREAS SHALL HAVE A SOUND TRANSMISSION CLASS |
| | (STC) OF NOT LESS THAN 50 (45 IF FIELD TESTED) FOR AIR |
| | BORNE NOISE WHEN TESTED IN ACCORDANCE WITH ASTM E 90. |
| | THE TEST REPORT CANNOT INCLUDE A DROPPED GYPSUM |
| | CEILING. PROVIDE A COPY OF THE TEST REPORT. |
| | |
| | B. FBC 1207.3, FLOOR/CEILING ASSEMBLIES BETWEEN |
| | DWELLING UNITS OR BETWEEN A DWELLING UNIT AND A PUBLIC |
| | OR SERVICE AREA WITHIN THE STRUCTURE SHALL HAVE AN |
| | IMPACT INSULATION CLASS (IIC) RATING OF NOT LESS THAN |
| | 50 (45 IF FIELD TESTED) WHEN TESTED IN ACCORDANCE WITH |
| | ASTM E 492. THE TEST REPORT CANNOT INCLUDE A DROPPED |
| | GYPSUM CEILING. PROVIDE A COPY OF THE TEST REPORT. |
| | |
| | C. FBC 603.1, ALLOWABLE MATERIALS IN NON COMBUSTIBLE |
| | BUILDINGS, SEE ITEM 2, EXCEPTION 2, ACOUSTICAL |
| | INSULATION INSTALLED BETWEEN A FINISHED FLOOR AND SOLID |
| | DECKING WITHOUT INTERVENING AIRSPACE SHALL BE ALLOWED |
| | TO HAVE A FLAME SPREAD INDEX OF NOT MORE THAN 200. SEE |
| | 803.1.1, PROVIDE TEST DATA IN ACCORDANCE WITH ASTM E 84 |
| | OR UL 723. |
| | |
| | 2ND REVIEW - SPEC SHEET FOR PROFLEX MSC 90 WAS |
| | SUBMITTED. A LETTER DATED 8/27/14 FROM PROFLEX TO ME |
| | STATED THAT THEY DO NOT HAVE THE STC/IIC TESTS WITHOUT |
| | A DROPPED CEILING. |
| | |
| | WE DO HAVE THE TEST REPORTS FOR PROFLEX SUPERSIM 90 ON |
| | FILE. |
| | |
| | NEW COMMENT: |
| | |
| | 2. VALUE IS TOO LOW FOR THE WORK PROPOSED, FBC 109. ALL |
| | PLANS RELATED TO THE PROPOSED RENOVATION ARE TO BE |
| | SUBMITTED WITH THIS SUBMITTAL AND THE VALUE OF ALL |
| | IMPROVEMENTS ARE TO BE INCLUDED, INCLUDING |
| | SUBCONTRACTORS AND MATERIAL PROVIDED BY OTHERS. |
| | |
| | 3. A LETTER STATES THAT "A CHASE IS BEING RAISED". THE |
| | PROPOSED WORK IS NOT SHOWN ON THE PLANS, NO DETAIL |
| | PROVIDED. FBC 107, PLANS ARE TO SHOW SCOPE AND NATURE |
| | OF PROPOSED WORK. THE INDIVIDUAL TAKING RESPONSIBILITY |
| | FOR THE DESIGN IS TO SIGN THE PLAN. DEPENDING ON THE |
| | QUALITY OF THE RESUBMITTAL, IT IS POSSIBLE THAT A |
| | DESIGN PROFESSIONAL WILL BE REQUIRED TO PROVIDE A PLAN. |
| | |