| 2017-08-28 14:24:40 | 2ND REVIEW COMMENTS |
| | |
| | THIS PLAN WAS REVIEWED AND FAILED BY PETER LEDUC, FIRE |
| | MARSHAL, WITH THE FOLLOWING COMMENTS: |
| | |
| | THIS REVIEW AND THE COMMENTS ARE RELATED TO THE |
| | FOUNDATION PERMIT ONLY. |
| | |
| | |
| | 1) SHEET 2 OF 8 - THERE ARE NO INDICATION HOW THE |
| | EXISTING REQUIRED EXITING, INCLUDING WALKWAY AND |
| | STAIRS, WILL BE MAINTAINED DURING DEMO AND ALL PHASES |
| | OF CONSTRUCTION. |
| | |
| | NOT COMPLIED. YOUR COMMENTS THAT A DETAILED LIFE SAFETY |
| | PLAN WAS SUBMITTED COULD NOT BE FOUND. |
| | |
| | THE LIFE SAFETY PLAN SHALL INCLUDED THE EXIT PATH FROM |
| | ALL SOUTH END EXITS, INCLUDING THE STAIRS FROM THE 2 ND |
| | FL, THE TRAVEL PATH LEADING TO A POINT OF PUBLIC WAY, |
| | THESE PLANS SHALL INCLUDE EXIT WIDTH, ELEVATION |
| | CHANGES, EXIT SIGNAGE, SEPARATION MEASURES FROM |
| | CONSTRUCTION. |
| | |
| | THESE ITEMS WERE DISCUSSED AT LENGTH DURING A MEETING |
| | WITH THE AHRENS TEAM. |
| | |
| | PLEASE PROVIDE A DETAILED LIFE SAFETY PLAN INDICATING |
| | HOW AND WHERE THE EXITING FROM THE CURRENT BUILDING |
| | WILL BE MAINTAINED AND PROTECTED. |
| | |
| | |
| | |
| | |
| | 2) SHEET 7 OF 8 - THE FIRE LINE APPEARS TO BE UNDER THE |
| | FOUNDATION. PER NFPA 24 THIS IS A VIOLATION OF THE |
| | REQUIRERMENT. |
| | |
| | NOT COMPLIED. THERE IS NO DRAWING OR NOTE THAT SAYS THE |
| | FIRE LINE BEING MOVED. |
| | |
| | ADDITIONALLY, IT SHALL BE NOTED ON THE RESUBMITTAL THAT |
| | ALL UNDERGROUND WORK SHALL COMPLY WITH NFPA 24, |
| | STANDARD FOR THE INSTALLATION OF PRIVATE FIRE SERVICE |
| | MAINS AND THEIR APPURTENANCES, 2010 EDITION.AND BE DONE |
| | UNDER SEPARATE PERMIT BY CERTIFIED FLORIDA UNDERGROUND |
| | CONTRACTORS. NO FIRE LINE PIPE SHALL BE COVERED OVER |
| | PRIOR TO A FIRE INSPECTION. |
| | |
| | 10.6 PROTECTION AGAINST DAMAGE. |
| | 10.6.1 PIPE SHALL NOT BE RUN UNDER BUILDINGS. |
| | 10.6.2 WHERE PIPE MUST BE RUN UNDER BUILDINGS, SPECIAL |
| | PRECAUTIONS SHALL BE TAKEN, INCLUDING THE FOLLOWING: |
| | (1) ARCHING THE FOUNDATION WALLS OVER THE PIPE |
| | (2) RUNNING PIPE IN COVERED TRENCHES |
| | (3) PROVIDING VALVES TO ISOLATE SECTIONS OF PIPE UNDER |
| | BUILDINGS |
| | |
| | PLEASE REVIEW AND CORRECT. |
| | |
| | |
| | |
| | |
| | 3) WHEN RESUBMITTING, PLEASE PROVIDE PLAN SHEET |
| | REVISION CLOUDS OR NUMBERED NARRATIVE RESPONSES TO THE |
| | ABOVE. |
| | |
| | |
| | 4) ADDITIONAL COMMENTS MAY BE PROVIDED ON THE |
| | RE-SUBMITTAL OF THE ABOVE. |
| | |
| | |
| | PETER LEDUC |
| | FIRE MARSHAL |
| | 561-804-4709 |
| | [email protected] |
| | |