| 2017-08-29 15:55:17 | ****CORRECTIONS**** |
| | |
| | SAMANTHA HILL |
| | BUILDING PLANS EXAMINER |
| | [email protected] |
| | 561-805-6724 |
| | |
| | COMMENTS FROM PREVIOUS LIST: |
| | |
| | 1. THRESHOLD INSPECTION PLAN AND SOILS REPORT ARE |
| | PHOTOCOPIES; ORIGINALS REQUIRED FS471. |
| | |
| | 2ND REVIEW; THE THRESHOLD INSPECTION PLAN AND SOILS |
| | REPORT ARE ALSO (STILL) PHOTOCOPIES (NO NEW DOCUMENTS |
| | SUBMITTED). RESPONSE LETTER STATES "COMPLIED. MULTIPLE |
| | ORIGINALS HAVE BEEN SUBMITTED WITH THIS PROJECT'S |
| | PREVIOUS PERMIT SUBMISSION. PLEASE REFERENCE THE TWO |
| | COPIES SUBMITTED WITH THIS RE-SUBMISSION AND/OR WITH |
| | THE MAIN BUILDING PERMIT SET." |
| | |
| | FBC 107, APPLICANT IS TO PROVIDE ALL DOCUMENTS REQUIRED |
| | TO DETERMINE CODE COMPLIANCE. DOCUMENTS IN ANOTHER |
| | PERMIT APPLICATION CANNOT BE USED FOR THIS PERMIT. |
| | DOCUMENTS WITH ANOTHER PERMIT APPLICATION ARE NOT |
| | OFFICIAL PERMIT RECORD UNTIL ISSUANCE. DOCUMENTS |
| | PREPARED BY AN ENGINEER AND SUBMITTED FOR PUBLIC RECORD |
| | ARE TO BE SIGNED, SEALED, DATED ORIGINALS. PLEASE |
| | PROVIDE THE ORIGINAL DOCUMENTS REQUESTED. |
| | |
| | 2. SEE FIRE COMMENTS. ADVISE AS TO HOW EXITING FOR THE |
| | EXISTING SCHOOL WILL BE AFFECTED BY THE PROPOSED |
| | CONSTRUCTION. THIS INFORMATION IS REQUIRED PRIOR TO |
| | COMMENCEMENT OF ANY WORK AFFECTING THE EXIT AND EXIT |
| | DISCHARGE FOR EXISTING SCHOOL. |
| | |
| | 2ND REVIEW, SEE FIRE REVIEW. |
| | |
| | NEW COMMENTS: |
| | |
| | 3. AN ENTIRELY NEW SET OF PLANS WAS SUBMITTED. THE |
| | STRUCTURAL PAGES ARE NOT SIGNED, SEALED, DATED |
| | ORIGINALS (PHOTOCOPIES), SEE FS 471. |
| | |
| | 4. PLEASE REMOVE SHEETS NOT REQUIRED FOR THIS |
| | FOUNDATION SUBMITTAL. FOR INSTANCE: |
| | |
| | CIVIL SHEET 5, PAVING AND DRAINAGE DETAILS |
| | A0.05, SECOND FLOOR LIFE SAFETY PLAN - SOUTH |
| | A0.16 WINDOW ELEVATIONS |
| | |
| | IT APPEARS THAT A FULL SET OF PLANS FOR THE BUILDING |
| | WAS SUBMITTED. PAGES NOT NEEDED FOR FOUNDATION SHOULD |
| | BE REMOVED. GENERALLY, DOCUMENTS REQUIRED FOR |
| | FOUNDATION PERMIT ARE: |
| | |
| | PERMIT APPLICATION WHICH STATES SCOPE (FOR FOUNDATION |
| | PERMIT, TYPICALLY FOOTINGS OR FOOTINGS AND SLAB) |
| | GEOTECHNICAL REPORT |
| | SURVEY DRAWING |
| | STORM WATER POLLUTION PREVENTION PLAN |
| | SITE PLAN |
| | 1ST FLOOR ARCHITECTURAL PLAN |
| | ARCHITECTURAL CROSS SECTION(S) OF THE BUILDING |
| | FOUNDATION PLAN |
| | FOUNDATION DETAILS AND CROSS SECTIONS |
| | STRUCTURAL ENGINEER'S GENERAL NOTES |
| | UNDERGROUND PLUMBING PLAN (IF APPLICABLE) |
| | ELECTRICAL PLAN SHOWING ANY UNDERGROUND CONDUIT (IF |
| | APPLICABLE) |
| | ELECTRICAL GROUNDING TO STEEL DETAIL, IF APPLICABLE (OR |
| | EXPLAIN WHY THIS IS NOT APPLICABLE FOR THIS PROJECT). |
| | IF REQUIRED, A DETAIL IS REQUIRED AS A REVIEW, PERMIT, |
| | AND INSPECTION ARE REQUIRED PRIOR TO CONCRETE POUR |
| | PLAN SHOWING UNDERGROUND FIRE LINE |
| | THRESHOLD INSPECTION PLAN OR RESIDENT INSPECTION PLAN |
| | (AS APPLICABLE) |
| | SI OR RESIDENT INSPECTOR AGREEMENT (AS APPLICABLE) |
| | |
| | 5. THREE COMPLETE IDENTICAL SETS OF PLANS AND PERMIT |
| | DOCUMENTS REQUIRED, FBC 107. |
| | |
| | 6. THIS PERMIT WILL BE ISSUED WITH PROVISO: |
| | |
| | PERMIT IS ISSUED AT APPLICANT'S RISK |
| | |
| | A. FBC 105.13 PHASED PERMIT APPROVAL. AFTER SUBMITTAL |
| | OF THE APPROPRIATE CONSTRUCTION DOCUMENTS, THE BUILDING |
| | OFFICIAL IS AUTHORIZED TO ISSUE A PERMIT FOR THE |
| | CONSTRUCTION OF FOUNDATIONS OR ANY OTHER PART OF A |
| | BUILDING OR STRUCTURE BEFORE THE CONSTRUCTION DOCUMENTS |
| | FOR THE WHOLE BUILDING OR STRUCTURE HAVE BEEN |
| | SUBMITTED. THE HOLDER OF SUCH PERMIT FOR THE FOUNDATION |
| | OR OTHER PARTS OF A BUILDING OR STRUCTURE SHALL PROCEED |
| | AT THE HOLDER?S OWN RISK WITH THE BUILDING OPERATION |
| | AND WITHOUT ASSURANCE THAT A PERMIT FOR THE ENTIRE |
| | STRUCTURE WILL BE GRANTED. CORRECTIONS MAY BE REQUIRED |
| | TO MEET THE REQUIREMENTS OF THE TECHNICAL CODES. THIS |
| | PROVISION IS ONLY FOR THE FLORIDA BUILDING CODE, ALL |
| | OTHER AGENCY APPROVALS NECESSARY FOR CONSTRUCTION MUST |
| | BE SECURED PRIOR TO THIS PROVISION BEING APPLIED. |
| | |
| | B. REPLAT TO BE RECORDED PRIOR TO C.O. |
| | |
| | C. LIFE SAFETY AND OTHER ITEMS NOT REVIEWED; INTERIOR |
| | WILL BE REVIEWED UNDER THE BUILDING PERMIT. |
| | |
| | D. REVISE PLAN; THE ASSEMBLY SPACES ARE FOR USE BY THE |
| | SCHOOL ONLY AND NO OTHER ENTITIES. |
| | |
| | |