| Date |
Text |
| 2017-07-24 15:03:10 | 1) SHOW THE SPACING BETWEEN THE FUEL TANKS. COMPLY WITH |
| | NFPA 30, SEC. 15.3 & TABLE 15.3.WPB AMEND. TO FBC SEC. |
| | 107.2.1. |
| | 2) LABEL ALL DROP PIPES ENTERING THE TANKS.( THERE IS A |
| | DROP PIPE IN THE GASOLINE TANK THAT IS LOCATED BETWEEN |
| | THE DISPENSER AND FUEL FILL PORT AND ALSO IN THE DIESEL |
| | TANK LOCATED IN THE LEFT SIDE OF THE TANK NEXT TO THE |
| | CLOCK GAUGE THAT IS NOT IDENTIFIED.)WPB AMEND. TO FBC |
| | SEC. 107.2.1. |
| | 3) SHOW THE SIZE OF ALL VENTS & THE WITHDRAWL |
| | CONNECTIONS / DROP TUBES ON EACH TANK. WPB AMEND. TO |
| | FBC SEC. 107.2.1. |
| | 4) SUBMIT MANUFACTURER'S SPECIFICATIONS FOR BOTH |
| | TANKS.WPB AMEND. TO FBC SEC. 107.2.1. |
| | 5) INDICATE THE TYPE OF PIPE MATERIAL USED FOR THE TANK |
| | VENTS. MATERIALS SHALL COMPLY WITH NFPA 30 SEC. 27.4.1 |
| | & ASME B31. |
| | 6) EACH CONNECTION TO AN ABOVE GROUND TANK THROUGH |
| | WHICH LIQUID CAN NORMALLY FLOW SHALL BE PROVIDED WITH |
| | AN INTERNAL OR AN EXTERNAL VALVE LOCATED AS CLOSE AS |
| | PRACTICAL TO THE SHELL OF THE TANK PER NFPA 30 |
| | SEC.22.13.2. ( REFER TO DISPENSER LINES. |
| | 7) INSTALLATION INSTRUCTIONS FOR ABOVE GROUND STORAGE |
| | TANKS. - FACTORY-BUILT ABOVEGROUND TANKS SHALL BE |
| | PROVIDED WITH INSTRUCTIONS FOR TESTING THE TANKS AND |
| | FOR INSTALLATION OF THE NORMAL AND EMERGENCY VENTS. |
| | NFPA 30 SEC. 22.16. |
| | 8) SUBMIT A KEY PLAN AND SITE PLAN SHOWING THE LOCATION |
| | OF THE FUEL TANKS AND THE DISTANCES FROM ANY ADJOINING |
| | BUILDINGS. WPB AMEND. TO FBC SEC. 107.2.1. |
| | 9) IF THESE TANKS WILL BE EXPOSED TO ANY TYPE OF |
| | VEHICULAR TRAFFIC THEN COLLISION PROTECTION SHALL BE |
| | PROVIDED PER NFPA 30 SEC.22.15. CLARIFY. |
| | 10) STATIC ELECTRICITY. - MEANS SHALL BE PROVIDED TO |
| | MINIMIZE GENERATION OF STATIC ELECTRICITY PER NFPA 30 |
| | SEC. 18.5.2.2. SUCH MEANS SHALL MEET THE REQUIREMENTS |
| | OF NFPA 30 SEC.6.5.4. |
| | 11) SUBMIT MANUF. SPECIFICATIONS FOR THE HOSES, |
| | DISPENSERS, VALVES, ETC. PIPING, VALVES AND FITTINGS |
| | SHALL COMPLY WITH NFPA 30 CHAPTER 27. |
| | 12) WHERE PUMPS ARE USED FOR LIQUID TRANSFER, MEANS |
| | SHALL BE PROVIDED TO DEACTIVATE LIQUID TRANSFER IN THE |
| | EVENT OF A LIQUID SPILL OR FIRE PER NFPA 30 SEC. |
| | 18.5.2.3. |
| | 13) IF HOSE IS USED IN THE TRANSFER OPERATION, IT SHALL |
| | BE EQUIPPED WITH A SELF-CLOSING VALVE WITHOUT A |
| | HOLD-OPEN LATCH IN ADDITION TO THE OUTLET VALVE. ONLY |
| | LISTED OR APPROVED HOSE SHALL |
| | BE USED. NFPA 30 SEC. 18.5.2.1. |
| | |
| | |
| | TIM LARGE |
| | CHIEF PLUMBING INSPECTOR |
| | PLUMBING PLAN REVIEW |
| | 561-805-6692 |
| | [email protected] |
| | |
| | |
| | |