| 2017-09-05 12:29:49 | CODES IN EFFECT: |
| | FBC = FLORIDA BUILDING CODE 2014 5TH EDITION |
| | FBC CE = FLORIDA BUILDING CODE ENERGY CONSERVATION 2014 |
| | 5TH EDITION |
| | FBC RE = FLORIDA RESIDENTIAL CODE 2014 5TH EDITION, |
| | PART VIII ELECTRICAL |
| | NEC = NFPA 70 2011 EDITION, NATIONAL ELECTRICAL CODE |
| | FS = FLORIDA STATUTES |
| | |
| | ELECTRICAL REVIEW STATUS: DENIED, SEE COMMENTS BELOW. |
| | |
| | 1. ADDRESS NUMBER ON PERMIT APPLICATION IS 2191, ON |
| | COVER SHEET IS 2181, AND ON ELECTRICAL SHEETS IS 2180. |
| | PROVIDE CORRECT ADDRESS ON PLANS. FBC 107.2.1 |
| | 2. SHEET E-8 SHOWS 6 SETS OF 750 KCMIL CU FOR SERVICE |
| | FEEDERS, WHILE SHEET E-6 SHOWS 7 SETS OF 600 KCMIL CU. |
| | CORRECT DISCREPANCY. FBC 107.2.1 |
| | 3. LOAD CALCULATION FOR MDP SHOWS SEVERAL DIFFERENT |
| | CALCULATIONS (ONE STORY, TWO STORY, ETC.). PROVIDE LOAD |
| | CALCULATION RELATED TO THIS PERMIT ONLY FOR THE SIX |
| | STORY BUILDING. REMOVE ALL OTHER UNRELATED INFORMATION. |
| | ADDITIONALLY, THE LOAD VA SHOWN FOR THE 1 BEDROOM UNIT |
| | IS THE SAME AS FOR THE 2 BEDROOM UNIT. LOAD CALCULATION |
| | FOR PANEL H IS DIFFERENT THAN LISTED IN PANEL SCHEDULE. |
| | PROVIDE CORRECTIONS. NEC 220; FBC 107.2.1 |
| | 4. PANEL H SHOWS A JOCKEY PUMP ON CIRCUIT 19, 21, 23. |
| | IS THIS THE JOCKEY PUMP FOR THE FIRE PUMP SYSTEM? IF |
| | SO, THIS CANNOT BE FEED FROM PANEL H. THE JOCKEY PUMP |
| | SPECIFIED ON SHEET FP 2.0 IS NOT SHOWN ON RISER DIAGRAM |
| | WITH FIRE PUMP. PROVIDE CORRECTION. NEC 215.5, |
| | 695.4(B)(3); FBC 107.2.1 |
| | 5. FIRE PUMP SERVICE IS NOT LABELED AS ONE OF THE MAINS |
| | FOR THE BUILDING. PROVIDE CORRECTION. NEC 230.2(E) |
| | 6. PANEL H LOAD CALCULATION STATES THAT THE FIRST 10K |
| | VA ARE AT 100%. HOWEVER, THE LOAD SHOWN IS 4320 VA, NOT |
| | 10,000. PANEL H1 LOAD CALCULATION IS SIMILARLY WRONG. |
| | PROVIDE CORRECTION. NEC 220.44 |
| | 7. PROVIDE DETAILS OF SECOND POWER SOURCE REQUIRED FOR |
| | FIRE PUMP. NEC 695.3(B) |
| | 8. PROVIDE LOAD CALCULATION FOR FIRE PUMP CONTROLLER |
| | AND ASSOCIATED EQUIPMENT TO VERIFY FEEDER, GROUNDING, |
| | AND OVERCURRENT PROTECTION REQUIREMENTS. NEC 695.6 |
| | 9. PLAN STATES THAT THE LOCKED ROTOR CURRENT FOR THE |
| | FIRE PUMP MOTOR IS 32.2 AMPS. ACCORDING TO TABLE |
| | 430.251(B), THE LOCKED ROTOR CURRENT FOR A MOTOR THIS |
| | SIZE SHOULD BE 179 AMPS. PROVIDE CORRECTION. NEC TABLE |
| | 430.251(B); FBC 107.2.1 |
| | 10. PLAN INCLUDES ELECTRICAL PLAN FOR 1ST FLOOR, 4TH |
| | FLOOR, AND ROOF ONLY. PROVIDE FULL SET OF PLANS FOR |
| | REVIEW. FBC 107.2.1, 107.3.5 |
| | |
| | PLEASE NOTE: SUBMITTAL OF ADDITIONAL AND/OR REVISED |
| | MATERIALS MAY RESULT IN NEW PLAN REVIEW COMMENTS. WHEN |
| | RESUBMITTING, IT IS HELPFUL TO PROVIDE A RESPONSE |
| | LETTER ADDRESSING EACH ITEM ALONG WITH THE CITY |
| | RESUBMITTAL FORM. ADDITIONALLY, INSERT CORRECTED PAGES |
| | INTO THE ORIGINAL SUBMITTAL AND REMOVE OR VOID THE |
| | PREVIOUSLY REVIEWED SHEETS. |
| | |
| | SINCERELY, |
| | |
| | JOHN PEARSON |
| | ELECTRICAL PLANS EXAMINER |
| | 561-805-6746 |
| | [email protected] |
| | |