Plan Review Notes
Plan Review Notes For Permit 17060065
Permit Number 17060065
Review Stop FIRE
Sequence Number 1
Notes
Date Text
2017-06-08 10:11:01THIS PLAN WAS REVIEWED AND FAILED BY PETER LEDUC, FIRE
 MARSHAL, WITH THE FOLLOWING COMMENTS:
  
  
 1) SHEET G 109 - THE LIFE SAFETY PLAN DOES NOT APPEAR
 TO INDICATED EXIT CONDITIONS DURING CONSTRUCTION. THE
 LIFE SAFETY PLAN MUST INDICATE HOW THE CONSTRUCTION
 AREA WILL BE PROTECTED/SEPARATED FROM REGULAR BUSINESS
 ACTIVITIES.
  
 WHAT EXITS WILL BE BLOCKED, HOW WILL THEY REROUTE
 PEOPLE, WHAT IS/ARE THE PROPOSED OCCUPANCY LOADS
 CHANGING BASED ON THE REROUTING, WILL FIRE ALARM
 DEVICES/NOTIFICATIONS BE AFFECTED BY THE CONSTRUCTION
 SEPARATIONS , NEW EXIT SIGNS, NEW EMERGENCY LIGHTING,
 ETC.
  
 PLEASE PROVIDE DETAILED INDICATIONS AND NARRATIVES
 RELATING TO THE ABOVE.
  
  
  
 2) SHEET G 109 - THERE IS A NOTE INDICATING EXISTING DE
 DOORS WILL BE REMOVED AT THE END OF PHASE 1A. HAVE
 THESE DOORS BEEN ELVALUATED FOR THEIR FUNCTION RELATING
 TO SMOKE CONTROL/BARRIERS?
  
 PLEASE REVIEW THE EXISTING LIFE SAFETY ENGINEERING
 SYSTEMS AND ENSURE THAT THESE DOORS CAN BE REMOVED AND
 PROVIDE AND APPLICATION NOTE OR LETTE FROM THE EOR.
  
  
  
  
 3) LIFE SAFETY SHEETS - IN ADDITION TO THE ABOVE
 COMMENT, DOES ANY OF THE PROPOSED CONSTRUCTION PHASES
 INTERFERE WITH THE EXISTING ENGINEERED LIFE SAFETY
 EQUIPMENT/FEATURES OF THE OCCUPANCY.
  
 IS THERE SMOKE CONTROL, SMOKE BARRIERS,
 PRESSURIZATIONS, EVACUATION SYSTEMS THAT MAY OR WILL BE
 COMPROMISED BY THIE PROPOSED CONSTRUCTION?
  
 PLEASE PROVIDE A DETAILED REVIEW OF ALL PHASES AND/OR
 PROVIDE FOR THE CORRECTION OR MAINTENANCE OF THESE
 SYSTEMS.
  
  
  
  
 4) F 111.A - THE FFP PAGE TITLE SHOWS ONLY PHASE 1 - A;
 HOWEVER, ALL PHASES APPEAR TO BE DRAWN.
  
 EACH PHASE SHOULD BE DETAILED ON HOW IT WILL BE
 ISOLATED OR CONTROLLED TO MAINTAIN FUNCTION THROUGHOUT
 CONTRUCTION.
  
 PLEASE REVIEW, CLARIFY OR CORRECT.
  
  
  
  
 5) SHEET E 001 - UNDER DEMOLITION GENERAL NOTES AND
 GENERAL NOTES, THERE IS/ARE NO INDICATIONS OF FIRE
 ALARM WORK. THE FIRE ALARM SHALL BE MAINTAINED
 THROUGHOUT CONTRUCTION. ALL WORK SHALL BE DONE BY
 CERTIFIED LIFE SAFETY CONTRACTORS UNDER SEPARATE SHOP
 DRAWINGS. BASED ON THE SEPARATION OF AREAS AND PHASES,
 ADDITIONAL DEVICES MAY BE REQUIRED FOR CODE COVERAGE
 PURPOSES.
  
 PLEASE REVIEW AND PROVIDE AND APPLICABLE NOTE.
  
  
  
 6) SHEET E 109 - THERE ARE TWO NOTE TAGE; 0.99.1 &
 0.98.1, THAT DO NOT APPEAR TO HAVE AN OBVIOUS
 EXPLANATION DETAIL OF DEFINITION. WHAT DOES THESE
 INDICATE.
  
 PLEASE CLARIFY.
  
  
 7) WHEN RESUBMITTING, PLEASE PROVIDE PLAN SHEET
 REVISION CLOUDS OR NUMBERED NARRATIVE RESPONSES TO THE
 ABOVE.
  
  
  
 8) ADDITIONAL COMMENTS MAY BE PROVIDED ON THE
 RE-SUBMITTAL OF THE ABOVE.
  
  
  
 PETER LEDUC
 FIRE MARSHAL
 561-804-4709
 [email protected]
  