| Date |
Text |
| 2017-07-27 12:27:05 | GAS PLAN REVIEW |
| | A GAS PLAN HAS NOT BEEN INCLUDED IN THIS SUBMITTAL |
| | PACKAGE. A GAS PLAN REVIEW HAS NOT BEEN PERFORMED AT |
| | THIS TIME. A SEPARATE GAS PERMIT AND PLANS WILL BE |
| | REQUIRED FOR A CONTRACTOR TO PERFORM THE RELATED WORK. |
| | PROVIDE COMPLETE PLANS, APPLIANCE/ EQUIPMENT |
| | SPECIFICATIONS AND GAS RISER THAT REFLECT THE ENTIRE |
| | SCOPE OF GAS WORK TO BE DONE. WPB AMEND. TO FBC SEC. |
| | 107.2.1. |
| | |
| | GAS APPLIANCES SHALL BE LISTED AND LABELED PER THE |
| | FBC-R, SEC. G2404.3. |
| | GAS APPLIANCES SHALL BE LISTED AND LABELED PER FBC-FUEL |
| | GAS SEC. 301.3. |
| | |
| | A SEPARATE PERMIT IS REQUIRED FOR THE GAS INSTALLATION. |
| | |
| | GAS PERMIT APPLICATION REQUIREMENTS |
| | |
| | EFFECTIVE IMMEDIATELY THE FOLLOWING INFORMATION SHALL |
| | BE SHOWN ON ALL GAS DRAWINGS SUBMITTED FOR PERMITTING |
| | IN THE CITY OF WEST PALM BEACH: |
| | |
| | 1. SUBMIT AN ISOMETRIC DRAWING THAT CLEARLY SHOWS ALL |
| | CUT SECTIONS OF PIPE AND CORRESPONDING LENGTHS PER |
| | FBC-2014 FUEL GAS, SECS. 402.4.1, 402.4.2. |
| | |
| | 2. SHOW TYPE OF PIPING MATERIAL BEING INSTALLED, ALL |
| | PIPE SIZES, AND THE EHD NUMBER OF CORRUGATED STAINLESS |
| | STEEL TUBING FOR EACH PIPE SIZE IF BEING USED. WPB |
| | AMENDMENTS TO FBC SEC. 107.2.1. |
| | |
| | 3. TYPE OF GAS, (LP OR NATURAL). |
| | |
| | 4. BTU LOAD OF EACH APPLIANCE AND THE TOTAL BTU LOAD ON |
| | THE SYSTEM. REFER TO THE FBC-2014 FUEL GAS SECS. 401.8 |
| | THRU 402.6.1 AND TABLES 402.4(1) THRU 402.4(37). |
| | |
| | 5. SHOW THE DISTANCE FROM THE POINT OF DELIVERY, |
| | (METER), TO THE MOST REMOTE OUTLET IN THE BUILDING |
| | AND/OR SYSTEM PER THE FBC-2014 FUEL GAS APPENDIX A ? |
| | USE OF CAPACITY SECTION A.3.1(4) & 2014 FUEL GAS CODE |
| | SEC. 402.4.1. |
| | |
| | 6. SUBMIT CALCULATIONS FOR COMBUSTION AIR PER THE |
| | FBC-2014 FUEL GAS CODE SEC. 304. |
| | |
| | 7. INDICATE THE DELIVERY PRESSURE (PSI) PER FBC-2014 |
| | FUEL GAS SEC. 402.2. IF NATURAL GAS SPECIFY .5 PSI OR 2 |
| | PSI. |
| | |
| | 8. SUBMIT A DETAIL SHOWING THE TYPE, LOCATION, SIZE AND |
| | TERMINATION OF THE GAS VENTS PER FBC-2014 FUEL GAS CODE |
| | SEC. 502 THRU 505. |
| | |
| | 9. SUBMIT MANUFACTURER?S SPECIFICATION SHEETS FOR ALL |
| | GAS EQUIPMENT TO VERIFY COMPLIANCE WITH STANDARDS NFPA |
| | 54, NFPA 58, AND FBC-2014 FUEL GAS SEC. 402.2 |
| | |
| | 10. CLEARLY SHOW THE LOCATION AND CAPACITY OF LP |
| | TANK(S), TYPE OF TANK (DOT OR ASME), THE DISTANCE OF |
| | THE TANK FROM THE BUILDING AND ADJACENT PROPERTY LINES |
| | THE DISTANCE OF THE TANK FROM ALL SOURCES OF IGNITION, |
| | OTHER CONTAINERS, BUILDINGS, AND THE LOCATION OF ANY |
| | BUILDING OPENINGS BELOW THE RELIEF VALVE OF THE TANK |
| | PER NFPA 58, TABLE 3-2.2.2. |
| | |
| | 11. CLEARLY INDICATE ON THE PLAN IF THE LP TANK IS |
| | ABOVE OR BELOW GROUND, AND SHOW REQUIRED PROTECTION OF |
| | THE TANK AND APPURTENANCES PER NFPA 58. IF THE TANK IS |
| | BELOW GROUND THE CONTAINER SHALL BE SECURELY ANCHORED |
| | PER NFPA 58 SECTION 3-2.2.7(H). |
| | |