| Plan Review Notes For Permit 17050949 |
| Permit Number |
17050949 |
|
| Review Stop |
P |
| Sequence Number |
1 |
|
| Notes |
| Date |
Text |
| 2017-05-25 06:44:46 | 1) SUBMIT 2 COPIES OF A SITE PLAN SHOWING THE LOCATION | | | OF THE WORK TO BE DONE. WPB AMEND. TO FBC SEC. 107.2.1. | | | 2) IF THE NEW SEWER IS BEING RUN ALL THE WAY TO THE | | | CITY LATERAL, A CLEANOUT BROUGHT TO GRADE MUST BE | | | INSTALLED AT THE CITY LATERAL. | | | 3) A SAMPLING PORT SHLL BE INSTALLED AT THE OUTLET OF | | | THE GREASE INTERCEPTOR. THE SAMPLING PORT SHALL BE THE | | | SAME SIZE AS THE OUTLET LINE AND A MINIMUM OF 4 INCH. A | | | TWO WAY CLEANOUT TEE WILL MEET THIS REQUIREMENT. | | | NOTE: THE SITE PLAN CAN BE HAND DRAWN. | | | | | | TIM LARGE | | | CHIEF PLUMBING INSPECTOR | | | PLUMBING PLAN REVIEW | | | 561-805-6692 | | | [email protected] | | | |
|