| 2017-05-04 08:41:51 | CONRAILILITY RELEASES WERE PROVIDED WITH THIS |
| | DEMOLITION APPLICATION. WE NEED TO CONFIRM THE |
| | FOLLOWING PRIOR TO ISSUANCE; |
| | |
| | 1) EITHER A COPY OF FPL UTILITY DISCONNECT OR IF |
| | PARTIAL DEMO OF STRUCTURE, AN ELECTRICAL PERMIT TO |
| | DISCONNECT POWER TO PROPOSED AREAS. |
| | |
| | 2) RELEASE COPY FROM FPU THAT NO GAS IS PROVIDED TO |
| | PROPOSED AREAS. |
| | |
| | 3) THE DEMOLITION IS A SHOW ROOM AND SERVICE SHOP. |
| | ASSUMING BATHROOM FACILITIES ARE INVOLVED, THE SEWER |
| | LATERALS WILL NEED TO BE CAPPED WITH A TURN A ROUND |
| | PLUMBING PERMIT. A FINAL #703 WILL NEED TO BE REQUESTED |
| | AND PASSED ON THAT PERMIT. |
| | |
| | 4) A REQUEST TO THE UTILITIES DEPARTMENT TO DISCONNECT |
| | THE WATER METERS INVOLVED OR IF ONLY A PARTIAL |
| | DISCONNECT A BACKFLOW CAN BE INSTALLED AND KEEP THE |
| | DEMO WET. WHEN THE UTILITIES DEPARTMENT GETS THIS |
| | REQUEST THEY WILL ALSO MARK THE LOCATION OF THE SEWER |
| | LATERAL ON SITE. |
| | |
| | 5) COMMERCIAL DEMOLITION REQUIRES AN ASBESTOS ABATEMENT |
| | SURVEY BE COMPLETED WITH COPY PROVIDED IN APPLICATION. |
| | |
| | 6) A RODENT LETTER BY A PEST CONTROL COMPANY WILL NEED |
| | TO BE INCLUDED IN THE APPLICATION STATING THEY HAVE |
| | INSPECTED AND FOUND NO RODENTS OR FOUND AND TREATED FOR |
| | THEM. |
| | |
| | 7) A DEBRIS DISPOSAL FORM SHOULD BE COMPLETED AT TIME |
| | OF PICK UP. |
| | |
| | FEEL FREE TO CALL TOM WITH ANY QUESTIONS, AT |
| | 561-805-6669 |
| | |
| | |