| 2017-04-17 13:47:04 | THIS PLAN WAS REVIEWED AND APPROVED BY PETER LEDUC, |
| | FIRE MARSHAL, WITH THE FOLLOWING COMMENTS: |
| | |
| | PLEASE CONSIDER THE FOLLOWING AS PROVISO: |
| | |
| | THESE PROVISO COMMENTS WILL BE VERIFIED AND CONFIRMED |
| | AT THE TIME OF FIRE INSPECTION. FAILURE TO FOLLOW THESE |
| | PROVISO COMMENTS WILL RESULT IN A FAILED FIRE |
| | INSPECTION. |
| | |
| | |
| | 1) THERE WERE NO FLAME RETARDENT CERTIFICATES PROVIDED |
| | ON THE SUBMITTAL. ALL TENT FABIC SHALL HAVE A CURRENT |
| | AND APPLICABLE FLAME RETARDENT CERTIFICATE. |
| | |
| | 25.2.2 FLAME PROPAGATION PERFORMANCE. |
| | 25.2.2.1 ALL TENT FABRIC SHALL MEET THE FLAME |
| | PROPAGATION PERFORMANCE CRITERIA CONTAINED IN NFPA 701, |
| | STANDARD METHODS OF FIRE TESTS FOR FLAME PROPAGATION OF |
| | TEXTILES AND FILMS. [101:11.11.2.1] |
| | |
| | 25.2.2.2 ONE OF THE FOLLOWING SHALL SERVE AS EVIDENCE |
| | THAT THE TENT FABRIC MATERIALS HAVE THE REQUIRED FLAME |
| | PROPAGATION PERFORMANCE: |
| | (1) THE AHJ SHALL REQUIRE A CERTIFICATE OR OTHER |
| | EVIDENCE OF ACCEPTANCE BY AN ORGANIZATION ACCEPTABLE TO |
| | THE AHJ. |
| | (2) THE AHJ SHALL REQUIRE A REPORT OF TESTS MADE BY |
| | OTHER INSPECTION AUTHORITIES OR ORGANIZATIONS |
| | ACCEPTABLE TO THE AHJ. [101:11.11.2.2] |
| | 25.2.2.3 WHERE REQUIRED BY THE AHJ, CONFIRMATORY FIELD |
| | TESTS SHALL BE CONDUCTED USING TEST SPECIMENS FROM THE |
| | ORIGINAL MATERIAL, WHICH SHALL HAVE BEEN AFFIXED AT THE |
| | TIME OF MANUFACTURE TO THE EXTERIOR OF THE TENT. |
| | [101:11.11.2.3] |
| | |
| | PLEASE PROVIDE THE APPLICABLE FLAME RETARDENTS |
| | CERTIFICATES AND/OR SMAPLE TO THE FIRE INSPECTOR ON |
| | INSPECTION. |
| | |
| | |
| | |
| | 2) ANY FUTURE SUBMITTALS NOT CONTAINING APPLICABLE |
| | FLAME RETARDENT CERTIFICATIONS WILL BE DENIED. |
| | |
| | |
| | |
| | PETER LEDUC |
| | FIRE MARSHAL |
| | 561-804-4709 |