| Date |
Text |
| 2017-02-21 10:12:20 | 1ST REVIEW FBC-2014 MECHANICAL |
| | PERMIT #17020696 |
| | 2/21/17 |
| | |
| | 1) PLEASE ADD THE REPLACEMENT OF THE 14 EXHAUST FANS TO |
| | THE WORK DESCRIPTION ON THE APPLICATION, AND ADJUST THE |
| | VALUE ACCORDINGLY- SECTION 109.3 WPB AMENDMENTS TO THE |
| | FBC. |
| | |
| | 2) I AM CHALLENGING THE $250,000 JOB VALUE FOR THE |
| | PROPOSED PROJECT BASED ON COST VALUATION TABLES |
| | PUBLISHED BY MARSHALL & SWIFT VALUATION SERVICE. AS |
| | LISTED IN THE TABLES THE THE REPLACEMENT OF THE HEAT |
| | PUMPS AND DUCTWORK ALONE WOULD AMOUNT TO APPROXIMATELY |
| | $250,000- SEE SECTION 53 PAGE 4. PLEASE PROVIDE AN |
| | ITEMIZED COST BREAKDOWN THAT INCLUDES THE COOLING |
| | TOWER, THE PUMPS, THE BOILER, THE DUCTWORK, THE PIPING |
| | AND CONTROLS, THE EXHAUST FANS, AND THE COOLING TOWER |
| | SUPPORT STRUCTURE, STAIRS AND CATWALK. |
| | |
| | 3) PROVIDE THE WIND LOAD DESIGN CRITERIA FOR |
| | INSTALLATION OF ALL THE ROOFTOP FANS AND THE COOLING |
| | TOWER, AND ENGINEERED DRAWINGS AND DETAILS FOR |
| | INSTALLATION OF THE COOLING TOWER AND SUPPORT |
| | STRUCTURE- SECTION 301.15. |
| | |
| | 4) PROVIDE A LIST OF CODES AND STANDARDS USED IN THE |
| | DESIGN OF THE PROJECT. |
| | |
| | 5) NEW BOILER: A) PROVIDE A COMPLETE EQUIPMENT SCHEDULE |
| | FOR THE BOILER INCLUDING BTUH CAPACITY. B) PROVIDE AN |
| | ENLARGED DRAWING SHOWING THE REQUIRED WORKING |
| | CLEARANCES AND LENGTH OF THE NEW 10'' FLUE. C) PROVIDE |
| | THE TOTAL RUN LENGTH OF THE FLUE AND EXISTING VENT FROM |
| | THE BOILER OUTLET TO THE TERMINATION ON THE ROOF. D) |
| | SHOW THE VENT TERMINATION ON SHEET M-1. |
| | |
| | 6) COMMISSIONING FOR THE REPLACED COOLING TOWER AND |
| | HEAT PUMPS IS REQUIRED PER SECTION C408.2 FBC-14 ENERGY |
| | CONSERVATION. PLEASE SUBMIT A COMMISSIONING PLAN AS |
| | OUTLINED IN SECTION C408.2.1. |
| | |
| | 7) PROVIDE A MECHANICAL DEMOLITION PLANS FOR THE |
| | EQUIPMENT ROOM. |
| | |
| | 8) PROVIDE DUCT HANGING AND CONNECTION DETAILS PER |
| | SMACNA HVAC CONSTRUCTION STANDARDS 2005. |
| | |
| | 9) SUBMIT TWO COPIES OF A FL. PRODUCT APPROVAL AND/OR |
| | MIAMI-DADE NOA FOR THE GREENHECK LOUVERS. |
| | |
| | 10) PLEASE CLARIFY IF THE THE REPLACED HEAT PUMPS (O/A |
| | UNITS) ARE PART OF THE SMOKE CONTROL SYSTEM AND ARE |
| | BEING USED FOR PRESSURIZATION OF CORRIDORS IN THE EVENT |
| | OF FIRE. PLEASE NOTE IF THEY ARE SERVING THAT FUNCTION, |
| | THEN SPECIAL INSPECTION OF THE SYSTEMS IS REQUIRED AS |
| | NOTED IN SECTION 909.3 FBC-14 BUILDING. |
| | |
| | CHRISTOPHER L. COLE |
| | MECHANICAL PLANS EXAMINER |
| | 561-805-6719 |
| | [email protected] |
| | |