| Date |
Text |
| 2017-03-14 06:40:16 | 1) SUBMIT FACTORY SIZING CALCULATIONS FRROM SCHIER FOR |
| | THE SIZING OF THE NEW GREASE INTERCEPTOR. 2014 |
| | FBC-PLUMBING, SEC. 1003.2. |
| | 2) SHT.A 501D - DETAIL #2 - THE TOILET PAPER DISPENSER |
| | IN THE ACCESSIBLE TOILET ROOMS SHALL BE 7 INCHES |
| | MINIMUM AND 9 INCHES MAXIMUM IN FRONT OF THE WATER |
| | CLOSET MEASURED TO THE CENTERLINE OF THE DISPENSER.THE |
| | OUTLET OF THE DISPENSER SHALL BE 14 INCHES MINIMUM AND |
| | 19 INCHES MAXIMUM ABOVE THE FINISH FLOOR.THERE SHALL BE |
| | A CLEARANCE OF 1 1/2 INCHES MINIMUM BELOW THE GRAB BAR. |
| | 2014 FBC-ACCESS. SEC.604.9.6. |
| | 3) SHT. A 501D-DETAIL #2 - THE HEIGHT OF THE GRAB BARS |
| | SHALL BE MEASURED TO THE TOP OF THE GRIPPING SURFACE, |
| | NOT TO THE CENTERLINE.2014 FBC-ACCESS. SEC. 609.4. |
| | 4) SHT. A 501D - DETAIL #10 - PROTRUDING OBJECTS SHALL |
| | COMPLY WITH 2014 FBC-ACCESS. SEC.307.2. |
| | 5) SHT. A 405D - SHOW THE LOCATION OF THE WINE |
| | DISPENSER ON THE PLAN ( ITEM# B1). |
| | 6) SHT. P1.3 - EQUIPMENT ITEM #B10 IS NOTED AS AN |
| | ICEMAKER AND THE WASTE IS DISCHARGING INTO THE GREASY |
| | WASTE SYSTEM. WASTES THAT DO NOT REQUIRE TREATMENT OR |
| | SEPARATION SHALL NOT BE DISCHARGED INTO ANY INTERCEPTOR |
| | OR SEPARATOR. 2014 FBC-PLUMBING SEC.1003.2. THIS WASTE |
| | SHALL DISCHARGE TO THE SANITARY. |
| | 7) SHT. P1.4 - SIZE THE REMAINDER OF THE GAS LINE TO |
| | EQUIPMENT K6 & K1. |
| | 8) SHT. P1.4 SHOWS "EXISTING/NEW" (2) 1 INCH BACKFLOW |
| | PREVENTTERS. ARE THEY "NEW" OR "EXISTING". CLARIFY. |
| | 9) A MINIMUM OF TWO DRINKING FOUNTAINS ARE REQUIRED PER |
| | 2014 FBC-PLUMBING, TABLE 403.1, FOOTNOTE "E" & 2014 |
| | FBC-ACCESSIBILITY SEC. 211.2. |
| | |
| | TIM LARGE |
| | CHIEF PLUMBING INSPECTOR |
| | PLUMBING PLAN REVIEW |
| | 561-805-6692 |
| | [email protected] |
| | |
| | |