| 2017-02-10 03:10:54 | 1) IS THE NEW TANKLESS WATER HEATER REPLACING AN |
| | EXISTING TANKLESS WATER HEATER OR IS THE TANKLESS |
| | REPLACING A TANK TYPE WATER HEATER? NOTE THIS ON THE |
| | PLAN.IF A TANK TYPE WATER HEATER IS BEING REPLACED WITH |
| | THE TANKLESS, AN UPGRADE TO THE ELECTRIC MAY BE |
| | REQUIRED WHICH WILL REQUIRE A SEPARATE PERMIT. WPB |
| | AMEND. TO FBC SEC.107.2.1. |
| | 2) IS THE TANKLESS WATER HEATER BEING INSTALLED ON THE |
| | INTERIOR OR EXTERIOR OF THE STRUCTURE? SUBMIT TWO |
| | COPIES OF A HOUSE PLAN SHOWING THE LOCATION OF THE |
| | TANKLESS WATER HEATER AND THE LOCATION OF ANY OPERABLE |
| | DOORS OR WINDOWS. THE LOCATION OF THE WATER HEATER |
| | SHALL COMPLY WITH THE MANUFACTURER'S INSTALLATION |
| | INSTRUCTIONS. THE HOUSE PLAN CAN BE HAND DRAWN. WPB |
| | AMEND. TO FBC SEC. 107.2.1. |
| | 3) SUBMIT 2 COPIES OF THE MANUFACTURER'S |
| | SPECIFICATIONS/INSTALLATION INSTRUCTIONS FOR THE |
| | TANKLESS WATER HEATER. WPB AMEND. TO FBC SECS. |
| | 102.1,107.2.1. |
| | 4) CLEARLY IDENTIFY ON THE SANITARY RISER DIAGRAM WHAT |
| | PIPING IS BEING REPLACED. IS ALL THE UNDERGROUND/UNDER |
| | SLAB PIPING BEING REPLACED INCLUDING THE STACKS? |
| | 5) IF THE AREA UNDER THE SLAB IS TO BE TUNNELLED TO |
| | GAIN ACCESS TO THE EXISTING SANITARY LINES, THEN THE |
| | FOLLOWING SHALL BE ADHERED TO: |
| | |
| | PLUMBING REPAIR TUNNEL WORK |
| | |
| | A CLEAR AND LEGIBLE SANITARY RISER DIAGRAM SHALL BE |
| | SUBMITTED SHOWING ALL PIPE SIZES, CONNECTION POINTS TO |
| | EXISTING PIPING, HOW THE NEW PIPE WILL BE SUPPORTED, |
| | THE TYPE OF ADAPTERS USED FOR THE CONNECTIONS TO |
| | EXISTING PIPE, AND THE LOCATIONS OF REQUIRED CLEANOUTS. |
| | DETAILS AND BACKFILLING PROCEDURES SHALL BE SUBMITTED |
| | THAT CLEARLY SHOW HOW THE STRUCTURAL INTEGRITY OF THE |
| | CONCRETE SLAB WILL BE MAINTAINED DURING EXCAVATION AND |
| | BACKFILLING. STRUCTURAL FOAM IS NOT PERMITTED BELOW |
| | GROUND PER THE FLORIDA BUILDING CODE, RESIDENTIAL, |
| | SECTION 318 AND THE FLORIDA BUILDING CODE, BUILDING, |
| | SECTION 26. A SIGNED AND SEALED LETTER FROM AN ENGINEER |
| | SHALL BE SUBMITTED FOR FINAL INSPECTION STATING THAT |
| | THE STRUCTURAL INTEGRITY OF THE EXISTING SLAB HAS NOT |
| | BEEN COMPROMISED. |
| | |
| | TIM LARGE |
| | CHIEF PLUMBING INSPECTOR |
| | PLUMBING PLAN REVIEW |
| | 561-805-6692 |
| | [email protected] |
| | |