Plan Review Notes
Plan Review Notes For Permit 17010911
Permit Number 17010911
Review Stop B
Sequence Number 8
Notes
Date Text
2018-07-19 13:25:25****PROVISOS****
  
 SAMANTHA HILL
 BUILDING PLANS EXAMINER
 [email protected]
 561-805-6724
  
 FBC = FLORIDA BUILDING CODE, 5TH EDITION (2014)
 FBC B = FBC BUILDING
 FBC R = FBC RESIDENTIAL
 FBC EB = FBC EXISTING BUILDING
 FBC A = FBC ACCESSIBILITY
 FBC EC = FBC ENERGY CONSERVATION
  
 BANYAN CAY FOUR STORY HOTEL **FOUNDATION ONLY**
 ***THRESHOLD BUILDING***, POST TENSION 6"-8" SLABS, FRT
 TRUSSES, TYPE IIA
 ARCHITECT - ADACHE GROUP ARCHITECTS, DANIEL E. ADACHE
 AR7073
 ENGINEER - MUE ENGINEERS, INC (29348), MARCUS O.
 UNTERWEGER, PE63860
 MEP - TLC ENGINEERING
 MECHANICAL - JORGE E. REYES, PE54904
 ELECTRICAL - RALPH BAEZA, PE42641
 PLUMBING - JORGE E. REYES, PE54904
  
 A. COMPLIANCE WITH ART IN PUBLIC PLACES ORDINANCE
 78-123 REQUIRED: MS. SYBILLE WELTER, 561-822-1515,
 [email protected]. MS. WELTER WILL ADVISE VIA EMAIL WHEN
 THIS IS COMPLETE.
  
 B. FBC 110.3.7.4.3 SHORING AND RESHORE ENGINEERING TO
 BE SUBMITTED AND REVIEWED PRIOR TO INSTALLATION.
 FAILURE TO SUBMIT SHORING/RESHORE ENGINEERING TIMELY
 WILL RESULT IN A STOP WORK ORDER. AN ENGINEERED
 GUARDRAIL DETAIL (CONSTRUCTION IN PROGRESS) IS ALSO
 REQUIRED PRIOR TO INSTALLATION.
  
 C. FBC 105.13 PHASED PERMIT APPROVAL. AFTER SUBMITTAL
 OF THE APPROPRIATE CONSTRUCTION DOCUMENTS, THE BUILDING
 OFFICIAL IS AUTHORIZED TO ISSUE A PERMIT FOR THE
 CONSTRUCTION OF FOUNDATIONS OR ANY OTHER PART OF A
 BUILDING OR STRUCTURE BEFORE THE CONSTRUCTION DOCUMENTS
 FOR THE WHOLE BUILDING OR STRUCTURE HAVE BEEN
 SUBMITTED. THE HOLDER OF SUCH PERMIT FOR THE FOUNDATION
 OR OTHER PARTS OF A BUILDING OR STRUCTURE SHALL PROCEED
 AT THE HOLDER?S OWN RISK WITH THE BUILDING OPERATION
 AND WITHOUT ASSURANCE THAT A PERMIT FOR THE ENTIRE
 STRUCTURE WILL BE GRANTED. CORRECTIONS MAY BE REQUIRED
 TO MEET THE REQUIREMENTS OF THE TECHNICAL CODES. THIS
 PROVISION IS ONLY FOR THE FLORIDA BUILDING CODE, ALL
 OTHER AGENCY APPROVALS NECESSARY FOR CONSTRUCTION MUST
 BE SECURED PRIOR TO THIS PROVISION BEING APPLIED.
  
 D. THE LIFE SAFETY SHEETS WERE NOT THOROUGHLY REVIEWED.
 THIS WILL BE REVIEWED UNDER THE BUILDING PERMIT
 APPLICATION; FOUNDATION PERMIT WILL BE ISSUED AT
 APPLICANT'S RISK.
  
 E. ENERGY CALCS HAVE BEEN VOIDED AS THEY ARE NOT
 CORRECT AND ARE INCOMPLETE. SUBMIT WITH VERTICAL
 BUILDING PERMIT.
  
 F. PRIOR TO COMMENCEMENT, SCHEDULE A PRE-CONSTRUCTION
 MEETING WITH KEN CONRAD, CHIEF BUILDING INSPECTOR.
 SCHEDULE A 143 BUILDING MISC INSPECTION AND ADVISE THAT
 IT IS A PRE-CON MEETING. THE CONTRACTOR AND ON SITE
 INSPECTOR SHOULD ATTEND TO DISCUSS PROCEDURE.
  
  
  