| Date |
Text |
| 2017-04-20 06:07:14 | THE FOLLOWING ITEMS WILL BE CONSIDERED DEFERRED | | | SUBMITTALS. COMPLETE PLANS AND SPECIFICATIONS SHALL BE | | | SUBMITTED FOR REVIEW FOR THE FOLLOWING ITEMS PRIOR TO | | | THE INSTALLATION OF NOTED SYSTEMS: | | | 1) BOILER AND ASSOCIATED PIPING AND VENT - SUBMIT AN | | | EQUIPMENT SCHEDULE FOR THE BOILER, BOILER VENT PIPE(S), | | | AND MANUFACTURER'S SPECIFICATIONS FOR EACH. PROVIDE A | | | DIMENSIONAL ELEVATION VIEW THAT SHOWS THE TOTAL VENT | | | RUN FROM THE OUTLET OF THE BOILER TO THE TERMINATION | | | CAP ABOVE THE ROOF. SHOW HOW THE VENT WILL BE SUPPORTED | | | AND ANCHORED TO THE ROOF STRUCTURE. | | | 2) STEAM PIPING - PROVIDE STEAM PIPING DRAWINGS THAT | | | SHOW THE PIPING RUNS, TYPES AND SIZES OF PIPES & PIPE | | | INSULATION. | | | 3) EQUIPMENT SCHEDULE AND PIPING PLAN FOR THE TANKS AND | | | KETTLES USED IN THE BREWING PROCESS. | | | 4)SUBMIT A DETAIL SHOWING THE TYPE, LOCATION, SIZE, | | | TERMINATION POINT, HEIGHT ABOVE THE ROOF AND ANCHORING | | | DETAILS OF THE GAS VENT(S) PER 2014 FBC-FUEL GAS SECS. | | | 502 THRU 505. | | | | | | TIM LARGE | | | CHIEF PLUMBING INSPECTOR | | | PLUMBING PLAN REVIEW | | | 561-805-6692 | | | [email protected] | | | |
|