| 2017-03-25 08:09:27 | 1) 2014 FBC-PLUMBING SEC.403.1.3 - SEE REQUIREMENTS FOR |
| | POTTY PARITY. |
| | 403.1.3 POTTY PARITY. |
| | IN ASSEMBLY OCCUPANCIES, RESTROOMS WHICH ARE OPEN TO |
| | THE PUBLIC MUST HAVE A RATIO OF 3:2 WATER CLOSETS |
| | PROVIDED FOR WOMEN AS THE COMBINED TOTAL OF WATER |
| | CLOSETS AND URINALS PROVIDED FOR MEN, UNLESS THESE ARE |
| | TWO OR FEWER SUCH FIXTURES FOR MEN, IN ACCORDANCE WITH |
| | SECTION 553.86, FLORIDA STATUTES. |
| | EXCEPTION: THIS SECTION DOES NOT APPLY TO |
| | ESTABLISHMENTS LICENSED UNDER CHAPTER 509, FLORIDA |
| | STATUTES, IF THE ESTABLISHMENT DOES NOT PROVIDE MEETING |
| | OR BANQUET ROOMS WHICH ACCOMMODATE MORE THAN 150 |
| | PEOPLE, AND THE ESTABLISHMENT HAS AT LEAST THE SAME |
| | NUMBER OF WATER CLOSETS FOR WOMEN AS THE COMBINED TOTAL |
| | OF WATER CLOSETS AND URINALS FOR MEN. |
| | 2) THE TOILET COMPARTMENT IN THE MEN'S RESTROOM THAT IS |
| | SHOWN AS A NON-HANDICAPPED ACCESSIBLE COMPARTMENT SHALL |
| | COMPLY WITH THE 2014 FBC-ACCESSIBILITY SEC.604.8.2 PER |
| | FAC SEC. SEC.213.3.1. - AMBULATORY ACCESSIBLE |
| | COMPARTMENTS - (213.3.1- TOILET COMPARTMENTS.) |
| | WHERE TOILET COMPARTMENTS ARE PROVIDED, AT LEAST ONE |
| | TOILET COMPARTMENT SHALL COMPLY WITH 604.8.1. IN |
| | ADDITION TO THE COMPARTMENT REQUIRED TO COMPLY WITH |
| | 604.8.1, AT LEAST ONE COMPARTMENT SHALL COMPLY WITH |
| | 604.8.2 WHERE SIX OR MORE TOILET COMPARTMENTS ARE |
| | PROVIDED, OR WHERE THE COMBINATION OF URINALS AND WATER |
| | CLOSETS TOTALS SIX OR MORE FIXTURES. ) |
| | 3) SHT.A-8.0 THE SIDE WALL GRAB BAR FOR THE WATER |
| | CLOSET IN THE HANDICAPPED ACCESSIBLE TOILET |
| | COMPARTMENTS SHALL BE LOCATED AS SPECIFIED IN 2014 |
| | FBC-ACCESS. SEC.604.5.1 AND THE REAR WALL GRAB BAR |
| | SHALL BE LOCATED AS SPECIFIED IN SEC.604.5.2. |
| | 4) SHT. A-1.3 - EQUIPMENT PLAN NOTE #6 REFERS TO AN 80 |
| | GAL. AIR COMPRESSOR BUT IT IS NOT INDICATED ON THE |
| | FLOOR PLAN. SHOW THE LOCATION ON THE FLOOR PLAN AND |
| | SUBMIT A COMPRESSED AIR RISER DIAGRAM FOR ANY |
| | COMPRESSED AIR PIPING TO BE INSTALLED.SHOW TYPE OF |
| | MATERIAL AND PIPE SIZES, VALVES, ETC. WPB AMEND. TO FBC |
| | SEC. 107.2.1. |
| | 5) SHT. A-9.2 - DETAIL #11 - THE NOTED DIMENSIONS ON |
| | THE LAVATORY DETAIL ARE VERY SMALL AND ALMOST |
| | ILLEGIBLE. DETAILS SHALL BE OF SUFFICIENT CLARITY TO |
| | INDICATE THE NATURE AND EXTENT OF THE WORK PROPOSED AND |
| | SHOW IN DETAIL THAT IT WILL CONFORM TO THE PROVISIONS |
| | OF THIS CODE. WPB AMEND. TO FBC SEC. 107.2.1. |
| | 6) SHT.P5.1 - SIZE ALL SECTIONS OF THE VENT SYSTEM ON |
| | THE SANITARY RISER. COMPLY WITH 2014 FBC-PLUMBING SECS. |
| | 906.1 & 906.2. |
| | 7) THE BRANCH VENT CONNECTING THE STACK VENTS ON THE |
| | SANITARY RISER SHALL BE INCREASED BY ONE NOMINAL PIPE |
| | SIZE PER 2014 FBC-PLUMBING SEC. 906.2 - VENTS EXCEEDING |
| | 40 FEET IN DEVELOPED LENGTH SHALL BE INCREASED BY ONE |
| | NOMINAL PIPE SIZE FOR THE ENTIRE DEVELOPED LENGTH OF |
| | THE VENT PIPE. |
| | 8) SHT. P5.1 - A VENT IS REQUIRED BETWEEN THE TWO WATER |
| | CLOSETS IN THE WOMEN'S RESTROOM PER 2014 FBC-PLUMBING |
| | SEC.909.1. |
| | 9) THE TRENCH DRAIN LOCATED IN ROOM #111 SHALL COMPLY |
| | WITH FBC-PLUMBING TABLE 909.1 FOR THE MAXIMUM DISTANCE |
| | OF THE FIXTURE TRAP FROM A VENT. THIS WILL BE CHECKED |
| | IN THE FIELD AND IS NOTED HERE AS A POSSIBLE CODE |
| | VIOLATION. |
| | 10) SHT. P5.1 - A URINAL IS DISCHARGING INTO THE WET |
| | VENT AT THE FURTHEST UPSTREAM WATER CLOSETS IN TOILET |
| | ROOMS #101 & 102. THE URINAL MUST DISCHARGE DOWNSTREAM |
| | OF THE HORIZONTAL WET VENT PER FBC-PLUMBING SEC.912.1. |
| | 11) THE SANITARY RISER SHOWS A 2 1/2 INCH VENT. WHERE |
| | DOES THIS VENT CONNECT? CLARIFY. |
| | 12) SIZE THE URINAL WASTE STACKS AND VENTS. |
| | FBC-PLUMBING SEC.906.1. |
| | 13) THE WATER SUPPLY LINE FOR THE ICE CHEST & BEER |
| | FILLER SHOWN ON THE WATER RISER SHALL BE EQUIPPED WITH |
| | A BACKFLOW PREVENTER COMPLYING WITH ASSE 1022 PER |
| | FBC-PLUMBING SEC.608.3. |
| | 14) THE POTABLE WATER CONNECTION TO THE BOILER SHALL BE |
| | EQUIPPED WITH A BACKFLOW PREVENTER WITH AN INTERMEDIATE |
| | VENT COMPLYING WITH ASSE 1012 OR CSA B64.3. |
| | FBC-PLUMBING SEC.608.16.2. |
| | 15) ROOM #110 SHOWS THE BOILER BLOW-OFF DISCHARGING TO |
| | A FLOOR DRAIN. WASTE WATER THAT IS DISCHARGED INTO THE |
| | BUILDING DRAINAGE SYSTEM SHALL BE AT A TEMPERATURE NOT |
| | GREATER THAN 140 DEGREES FARENHEIT. WHERE HIGHER |
| | TEMPERATURES EXIST, APPROVED COOLING METHODS SHALL BE |
| | PROVIDED. 2014 FBC SEC.701.9. |
| | |