Plan Review Notes
Plan Review Notes For Permit 16120091
Permit Number 16120091
Review Stop M
Sequence Number 1
Notes
Date Text
2016-12-14 17:01:351ST REVIEW FBC-2014 MECHANICAL, EXISTING BUILDING, &
 ENERGY CONSERVATION CODES
 PERMIT #16120091
 12/14/16
  
 1) PLACE A NOTE ON THE PLANS INDICATING SEPARATE
 PERMITS ARE REQUIRED FOR THE WALK-IN COOLER.
  
 2) COMPLIANCE WITH THE FLORIDA ENERGY CONSERVATION CODE
 IS REQUIRED IN ACCORDANCE WITH SECTION C101.4.4. REFER
 TO SECTION C401.2 FOR COMPLIANCE PATHS.
  
 3) PROVIDE AC COOLING AND HEATING CALCULATIONS FOR THE
 NEW RTU-1 PER SECTION C403.2.1.
  
 4) THE O/A CALCULATION IS INCOMPLETE AND DOES NOT
 INCLUDE THE BREWERY AND FERMENTATION AREAS. AT 6600
 TOTAL SQUARE FOOTAGE, IT APPEARS THAT THE 2859 SQUARE
 FOOTAGE FOR THE TASTING ROOM IS UNDERESTIMATED, AND THE
 TOTAL LOAD PER TABLE 403.3 SHALL BE CALCULATED AT 289.
  
 5) THE EXISTING AHU THAT IS PROVIDING 300 CFMS OF O/A
 TO THE TASTING ROOM IS 1549 CFMS SHORT PER THE SCHEDULE
 AND THE CALCULATIONS CURRENTLY SHOWN ON THE PLAN,
 HOWEVER THIS AMOUNT WILL INCREASE BASED ON REVISED
 CALCULATIONS PER COMMENT #4 ABOVE. PLEASE NOTE THAT
 DEMAND CONTROLLED VENTILATION IS REQUIRED FOR THE BAR
 IN COMPLIANCE WITH SECTION C403.2.5.1 FBC-14 ENERGY
 CONSERVATION. SHOW A MEANS OF COMPLIANCE ON THE PLAN.
 IF CO2 SENSORS ARE TO BE USED, PROVIDE THE MAKE AND
 MODEL NUMBER ON THE PLANS AND SUBMIT SPECS.
  
 6) PLEASE RE-LABEL THE CHILLER POSSIBLY USING CH-1
 RATHER THAN RTU-1 WHICH IS BEING USED TO IDENTIFY THE
 NEW ROOFTOP UNIT.
  
 7) PROVIDE EQUIPMENT SCHEDULES ON THE PLAN FOR THE NEW
 BOILER, BLOW DOWN TANK, AND FLUE VENT, AND SUBMIT
 MANUFACTURER'S SPECIFICATIONS WITH SHOP DRAWING
 APPROVAL STAMPS BY THE EOR- SEE SECTION 631.1 FBC-14
 FUEL GAS.
  
 8) PROVIDE A COMBUSTION AIR CALCULATION FOR THE BOILER
 IN COMPLIANCE WITH SECTION 304.6.2 FBC-14 FUEL GAS.
  
 9) SHEETS 1.5A & 3.1M: THE COMBUSTION AIR DUCT RUNS AT
 THE BOILER ROOM DO NOT MATCH- CHOOSE ONE METHOD OR THE
 OTHER. IF USING THE METHOD SHOWN ON SHEET 1.5A,
 RELOCATE THE LOCATION OF THE UPPER COMBUSTION AIR DUCT
 OPENING TO WITHIN 12 INCHES OF THE TOP OF THE ROOM.
  
 10) INDICATE THE TYPE OF COMBUSTION AIR DUCT TO BE
 INSTALLED AND INDICATE HOW THE OPENING AT THE ROOF
 LEVEL WILL BE PROTECTED- SECTION 304.10 FBC-14 FUEL
 GAS.
  
 11) 3.1M: PLEASE LABEL THE AHU ON THE FLOOR PLAN
 DRAWING AND PROVIDE SYMBOLS TO SHOW THE LOCATIONS OF
 THE REQUIRED DUCT SMOKE DETECTORS FOR THE AHU AND THE
 RTU- SECTION 606.2.1.
 A) INDICATE IF THE DETECTORS WILL BE CONNECTED TO A
 FIRE ALARM SYSTEM, OR IF NO FIRE ALARM, SHOW THE
 LOCATIONS OF AUDIBLE AND VISUAL SIGNALING DEVICES.
  
 12) THE F TRANSFER GRILLS ARE UNDERSIZED FOR 4200 CFMS-
 SEE SECTION 601.5(2). SHOW HOW AIR IS BEING RETURNED
 FROM THE GRILLS TO THE AHU- NO RETURN DUCTS OR GRILLS
 ARE SHOWN.
  
 13) CLARIFY THE PURPOSE OF EF-2 AND PROVIDE AN EXHAUST
 VENTILATION CALCULATION AND CONTROL OPERATION.
  
 14) REFER TO SECTION C402.4.5.2 AND PROVIDE AN
 EQUIPMENT SCHEDULE FOR THE MOTORIZED DAMPER AT THE O/A
 INTAKE FOR THE AHU. A) AN AUTOMATIC SHUTOFF DAMPER IS
 REQUIRED FOR THE O/A SUPPLY FROM THE RTU.
  
 15) PROVIDE SPECIFICATIONS FOR THE GLYCOL AND STEAM
 PIPING AND THE PIPE INSULATIONS.
  
 16) REFER TO SECTION 1003.1 AND PROVIDE MANUFACTURER'S
 SPECIFICATIONS FOR THE STEAM KETTLE, THE LIQUOR TANK,
 AND ALL OTHER BREWERY TANKS AND EQUIPMENT.
  
 17) 1.5A) ENLARGE THE PRINT SHOWN UNDER THE BREWERY
 TANKS AND EQUIPMENT- IT IS NOT LEGIBLE.
  
 18) 3.1M: LABEL THE BREWERY TANKS AND EQUIPMENT AND
 PROVIDE WORKING CLEARANCE MEASUREMENTS ON THE PLAN.
  
 19) REFER TO SECTION 401.4 AND VERIFY CLEARANCE
 DISTANCES FOR THE O/A INTAKE ARE IN COMPLIANCE.
  
 20) REFER TO SECTION 401.5 AND INDICATE HOW THE O/A
 INTAKE OPENING WILL BE PROTECTED. SUBMIT A FLL. PRODUCT
 APPROVAL OR MIAMI-DADE NOA FOR A LOUVER IF TO BE USED.
  
 21) PROVIDE DUCT HANGING AND CONNECTION DETAILS PER
 SMACNA STANDARDS AND TABLE C403.2.7.2 FBC-14 ENERGY
 CONSERVATION.
  
 22) SHEET 3.4M: REFER TO SECTION 304.11 AND PROVIDE
 GUARDS AT THE ROOF EDGES IN PROXIMITY OF THE ACCU AND
 CHILLER.
  
 23) 3.4M: ROOFTOP MECHANICAL INSTALLATION DETAILS ARE
 PROVIDED FOR BOTH BAR JOIST AND CONCRETE DECK- PLEASE
 CLARIFY THIS CONFLICT, AND PROVIDE COMPLETE WIND DESIGN
 CRITERIA PER SECTION 1609 FBC-14 BUILDING. SUBMIT A
 FLORIDA PRODUCT APPROVAL OR MIAMI-DADE NOA FOR THE ROOF
 STAND WITH APPLICABLE INSTALLATION DETAILS, ANCHORS,
 DESIGN PRESSURES ETC. CIRCLED HIGHLIGHTED, OR OTHERWISE
 MARKED BY THE ENGINEER OF RECORD.
  
 CHRISTOPHER L. COLE
 MECHANICAL PLANS EXAMINER
 561-805-6719
 [email protected]
  