| 2017-03-10 15:21:42 | 1) THE ARCHITECTURAL PLANS CONTAIN COPIES OF THE |
| | REQUIRED SIGNATURE AND SEAL AND DO NOT COMPLY WITH |
| | F.A.C. RULE 61G1- 16.001, 61G1-16.003. |
| | 2) SHT. F-2 - THE HOSE BIBB SHALL BE EQUIPPED WITH A |
| | SHUTOFF VALVE AND A VACUUM BREAKER. 2014 FBC SEC.606.2, |
| | 608.15.4. |
| | 3) INDICATE ON THE PLANS WHERE THE FLOOR DRAIN IN THE |
| | PUMP ROOM DISCHARGES. THE FLOOR DRAIN SHALL DISCHARGE |
| | TO THE SANITARY AND BE EQUIPPED WITH A TRAP PRIMER.2014 |
| | FBC SEC.1002.4. SUBMNIT SANITARY RISER DIAGRAM AND ALSO |
| | A WATER RISER DIAGRAM FOR ANY AND ALL DOMESTIC WATER |
| | PIPING AND SANITARY DRAIN PIPING FOR THIS PROJECT. WPB |
| | AMEND. TO FBC SEC. 107.2.1. |
| | 4) SHT. F-3 - THE FEATURE PUMP CURVE TEXT INDICATES A 6 |
| | INCH SUCTION AND A 5 INCH DISCHARGE FOR THE MARLOW |
| | SERIES 530 SC 5-9 FEATURE DISCHARGE PUMP BUT THE PLAN |
| | VIEW ON SHT. F-2 AND SHT. F-4 SHOWS AN 8 INCH DISCHARGE |
| | AND SUCTION. CLARIFY. |
| | 5) SUBMIT MANUF. SPECIFICATION SHEETS FOR THE AQUASTAR |
| | CHANNEL DRAIN. WPB AMEND. TO 2014 FBC SEC. 107.2.1. |
| | 6) THE AUTO FILL SHALL BE EQUIPPED WITH AN APPROVED |
| | BACKFLOW PREVENTION DEVICE. 2014 FBC- PLUMBING, SEC. |
| | 608.13, 608.15. |
| | 7) SHT. F-4 - PLACE A NOTE / DETAILS ON THE PLANS AS TO |
| | HOW THE PIPE SUPPORTS WILL BE SECURED TO THE SUBSTRATE |
| | AND THE SPACING OF SAID SUPPORTS. WPB AMEND. TO FBC |
| | SEC. 107.2.1. |
| | 8) SUBMIT FILTRATION RATES / CALCULATIONS FOR THE |
| | SYSTEM. |
| | |