| Plan Review Notes For Permit 16110549 |
| Permit Number |
16110549 |
|
| Review Stop |
M |
| Sequence Number |
1 |
|
| Notes |
| Date |
Text |
| 2016-11-21 08:58:37 | 1ST REVIEW FBC-2014 MECHANICAL | | | PERMIT #16110549 | | | 11/21/16 | | | | | | 1) CLARIFY HOW HEAT IS BEING PROVIDED TO THE NEW | | | OFFICES. THE VAV BOX SCHEDULE DOES NOT INDICATE ANY | | | HEATER CAPACITIES. | | | | | | 2) THE DESIGN INSTALLATION AC CONTRACTOR- ALTMAN | | | BROTHERS MUST SUBMIT A SUB-PERMIT APPLICATION FOR THE | | | PROPOSED PROJECT- SECTION 105.3.1.2 FBC-14 BUILDING. | | | | | | CHRISTOPHER L. COLE | | | MECHANICAL PLANS EXAMINER | | | 561-805-6719 | | | [email protected] | | | |
|