Plan Review Notes
Plan Review Notes For Permit 16110067
Permit Number 16110067
Review Stop G
Sequence Number 2
Notes
Date Text
2017-01-04 11:29:421) SHT.P4.1 - A LISTED SHUTOFF VALVE SHALL BE INSTALLED
 IMMEDIATELY AHEAD OF EACH MP REGULATOR. A SHUTOFF VALVE
 SHALL BE LOCATED BETWEEN THE GAS METER AND THE NEW
 REGULATOR. 2ND REQUEST. FBC FUEL GAS SEC.409.4.
 2) SHT. P4.1 - SHOW THE CORRECT DISTANCE FROM THE NEW
 GAS REGULATOR TO THE MOST REMOTE OUTLET ON THE SYSTEM
 WHICH APPEARS TO BE THE GENERATOR. THE PLANS NOTE THE
 LONGEST RUN OF GAS PIPING FROM THE NEW GAS REGULATOR TO
 THE MOST REMOTE GAS OUTLET AS 195 FEET. THE FOLLOWING
 LENGTHS OF PIPE MEASUREMENTS SHOWN ON THE PLANS TO THE
 MOST REMOTE GAS OUTLET ARE AS FOLLOWS:
 3' + 5' + 15'- 6" + 56' +140' + 15'- 6" +3' . PLEASE
 EXPLAIN HOW THIS EQUALS 195 FEET WHEN I CALCULATE 238
 FEET. 2ND REQUEST.2014 FBC-FUEL GAS SEC.402.4.1. A
 COMPREHENSIVE GAS REVIEW CANNOT BE PERFORMED UNTIL THE
 CORRECT DISTANCE IS PROVIDED AND THE PLANS ARE
 CORRECTED. IF THE DISTANCE IS 238 FEET THE ENTIRE GAS
 SYSTEM IS UNDERSIZED FOR GALVANIZED PIPE. SIZE ALL
 SECTIONS OF THE GAS RISER IN ACCORDANCE WITH THE
 APPLICABLE SIZING TABLES IN THE FUEL GAS CODE.
 3) SHT. P4.1 - THE GAS RISER STILL SHOWS THE
 UNDERGROUND PIPE AS GALVANIZED ( LABELED "G") BUT THE
 TEXT STATES THE UNDERGROUND PIPE TO BE PE. CLEARLY
 IDENTIFY THE TYPE OF PIPING IN THE DIFFERENT AREAS ON
 THE GAS RISER. 2ND REQUEST. 2014 FBC-FUEL GAS
 SEC.404.11.
 4) SUBMIT CALCULATIONS FOR COMBUSTION AIR FOR THE
 KITCHEN EQUIPMENT AND ALL OTHER GAS APPLIANCES /
 EQUIPMENT PER THE 2014 FBC-FUEL GAS SEC.304.1.WHERE
 COMBUSTION AIR IS PROVIDED BY THE BUILDING'S MECHANICAL
 VENTILATION SYSTEM, THE SYSTEM SHALL PROVIDE THE
 SPECIFIED COMBUSTION AIR RATE IN ADDITION TO THE
 REQUIRED VENTILATION AIR. 2014 FBC-FUEL GAS SEC.
 304.9.3.THE CODE SECTION YOUR DESIGN IS BASED UPON
 REFERS TO THE SUPPLY OF COMBUSTION AIR BY MEANS OF A
 FAN/BLOWER THAT RUNS WHEN ANY OF THE SERVED APPLIANCES
 ARE IN A FIRING CYCLE. HOW ARE TRANSFER GRILLS AND
 DUCTS MEETING THIS REQUIREMENT?
 5) SUBMIT A DETAIL SHOWING THE TYPE, SIZE, LOCATION AND
 TERMINATION OF GAS VENTS PER 2014 FBC-FUEL GAS SECS.
 502 THRU 505. THIS HAS NOT BEEN DONE. 2ND REQUEST.
 6) SHOW THE EMERGENCY SHUT DOWN VALVE AND THE MANUAL
 SHUTOFF VALVE FOR THE GAS TO THE GAS COOKING APPLIANCES
 IN THE KITCHEN. THE LOCATION OF THE EMERGENCY SHUT DOWN
 AND THE MANUAL ACTIVATION VALVE SHALL BE LOCATED IN
 ACCORDANCE WITH NFPA 96-08 SECS. 10.4 & 10.5. 2ND
 REQUEST. THE EMERGENCY SHUT DOWN VALVE SHALL BE LOCATED
 BELOW THE CEILING AND THE MANUAL SHUTOFF VALVE SHALL BE
 UPSTREAM OF THE EMERGENCY SHUT DOWN VALVE WITH A UNION
 LOCATED DOWNSTREAM OF THE MANUAL VALVE. THESE ITEMS
 SHALL BE SHOWN ON THE GAS PLAN. 2ND REQUEST.
 7) APPLIANCES AND SUPPORTS THAT ARE EXPOSED TO WIND
 SHALL BE DESIGNED AND INSTALLED TO RESIST THE WIND
 PRESSURES DETERMINED IN ACCORDANCE WITH THE FLORIDA
 BUILDING CODE, BUILDING. SUBMIT WIND LOAD ANCHORING
 DETAILS FOR THE GENERATOR. 2ND REQUEST.
 8) SHOW THE GAS PIPING TO THE WATER HEATER ON SHT.
 P3.0.
 9) ARE THE DRYERS LOCATED IN ROOM #118 GAS OR ELECTRIC?
 IF GAS, SHOW THE DRYERS AND THE BTU LOAD OF EACH ONE ON
 THE GAS RISER, SUBMIT COMBUSTION AIR CALCULATIONS AND
 DETAILS ON THE VENTS.WPB AMEND. TO FBC SEC. 107.2.1.
 10) THE PLUMBING PLANS SHALL BE SIGNED AND SEALED BY
 THE DESIGN PROFESSIONAL OF RECORD PER THE FL. ADMIN.
 CODE RULE 61G15-23.001. THE SUBMITTED PLANS ARE COPIES
 OF THE SEAL AND SIGNATURE. 2ND REQUEST.
  
 TIM LARGE
 CHIEF PLUMBING INSPECTOR
 PLUMBING PLAN REVIEW
 561-805-6692
 [email protected]
  
  