| 2016-11-09 12:17:08 | 1ST REVIEW FBC-2014 MECHANICAL |
| | PERMIT #16110067 |
| | 11/9/16 |
| | |
| | 1) PROVIDE AC COOLING AND HEATING CALCULATIONS FOR |
| | RTU-1. IT APPEARS THAT HP-1 & 2 WERE SIZED USING ONLY |
| | THE SENSIBLE COOLING LOADS SHOWN IN THE SUMMARY |
| | CALCULATIONS, AND NO HEATING LOAD CALCS ARE SHOWN. |
| | |
| | 2) ENERGYGAUGE COMPLIANCE FORM: A) PROVIDE COMPLIANCE |
| | DATA FOR RTU-1. B) THE OWNER/AGENT MUST SIGN THE FORM- |
| | SEE PAGE 3. |
| | |
| | 3) SHEETS M1 & M1.1: PLACE THE #3 KEYED NOTE AT EACH |
| | FIRE DAMPER LOCATION. PLEASE CLARIFY WHY FIRE DAMPERS |
| | ARE BEING INSTALLED AT DUCT PENETRATIONS INTO THE |
| | CORRIDOR SMOKE PARTITIONS- SEE SHEET A1.1 AND SECTION |
| | 607.5.7. WHERE REQUIRED SMOKE DAMPERS SHALL BE |
| | INSTALLED IN SMOKE PARTITIONS. |
| | |
| | 4) REFER TO SECTION 606.2.1- 606.2.2 AND PROVIDE DUCT |
| | SMOKE DETECTORS IN ALL RETURN AIR SYSTEMS OR AREA SMOKE |
| | DETECTORS THAT ARE CONNECTED TO THE FIRE ALARM. PLEASE |
| | NOTE THAT FIRE ALARM PLANS MUST BE SUBMITTED UNDER |
| | SEPARATE PERMIT, HOWEVER THE SMOKE DETECTORS MUST BE |
| | SHOWN ON BOTH SETS OF PLANS. |
| | |
| | 5) M1.& M1.1: PLACE THE KEYED NOTE #9 AT EACH FAN COIL |
| | LOCATION AND PROVIDE A CONDENSATE DISPOSAL PLAN PER |
| | SECTION 307. SHOW THE PIPING RUNS, TYPE AND SIZES OF |
| | PIPINGS, AND DISCHARGE LOCATIONS. |
| | |
| | 6) M1 & M1.1: PLACE THE KEYED NOTE #11 AT EACH |
| | REFRIGERATION DISTRIBUTION BOX SHOWN ON THE PLAN AND |
| | INDICATE HOW ACCESS WILL BE PROVIDED TO THE BOX. |
| | |
| | 7) M1.1: SHOW THE DRYER EXHAUST DUCT RUNS AND PROVIDE |
| | DETAILS INCLUDING TYPES AND SIZES OF DUCTS, THE DUCT |
| | RUN LENGTHS AND TERMINATION LOCATIONS- SEE SECTION 504. |
| | A) PROVIDE MAKEUP AIR AND CALCULATIONS. B) SUBMIT |
| | MANUFACTURER'S SPECIFICATIONS AND PROVIDE AN EQUIPMENT |
| | SCHEDULE ON THE PLAN. C) INDICATE THE EXHAUST CFMS IN |
| | THE PRESSURIZATION CALCULATIONS ON M3.3. |
| | |
| | 8) INDICATE HOW COMBUSTION AIR WILL BE PROVIDED FOR THE |
| | COOKING APPLIANCES AND PROVIDE CALCULATIONS- SECTION |
| | 304 FBC-14 FUEL GAS. |
| | |
| | 9) M4: REFER TO SECTION 403.2.4.4 FBC-14 ENERGY |
| | CONSERVATION: IT APPEARS THAT THE CONTROL SEQUENCE FOR |
| | RTU-1 O/A IS NOT IN COMPLIANCE BECAUSE THE DAMPERS WILL |
| | REMAIN OPEN WHEN THE BUILDING IS UNOCCUPIED. |
| | |
| | 10) REFER TO SECTION 301.15 AND PROVIDE WIND LOAD |
| | ENGINEERING FOR ANCHORING THE RTU AND HP-1 & 2. PLEASE |
| | INCLDUE THE DESIGN CRITERIA AS OUTLINED IN SECTUION |
| | 1609 FBC-14 BUILDING. |
| | |
| | CHRISTOPHER L. COLE |
| | MECHANICAL PLANS EXAMINER |
| | 561-805-6719 |
| | [email protected] |
| | |