Plan Review Notes
Plan Review Notes For Permit 16100663
Permit Number 16100663
Review Stop M
Sequence Number 1
Notes
Date Text
2016-11-01 11:01:181ST REVIEW FBC-2014 MECHANICAL, EXISTING BUILDING CODES
 PERMIT #16100663
 11/1/16
  
 1) DESIGN CRITERIA: PROVIDE ON THE PLAN A LIST OF
 CURRENT CODE REFERENCES AND STANDARDS USED IN THE
 DESIGN OF THE PROJECT.
  
 2) THE MECHANICAL PLANS MUST BE DESIGNED BY A FLORIDA
 LICENSED ENGINEER PER FLORIDA STATUTE 471.003. THE SEAL
 ON THE PLANS INDICATES THE DESIGNER HAS A "CERTIFICATE"
 BUT IS NOT LICENSED.
  
 3) REFER TO SECTION C408.2 FBC-14 ENERGY CONSERVATION-
 AC SYSTEM COMMISSIONING IS REQUIRED.
 C408.2 MECHANICAL SYSTEMS COMMISSIONING AND COMPLETION
 REQUIREMENTS.
 PRIOR TO PASSING THE FINAL MECHANICAL INSPECTION, THE
 REGISTERED DESIGN PROFESSIONAL SHALL PROVIDE EVIDENCE
 OF MECHANICAL SYSTEMS COMMISSIONING AND COMPLETION IN
 ACCORDANCE THE PROVISIONS OF THIS SECTION.
 CONSTRUCTION DOCUMENT NOTES SHALL CLEARLY INDICATE
 PROVISIONS FOR COMMISSIONING AND COMPLETION
 REQUIREMENTS IN ACCORDANCE WITH THIS SECTION AND ARE
 PERMITTED TO REFER TO SPECIFICATIONS FOR FURTHER
 REQUIREMENTS. COPIES OF ALL DOCUMENTATION SHALL BE
 GIVEN TO THE OWNER AND MADE AVAILABLE TO THE CODE
 OFFICIAL UPON REQUEST IN ACCORDANCE WITH SECTIONS
 C408.2.4 AND C408.2.5.
  
 2A) C408.2.1 COMMISSIONING PLAN.
 A COMMISSIONING PLAN SHALL BE DEVELOPED BY A REGISTERED
 DESIGN PROFESSIONAL OR APPROVED AGENCY AND SHALL
 INCLUDE THE FOLLOWING ITEMS:
  
 1. A NARRATIVE DESCRIPTION OF THE ACTIVITIES THAT WILL
 BE ACCOMPLISHED DURING EACH PHASE OF COMMISSIONING,
 INCLUDING THE PERSONNEL INTENDED TO ACCOMPLISH EACH OF
 THE ACTIVITIES.
 2. A LISTING OF THE SPECIFIC EQUIPMENT, APPLIANCES OR
 SYSTEMS TO BE TESTED AND A DESCRIPTION OF THE TESTS TO
 BE PERFORMED.
 3. FUNCTIONS TO BE TESTED, INCLUDING, BUT NOT LIMITED
 TO CALIBRATIONS AND ECONOMIZER CONTROLS.
 4. CONDITIONS UNDER WHICH THE TEST WILL BE PERFORMED.
 AT A MINIMUM, TESTING SHALL AFFIRM WINTER AND SUMMER
 DESIGN CONDITIONS AND FULL OUTSIDE AIR CONDITIONS.
 5. MEASURABLE CRITERIA FOR PERFORMANCE.
  
 4) SITE SPECIFIC WIND LOAD ENGINEERING IS REQUIRED FOR
 INSTALLATION OF THE ROOF TOP AC EQUIPMENT PER SECTION
 301.15 FBC-14 MECHANICAL. PROVIDE ON THE PLAN THE WIND
 LOAD DESIGN CRITERIA AND COMPLETE DETAILS FOR ANCHORING
 THE ACCU'S AND OSA FAN TO THE ROOF STRUCTURE.
  
 5) REFER TO SECTION 102.8 FBC-14 BUILDING: ALL NEW AND
 REPLACED MECHANICAL EQUIPMENT MUST BE RAISED ABOVE THE
 ROOF SURFACE AT THE CLEARANCE HEIGHTS SPECIFIED IN
 TABLE 1522.3. PROVIDE DETAILS ON THE PLAN TO INDICATE
 COMPLIANCE.
  
 6) REFER TO SECTION 702.4 FBC-14 EXISTING BUILDING AND
 VERIFY THAT ALL MECHANICAL ROOFTOP EQUIPMENT IS NOT
 LOCATED WITHIN 10' OF ANY ROOF EDGE THAT DOES NOT HAVE
 A GUARD OR PARAPET AT A MINIMUM HEIGHT OF 42"- SEE
 SECTION 304.11 FBC-14 MECHANICAL.
  
 CHRISTOPHER L. COLE
 MECHANICAL PLANS EXAMINER
 561-805-6719
 [email protected]
  