| 2016-10-31 12:45:33 | 1) CLEARLY SHOW WHERE THE POOL WASTE DISCHARGES. POOL |
| | WATER SHALL NOT DISCHARGE TO THE CITY'S SANITARY SYSTEM |
| | OR TO THE STORM SYSTEM PER THE CITY OF WEST PALM BEACH |
| | CODE OF ORDINANCES ART.III, SEC.90-126 (B)(5) AND |
| | ART.V, SEC.90-203. |
| | 2) THE EQUALIZER LINE INLET SHALL BE PROTECTED BY AN |
| | ASME/ANSI A112.19.8 COMPLIANT COVER/GRATE PER 2014 FBC |
| | SEC.454.1.6.5.3.2.3. |
| | 3) THE FILTER RATE CAPACITY FOR THE CARTRIDGE FILTERS |
| | SHALL COMPLY WITH 2014 FBC SEC.454.1.6.5.5.1. |
| | 4) PRESSURE FILTER SYSTEMS SHALL COMPLY WITH 2014 FBC |
| | SEC.454.1.6.5.5.2.1. SUBMIT DETAILS OF THE CARTRDGE |
| | FILTERS. |
| | 5) A PORTABLE OR PLUMBED IN VACUUM CLEANING SYSTEM |
| | SHALL BE PROVIDED AND COMPLY WITH 2014 FBC |
| | SEC.454.1.6.5.12.SUBMIT DETAILS. |
| | 6) SUBMIT MANUFACTURER'S SPECIFICATIONS ON THE POOL |
| | HEATERS. WPB AMEND. TO FBC SEC.107.2.1. |
| | 7) SHT. CP4.0 - SHOW THE DISTANCE BETWEEN THE RECESSED |
| | TREADS FOR THE LADDER. COMPLY WITH 2014 FBC |
| | SEC.454.1.2.5.2. |
| | 8) GAS FIRED POOL HEATERS SHALL HAVE A MINIMUM THERMAL |
| | EFFICIENCY OF 82 PERCENT PER 2014 FBC-ENERGY, TABLE |
| | C404.2, SEC.C404.7.1. |
| | 9) A TIME SWITCH OR OTHER CONTROL METHOD THAT CAN |
| | AUTOMATICALLY TURN OFF AND ON HEATERS AND PUMPS SHALL |
| | BE INSTALLED ON ALL HEATERS AND PUMPS PER 2014 |
| | FBC-ENERGY, SEC.C404.7.2. |
| | 10) A VAPOR RETARDANT COVER ON OR AT THE SURFACE OR A |
| | LIQUID COVER OR OTHER MEANS PROVEN TO REDUCE HEAT LOSS |
| | SHALL BE PROVIDED ON HEATED POOLS PER 2014 FBC-ENERGY, |
| | SEC.C404.7.3. |
| | 11) EQUIPMENT ROOMS SHALL HAVE FORCED DRAFT OR CROSS |
| | VENTILATION IN ACCORDANCE WITH 2014 FBC SEC.454.1.5.4. |
| | 12) A SEPARATE PERMIT IS REQUIRED FOR THE GAS. |
| | |