| 2017-03-27 10:37:57 | RESIDENTIAL (R3) CHANGE OF USE/ALTERATION MECHANICAL |
| | REVIEW CHECKLIST. |
| | CODE: FBC 5TH EDITION (2014). |
| | |
| | NOTE: |
| | MECHANICAL REVIEW MAY BE APPROVED WITH PROVISO. PROVISO |
| | MEANS THAT CONTRACTOR MAY SUBMIT REQUIRED INFORMATION |
| | AFTER THE PERMIT IS ISSUED BUT BEFORE INSPECTIONS TO |
| | AVOID CONFLICTS/DELAYS. REVISION FEES WILL APPLY. |
| | CONTRACTOR TO ADVICE IF PROVISO OPTION IS PREFERRED AT |
| | THIS TIME OR IF RE-SUBMITTING CORRECT INFORMATION. |
| | |
| | 1- REVISED EQUIPMENT CALCULATIONS FOR THE REAR |
| | STRUCTURE NEEDS TO BE REVISED. SELECTED EQUIPMENT NEEDS |
| | TO BE CHANGED. "THE CORRESPONDING LATENT CAPACITY OF |
| | THE EQUIPMENT SHALL NOT BE LESS THAN THE CALCULATED |
| | LATENT LOAD". SEC. R403.6.1.1 FBC-ENERGY CONSERVATION, |
| | 5TH EDITION (2014). |
| | |
| | 2- EQUIPMENT SHOWN ON DRAWING M1 FOR THE REAR STRUCTURE |
| | DOESN'T MATCH EQUIPMENT SHOWN ON THE REVISED EQUIPMENT |
| | SIZING CALCULATIONS. REVISE AS REQUIRED TO MATCH , |
| | INCLUDING THE SEER. SEC. R403.6.1.1 FBC-ENERGY |
| | CONSERVATION. |
| | |
| | 3- ONLY THE SUMMARY SHEET OF THE EQUIPMENT SIZING |
| | CALCULATIONS WAS SUBMITTED. PROVIDE THE COMPLETE |
| | EQUIPMENT SIZING CALCULATIONS FOR THE MAIN HOUSE AND |
| | FOR THE REAR STRUCTURE. SEC. R403.6.1.1 FBC-ENERGY |
| | CONSERVATION. |
| | |
| | |
| | ****PLEASE PROVIDE RESPONSE LETTER ADDRESSING EACH |
| | COMMENT TO EXPEDITE THE REVIEW PROCESS. |
| | ****PLEASE INSERT ANY REVISED DRAWING AND REMOVE OLD |
| | DRAWING. DON'T STAPLE OLD DRAWINGS. SUBMITT OLD |
| | DRAWINGS FOR REFERENCE. |
| | |
| | IF YOU HAVE ANY QUESTIONS, PLEASE CONTACT |
| | JULIO GOMEZ |
| | COMMERCIAL COMBINATION PLANS EXAMINER |
| | DEVELOPMENT SERVICES DEPARTMENT |
| | BUILDING DIVISION |
| | (561)805-6712 |