| 2016-11-29 16:05:39 | 1ST REVIEW |
| | |
| | GEORGE JOHNSON |
| | PLUMBING PLANS EXAMINER LL |
| | CITY OF WEST PALM BEACH |
| | DEVELOPMENT SERVICES |
| | BUILDING DIVISION |
| | 561-805-6711 |
| | [email protected] |
| | |
| | GAS COMMENTS: |
| | |
| | 1. SUBMIT AN ISOMETRIC DRAWING THAT CLEARLY SHOWS ALL |
| | CUT SECTIONS OF PIPE AND CORRESPONDING LENGTHS PER |
| | FBC-2014 FUEL GAS, SECS. 402.4.1, 402.4.2. |
| | |
| | 2. BTU LOAD OF EACH APPLIANCE AND THE TOTAL BTU LOAD ON |
| | THE SYSTEM. REFER TO THE FBC-2014 FUEL GAS SECS. 401.8 |
| | THRU 402.6.1 AND TABLES 402.4(1) THRU 402.4(37). |
| | |
| | 3. SUBMIT CALCULATIONS FOR COMBUSTION AIR PER THE |
| | FBC-2014 FUEL GAS CODE SEC. 304. |
| | |
| | 4. SUBMIT MANUFACTURER?S SPECIFICATION SHEETS FOR ALL |
| | GAS EQUIPMENT TO VERIFY COMPLIANCE WITH STANDARDS NFPA |
| | 54, NFPA 58, AND FBC-2014 FUEL GAS SEC. 402.2 |
| | |
| | 5.THE PLUMBING FIXTURE SPECS STATE THE GWH AT 237,000 |
| | BTU YOUR SHOWING 7 GWH WITH A TOTAL BTU LOAD OF |
| | 1,659,000 THE NOTE ON THE 2PSI PE PIPING FOR GWH STATES |
| | A TOTAL OF 1,399,000 PLEASE CLARIFY. WPB AMEND TO FBC |
| | 107.2.1 |
| | |
| | 6. IF THE TOTAL BTU LOAD FOR THE HEATERS IS 1,659,00O |
| | THE PE PIPING WOULD NEED TO BE 11/2 TO THE FIRST TEE. |
| | PER FBC FG TABLE 402.4(22) |
| | |
| | 7. THE 2ND SECTION OF PE PIPE IS SHOWN AS 1" IT SHOULD |
| | BE 11/4. PER FBC FG TABLE 402.4(22) |
| | |
| | 8. THE TABLE IN YOUR NOTES ON THE 2PSI PE PIPING RISER |
| | SHOULD BE 402.4(22) NOT 402.4(20). |
| | |
| | 9. THE NOTE ON THE GAS PIPING UPSTREAM OF THE METER IS |
| | NOT NEEDED THAT PIPING IS NOT UNDER THE JURISDICTION OF |
| | THE BUILDING DEPT THAT IS SIZED AND THE PRESSURE |
| | DETERMINED BY THE GAS UTILITIES COMPANY. |
| | |
| | 10. THE NOTE ON THE LESS THAN 2PSI SYSTEM FOR KIT CALLS |
| | OUT 11/4 BUT THE PLAN SHOWS 3/4 PLEASE CLARIFY. PER WPB |
| | AMEND TO FBC 107.2.1 |