| Date |
Text |
| 2016-08-29 10:14:16 | 1ST REVIEW FBC-2014 MECHANICAL |
| | PERMIT #16070916 |
| | ROYAL PALM PLACE-, BUILDING-1 |
| | 8/29/16 |
| | |
| | 1) THE SUBMITTED AC CALCULATION PACKET DOES NOT INCLUDE |
| | THE AHU-A2/CU-2, AHU-A3/CU-3, AHU-B2/CU-2, AHU-5 (TRASH |
| | ROOM) AND AHU-6 (ELEVATOR VESTIBULE) SYSTEMS- PLEASE |
| | PROVIDE. B) THE CALCULATIONS ARE INCORRECTLY INDICATING |
| | MIAMI AS THE LOCATION. B) REVIEW THE AC SCHEDULE ON |
| | M-4.00 AS THE 4-TON SYSTEM AHU-1 SYSTEM DOES NOT MATCH |
| | THE AHU-1 SYSTEM SHOWN ON |
| | |
| | SHEET M-2.00 IN TERMS OF CAPACITY. B) REFER TO SECTION |
| | C403.2.1 FBC-14 ENERGY CONSERVATION: A COOLING AND |
| | HEATING CALCULATION SHALL BE SUBMITTED FOR EACH SYSTEM |
| | SHOWN ON THE PLAN, AND ALL SUMMARY CALCULATIONS |
| | SUBMITTED BY A REGISTERED ENGINEER SHALL BEAR THE |
| | SIGNATURE AND SEAL OF THE ENGINEER. SEE ALSO SECTION |
| | C407.5.2.3 IF SUBMITTING A TOTAL BUILDING PERFORMANCE |
| | ENERGY |
| | |
| | COMPLIANCE METHOD. |
| | |
| | 2) SHEETS M-2.00, M-2.01, & M-400: THE SPLIT AC |
| | SCHEDULE DOES NOT INCLUDE THE AHU-2, AHU-3, AHU-B2, & |
| | AHU-B3 SYSTEMS. |
| | |
| | 3) SHEETS M2.00 & M-2.01: THE EXCEPTION UNDER SECTION |
| | 504.6.1 THAT ALLOWED THE USE OF DRYER BOOSTER FANS HAS |
| | BEEN REMOVED FROM THE FBC-14 MECHANICAL CODE. PLEASE |
| | SUBMIT MANUFACTURER'S SPECIFICATIONS AND EXHAUST VENT |
| | INSTALLATION INSTRUCTIONS. |
| | |
| | 4) THE PROPOSED BUILDING SHALL BE IN COMPLIANCE WITH |
| | THE FBC-14 ENERGY CONSERVATION CODE. REFER TO SECTIONS |
| | C101.2, C101.5, AND C401.2 AND SUBMIT COMPLIANCE |
| | MATERIALS AND FORMS. |
| | |
| | 5) PROVIDE EQUIPMENT SCHEDULES FOR THE APARTMENT |
| | OUTSIDE AIR FANS AND MOTORIZED DAMPERS, AND PROVIDE |
| | CLEARANCE DISTANCE MEASUREMENTS FOR ALL AIR INTAKES- |
| | SECTION 401.4 |
| | |
| | 6) PROVIDE TRASH ROOM AND ELECTRICAL ROOM EXHAUST |
| | VENTILATION CALCULATIONS, AND HOISTWAY VENTING |
| | CALCULATIONS. |
| | |
| | 7) PROVIDE A REFRIGERANT PIPING RISER AND INCLUDE |
| | PIPING DETAILS- TYPES AND SIZES, TOTAL ALLOWABLE |
| | LENGTHS PER THE MANUFACTURER SPECIFICATIONS, AND TYPE |
| | AND THICKNESSES OF PIPE INSULATIONS. |
| | |
| | 8) PROVIDE UL FIRESTOPPING ASSEMBLIES FOR PIPE |
| | PENETRATIONS. |
| | |
| | 9) WIND LOAD DESIGN FOR ROOTOP MECHANICAL EQUIPMENT: |
| | THE CU MOUNTING DETAIL ON M-3.00 IS INDICATING AN |
| | INCORRECT WIND SPEED OF150 MPH. PLEASE PROVIDE CURRENT |
| | WIND LOAD DESIGN CRITERIA ON THE PLAN, AND SUBMIT THE |
| | MIAMI-DADE NOA #13-1017.09 LISTED IN THE DETAIL. PLEASE |
| | NOTE THE EOR SHALL PLACE HIS SHOP DRAWING APPROVAL |
| | STAMP AND SIGNATURE ON THE NOA AND ALL OTHER |
| | |
| | NOAS, PRODUCT APPROVALS, OR MANUFACTURER'S |
| | SPECIFICATIONS SUBMITTED AS PART OF THE PERMIT PACKAGE- |
| | INCLUDING THE GREENHECK MOTORIZED DAMPER AND LOUVER FOR |
| | THE HOISTWAY, AND ALL OTHER OUTSIDE AIR INTAKE AND |
| | EXHAUST OUTLET LOUVERS. |
| | |
| | 10) REFER TO SECTION 306.5 AND PROVIDE DETAILS FOR THE |
| | LADDER THAT IS PROVIDING ACCESS TO THE ROOF HATCH. |
| | |
| | 11) REFER TO SECTION 3006.2 FBC-14 BUILDING AND CLARIFY |
| | IF THERE IS AN ELEVATOR MACHINE ROOM, AND PROVIDE AN |
| | INDEPENDENT VENTILATION OR AIR CONDITIONING SYSTEM. THE |
| | PLANS SHOW AN ELEVATOR VESTIBULE BUT NO EQUIPMENT IS |
| | SHOWN IN THE ROOM. |
| | |
| | CHRISTOPHER L. COLE |
| | MECHANICAL PLANS EXAMINER |
| | 561-805-6719 |
| | [email protected] |
| | |
| | |
| | |
| | |