| 2017-01-13 15:50:45 | MECHANICAL PROVISOS: |
| | PERMIT #16070715 |
| | 1/13/17 |
| | |
| | 1) REVISE SHEETS M204, M206, M208, M502, M503, M504, |
| | M505, M506, M507, & M601 TO SHOW ALL OUTSIDE AIR DUCT |
| | RUNS AND REQUIRED AUTOMATIC SHUTOFF DAMPERS. |
| | |
| | 2) PROVIDE REFRIGERANT PIPING RISER DIAGRAMS FOR THE |
| | SPLIT AC SYSTEMS |
| | |
| | 3) FINAL COMMISSIONING REPORT: |
| | A REPORT OF TEST PROCEDURES AND RESULTS IDENTIFIED AS |
| | "FINAL COMMISSIONING REPORT" SHALL BE DELIVERED TO THE |
| | BUILDING OWNER AND SHALL INCLUDE: |
| | 1. RESULTS OF FUNCTIONAL PERFORMANCE TESTS. |
| | 2. DISPOSITION OF DEFICIENCIES FOUND DURING TESTING, |
| | INCLUDING DETAILS OF CORRECTIVE MEASURES USED OR |
| | PROPOSED. |
| | 3. FUNCTIONAL PERFORMANCE TEST PROCEDURES USED DURING |
| | THE COMMISSIONING PROCESS INCLUDING MEASURABLE CRITERIA |
| | FOR TEST ACCEPTANCE, PROVIDED HEREIN FOR REPEATABILITY. |
| | EXCEPTION: DEFERRED TESTS WHICH CANNOT BE PERFORMED AT |
| | THE TIME OF REPORT PREPARATION DUE TO CLIMATIC |
| | CONDITIONS. |
| | |
| | 4) PROVIDE A SIGNED AND SEALED COPY OF THE SMOKE |
| | CONTROL SYSTEM RATIONAL ANALYSIS BY JAMES S. LUKE P.E. |
| | COMMISSIONING OF THE SMOKE CONTROL SYSGTEMS REQUIRED AT |
| | FINAL INSPECTION. |
| | |
| | 5) SEPARATE PERMITS ARE REQUIRED FOR FIRE SPRINKLER, |
| | FIRE SUPPRESSION, KITCHEN HOOD EXHAUST SYSTEMS, AND |
| | WALK-IN COOLERS AND FREEZERS. |
| | |
| | 6) REQUIRED SUBMITTALS: |
| | A) STAIRWAY PRESSURIZATION FANS. |
| | B) CORRIDOR EXHAUST FAN. |
| | C) SMOKE EXHAUST DUCTWORK. |
| | D) FIRE/SMOKE AND FIRE DAMPERS. |
| | E) WINDLOAD ENGINEERING FOR INSTALLATION OF ALL ROOFTOP |
| | MECHANICAL EQUIPMENT, CURBS, STANDS, |
| | DUCTS, AND SUPPORTS |
| | F) MOTORIZED DAMPERS. |
| | G) OUTSIDE AIR AND EXHAUST LOUVERS AND TERMINATION |
| | CAPS. |
| | |
| | CHRISTOPHER L. COLE |
| | MECHANICAL PLANS EXAMINER |
| | 561-805-6719 |
| | [email protected] |
| | |
| | |
| | |